Tata Power Renewable Energy Limited (TPREL) has commissioned a 126 MW Omkareshwar floating solar project in the Khandwa district of Madhya Pradesh.
The Rs 5.96 billion engineering, procurement, and construction (EPC) project was awarded by NHDC Limited and will supply power to the Madhya Pradesh Power Transmission Company Limited (MPPTCL).
Completed within 26 months, this installation is among India’s largest floating solar projects, marking a significant milestone in the country’s renewable energy sector.
With this addition, TPREL’s total renewable energy capacity has reached 10.9 GW, including 5.6 GW of projects under various stages of implementation. The company’s operational capacity now stands at 5.3 GW, comprising 4.3 GW of solar and 1 GW of wind energy projects.
Author: PPD Team Date: January 29, 2026 ACME Group has signed a partnership with the Industrial Promotion and Investment Corporation of Odisha Limited (IPICOL) to develop a 200 kilo tonnes per annum green methanol manufacturing facility in Kendrapada district. The project will be implemented through ACME Akshya Energy and is expected to generate more than 1,100 jobs, marking the first large-scale green methanol initiative in the state. The IPICOL will facilitate the project, which forms…
Author: PPD Team Date: February 19, 2026 CleanMax Enviro Energy has fixed a price band of Rs 1,000 to Rs 1,053 per share for its initial public offering (IPO). The issue will open for subscription on February 23, 2026, and close on February 25, marking a listing focused on the private-sector renewable energy market. The IPO comprises a fresh issue of shares worth up to Rs 1,200 crore and an offer-for-sale (OFS) of up to…
Author: PPD Team Date: December 11, 2024 The Expert Appraisal Committee (EAC) of the Ministry of Environment, Forest and Climate Change (MoEFCC) has recommended the granting of Terms of Reference (ToR) for the 1,200 MW Sikaser Open Loop Pumped Storage Hydro-electric Project in Chhattisgarh in its latest meeting. The project is being developed by Chhattisgarh State Power Generation Company Limited (CSPGCL) near Sikaser village in Gariyaband district. The Rs Rs 5,118.03 billion project spans 160…
Author: PPD Team Date: November 27, 2024 Orient Solar has announced plans to increase its production capacity from 800 MW to 2 GW by mid-2025. This expansion involves an investment of Rs 1.30 billion, covering capital expenditure, land, and building costs. The enhanced capacity will primarily support utility-scale solar projects (65%), with the remaining 35% allocated to commercial and industrial rooftop solar projects, as well as solar street lights and pumps.
Author: PPD Team Date: April 15, 2025 Iraq has signed three memoranda of understanding (MoUs) with US entities to develop large-scale energy projects for reducing dependence on Iranian imports and diversifying its power sources. The Iraqi prime minister’s media office announced the agreements as part of the country’s broader energy strategy. Under the first MoU, GE Vernova will develop combined-cycle gas power plants with a total capacity of 24 GW. This is expected to be…
Author: PPD Team Date: February 6, 2026 Suzlon Energy Limited reported a consolidated net profit of Rs 445 crore for the third quarter ended December 31, 2025, an increase of 14.7% compared with the same period last year. Revenue rose 42% year on year to Rs 4,228 crore, supported by the company’s highest ever quarterly deliveries of 617 MW. Earnings before interest, tax, depreciation and amortisation (EBITDA) increased 48% to Rs 739 crore during the…