ISTS waiver extended for RE projects delayed by transmission gaps
The Ministry of Power issued an Office Memorandum on April 16, 2026, clarifying the conditions under which renewable energy (RE) projects can continue to avail the graded waiver of Inter-State Transmission System (ISTS) charges where commissioning has been delayed due to non-readiness of transmission infrastructure. The memorandum follows representations from RE developers seeking clarity on whether projects with a firm start date of connectivity between July 1, 2025 and June 30, 2028 would retain the…