Power Bytes

Power Sector News Roundup for February 23, 2026

Author: PPD Team Date: February 23, 2026

CEA panel finds 55% MTL flexible operation does not damage thermal units

A committee constituted by the Central Electricity Authority (CEA) found that operating thermal power plants at 55% minimum technical load (MTL) with conservative ramping rates does not result in significant damage to generating units. The report, based on meetings held between July and October 2025, noted NTPC’s reluctance to participate in mandated pilot projects for two-shift operation, delaying development of a compensation framework. GRID-INDIA reported that most inter-state generating stations and several state stations have technically achieved 55% MTL, though commercial and regulatory barriers persist. Analysis of Farakka Unit-2 and Jhajjar Unit-3 showed no evidence linking significant damage to 55% MTL operation, with about 70% of issues attributed to ageing, coal quality or operational disturbances. The committee recommended pilot studies on smaller and older 210 MW units and measures to achieve 40% MTL through retrofits, improved operational practices and updated technical specifications.

CAG audit flags operational gaps and revenue losses at NLC India

A performance audit by the Comptroller and Auditor General of India (CAG) identified operational, financial and compliance gaps at NLC India Limited’s lignite mines and thermal stations in Neyveli during 2017-18 to 2022-23. Land shortages left only 46.19 hectares available for active mining, causing a supply gap of 2.77 million tonnes and a potential revenue loss of Rs 338.62 crore, while extraction from overburden dump areas increased costs by Rs 364.80 crore. The audit reported environmental clearance lapses, overburden dump height violations, ageing equipment and delayed energy audits deferring potential annual savings of Rs 47.92 crore. Thermal station issues led to under-recovery of capacity charges of Rs 2,353.99 crore, generation loss of 1,594.77 million units and additional cost pressures including Rs 248.99 crore operation and maintenance expenditure above regulatory limits. CAG recommended faster land acquisition, slope monitoring systems, maintenance improvements, FBHE modifications, adequate lignite storage, manpower rationalisation and expediting Flue Gas Desulphurization (FGD) implementation.

KPI Green Energy completes 92.4 MW wind project in Gujarat

KPI Green Energy Limited completed a 92.4 MW wind power project for Ayana Renewable Power Four at Nakhatrana in Bhuj, Gujarat. The milestone was disclosed in a stock exchange filing stating that the project secured approval from the Central Electricity Authority (CEA). The project comprises 28 wind turbine generators, with KPI Green Energy executing the full scope including balance of plant, power substation development, extra high voltage (EHV) transmission line installation and erection and commissioning of all turbines. The facility adds to India’s renewable energy capacity and contributes to expansion of clean power generation infrastructure.

NTPC Green declares 165 MW commercial at Khavda-II solar project

NTPC Green Energy Limited (NGEL) declared commercial operation of 165 MW from the 1,200 MW Khavda-II Solar Photovoltaic (PV) Project in Gujarat effective February 20, 2026. The commissioned capacity forms the second phase of the project developed by NTPC Renewable Energy Limited (NREL), a wholly-owned step-down subsidiary of NTPC through NGEL. Following the addition, NTPC group’s overall installed capacity reached 87,974 MW and commercial capacity 86,894 MW, while NGEL group installed capacity increased to 8,992.68 MW and commercial capacity to 8,827.68 MW. The project is located in the Kutch region of Gujarat and expands NTPC’s solar portfolio within a major renewable energy cluster.

