Shakti Pumps commits Rs 75 crore to 2.2 GW solar manufacturing project
Author: PPD Team Date: January 19, 2026
Author: PPD Team Date: January 19, 2026
Shakti Pumps (India) Limited has approved an equity investment of Rs 75 crore in its wholly owned subsidiary, Shakti Energy Solutions Limited (SESL), to set up a 2.2 GW solar cell and module manufacturing facility in Madhya Pradesh. The investment marks a significant increase from the earlier proposal and advances the greenfield project.
In a regulatory disclosure, the company stated that the funds will be used to establish a high efficiency Solar Domestic Content Requirement (DCR) cell and Solar Photovoltaic (PV) module manufacturing plant at Pithampur. The revised investment of Rs 75 crore is substantially higher than the Rs 3 crore intent disclosed last week, reflecting the project’s scale-up.
The proposed facility forms part of Shakti Pumps’ wider expansion plan, which includes a capital expenditure programme of Rs 17,000 million to double its pump and motor manufacturing capacity by mid-2026. The move into solar cell and module manufacturing is aimed at securing internal supply while addressing rising demand in the renewable energy market.
SESL, which will receive the investment, is already engaged in the manufacture of solar structures and rooftop solutions. The subsidiary reported a turnover of Rs 216.53 crore in FY25. Shakti Pumps clarified that the investment is not a related party transaction and does not require any additional regulatory approvals.
Author: PPD Team Date: December 16, 2024 Vestas has received a firm and unconditional order for the 1.1GW Inch Cape offshore wind project in Scotland from Inch Cape Offshore, a joint venture between ESB and Red Rock Renewables. The contract includes the supply, installation, and commissioning of 72 V236-15.0 MW wind turbines. The 150km² site in the North Sea, located 15km offshore Angus, will feature turbines installed on monopile and jacket foundations in water depths…
Author: PPD Team Date: November 28, 2025 Tata Power Company Ltd has outlined a plan to set up a 10 GW ingot and wafer manufacturing facility in Odisha with an investment of Rs 10000 crore. The project is intended to expand the company’s solar manufacturing base and support its upstream supply chain. The company said ingots and wafers serve as core inputs for solar cells, solar modules and semiconductor chips. Tata Power’s existing cell and…
Author: PPD Team Date: January 9, 2026 The Tata Power Company Limited has announced the commissioning of a major transmission infrastructure project in Uttar Pradesh, strengthening the regional power network. The project involves the 400 / 220 kV Metro Depot Substation and associated transmission lines in Greater Noida, adding 1,000 MVA of transformation capacity to meet rising electricity demand in the region. The newly commissioned system is designed to support power requirements in Greater Noida…
Author: PPD Team Date: January 19, 2026 KPI Green Energy Limited has secured orders for the Balance of System (BoS) package for a 534 MW solar power cluster at Khavda in Gujarat. The contracts, covering supply and onsite services, were awarded by Adani Green Energy Limited and Adani Green Energy Six Limited. In its regulatory filing, KPI Green Energy stated that the BoS scope is split into two distinct orders. The supply order includes manufacturing,…
Author: PPD Team Date: October 30, 2024 Greenzo Energy has introduced the “Un Wheel,” a 100% indigenous 1 MW alkaline electrolyzer stack designed for green hydrogen production. Built by Indian scientists and engineers, the stack is tailored to operate effectively across diverse Indian climates, from -20°C to 60°C, with a 20-year lifespan. It generates hydrogen at 30 bar pressure, removing the need for additional compressors, and features advanced controls for water quality, pressure, and lye…
Author: PPD Team Date: September 11, 2025 The Central Electricity Regulatory Commission (CERC) has issued a draft order proposing changes to the way deviations for wind and solar generators are calculated under the Deviation Settlement Mechanism (DSM). The new approach will come into effect from April 1, 2026. The DSM Regulations, 2024, notified last year, already provide for a reduction in tolerance bands. For solar and hybrid projects, the permissible deviation will move from ±10…