NHPC approves Rs 5,702 crore investment for two J&K hydro projects

NHPC Limited approved investment proposals worth about Rs 5,702 crore for two hydroelectric projects in the Union Territory of Jammu & Kashmir with a combined capacity of 500 MW. The Board approved the Uri-I Stage-II Hydroelectric Project (240 MW) with an estimated cost of Rs 2,708.95 crore, including Rs 264.31 crore Interest During Construction (IDC) and Rs 26.20 crore for enabling infrastructure, with construction scheduled from March 1, 2026. It also approved the Dulhasti Stage-II Hydroelectric Project (260 MW) costing Rs 2,993.96 crore, including Rs 289.06 crore IDC and Rs 245.00 crore for enabling infrastructure, with construction also planned from March 1, 2026. The approvals remain subject to implementation agreements with the Government of Jammu & Kashmir or the Jammu & Kashmir State Power Development Corporation (JKSPDC) and statutory clearances. The projects expand NHPC’s hydropower development pipeline in Jammu & Kashmir.

Similar Posts

  • Power Bytes

    Power Sector News Roundup for March 13, 2026

    Author: PPD Team Date: March 13, 2026 EAC clears Adani’s 1,200 MW pumped storage project in Uttar Pradesh The Expert Appraisal Committee (EAC) for River Valley and Hydroelectric Projects has recommended granting Terms of Reference (ToR) for the proposed 1,200 MW Cherue Pumped Storage Project in Sonbhadra district, Uttar Pradesh. Adani Hydro Energy Six Limited will develop the project, with the recommendation made during the committee’s 49th meeting in February 2026. The project, estimated at…

  • Power Bytes

    Power Sector News Roundup for December 17, 2025

    Author: PPD Team Date: December 18, 2025 India Tata Power outlines 30 GW capacity target by FY30 Tata Power outlined its medium term growth roadmap at its Analyst Meet held on 15 December 2025, with a focus on clean energy, transmission, distribution and emerging technologies. The company is targeting 30 GW of total operational capacity by FY30, including 20 GW from clean and green sources such as renewable energy, hydro and pumped storage. Clean and…

  • Power Bytes

    Power Sector News Roundup for August 25, 2025

    Author: PPD Team Date: August 26, 2025 Global: Japan launches first osmotic power plant in Fukuoka India: Andhra Pradesh approves 250 MW solar plant in Kadapa PFC secures EUR 150 million loan from KfW for RDSS PFC incorporates SPV for transmission project between SR Grid and ER Grid Prostarm wins 150 MW/300 MWh BESS project in Karnataka ACME wins SECI’s green ammonia auction to supply IFFCO at Kandla Neo Infra fund acquires SolarArise for Rs…

  • Power Bytes

    Power Sector News Roundup for October 3, 2025

    Author: PPD Team Date: October 3, 2025 India: MNRE issues advisory on strict compliance in renewable energy procurement Sterlite Electric files DRHP with SEBI for IPO IREDA reports 86 per cent growth in loan sanctions in H1 FY 2025-26 Serentica partners with Envision Energy for 560 MW wind project Kosol Energie commissions 38 MWp solar project for GSECL in Gujarat MHI issues guidelines for EV charging station rollout under PM E-DRIVE Rays Power Infra files…

  • Power Bytes

    Power Sector News Roundup for November 4, 2025

    Author: PPD Team Date: November 4, 2025 India 93 GW renewable backlog triggers government action on unsigned PPAs and PSAs The Ministry of Power has instructed Renewable Energy Implementing Agencies (REIAs) to close or cancel pending renewable energy bids and Letters of Award (LoAs) by November 30, 2025, where Power Purchase Agreements (PPAs) or Power Sale Agreements (PSAs) cannot be signed. The move follows a review chaired by Secretary (Power) Pankaj Agarwal on October 17,…

  • Power Bytes

    Power Sector News Roundup for November 21, 2025

    Author: PPD Team Date: November 21, 2025 India Uttar Pradesh releases long term energy and renewable roadmap for 2047 Uttar Pradesh has issued its Energy and Renewable Vision 2047 with a target to meet 40 to 50 percent of its energy demand from renewable sources by 2047. The plan focuses on clean, reliable, and affordable power. It proposes new solar parks, floating solar projects, hybrid systems, and bioenergy units, along with wider EV charging and…

Leave a Reply

Your email address will not be published. Required fields are marked *