Power Bytes

Power Sector News Roundup for February 23, 2026

Author: PPD Team Date: February 23, 2026

CEA panel finds 55% MTL flexible operation does not damage thermal units

A committee constituted by the Central Electricity Authority (CEA) found that operating thermal power plants at 55% minimum technical load (MTL) with conservative ramping rates does not result in significant damage to generating units. The report, based on meetings held between July and October 2025, noted NTPC’s reluctance to participate in mandated pilot projects for two-shift operation, delaying development of a compensation framework. GRID-INDIA reported that most inter-state generating stations and several state stations have technically achieved 55% MTL, though commercial and regulatory barriers persist. Analysis of Farakka Unit-2 and Jhajjar Unit-3 showed no evidence linking significant damage to 55% MTL operation, with about 70% of issues attributed to ageing, coal quality or operational disturbances. The committee recommended pilot studies on smaller and older 210 MW units and measures to achieve 40% MTL through retrofits, improved operational practices and updated technical specifications.

CAG audit flags operational gaps and revenue losses at NLC India

A performance audit by the Comptroller and Auditor General of India (CAG) identified operational, financial and compliance gaps at NLC India Limited’s lignite mines and thermal stations in Neyveli during 2017-18 to 2022-23. Land shortages left only 46.19 hectares available for active mining, causing a supply gap of 2.77 million tonnes and a potential revenue loss of Rs 338.62 crore, while extraction from overburden dump areas increased costs by Rs 364.80 crore. The audit reported environmental clearance lapses, overburden dump height violations, ageing equipment and delayed energy audits deferring potential annual savings of Rs 47.92 crore. Thermal station issues led to under-recovery of capacity charges of Rs 2,353.99 crore, generation loss of 1,594.77 million units and additional cost pressures including Rs 248.99 crore operation and maintenance expenditure above regulatory limits. CAG recommended faster land acquisition, slope monitoring systems, maintenance improvements, FBHE modifications, adequate lignite storage, manpower rationalisation and expediting Flue Gas Desulphurization (FGD) implementation.

KPI Green Energy completes 92.4 MW wind project in Gujarat

KPI Green Energy Limited completed a 92.4 MW wind power project for Ayana Renewable Power Four at Nakhatrana in Bhuj, Gujarat. The milestone was disclosed in a stock exchange filing stating that the project secured approval from the Central Electricity Authority (CEA). The project comprises 28 wind turbine generators, with KPI Green Energy executing the full scope including balance of plant, power substation development, extra high voltage (EHV) transmission line installation and erection and commissioning of all turbines. The facility adds to India’s renewable energy capacity and contributes to expansion of clean power generation infrastructure.

NTPC Green declares 165 MW commercial at Khavda-II solar project

NTPC Green Energy Limited (NGEL) declared commercial operation of 165 MW from the 1,200 MW Khavda-II Solar Photovoltaic (PV) Project in Gujarat effective February 20, 2026. The commissioned capacity forms the second phase of the project developed by NTPC Renewable Energy Limited (NREL), a wholly-owned step-down subsidiary of NTPC through NGEL. Following the addition, NTPC group’s overall installed capacity reached 87,974 MW and commercial capacity 86,894 MW, while NGEL group installed capacity increased to 8,992.68 MW and commercial capacity to 8,827.68 MW. The project is located in the Kutch region of Gujarat and expands NTPC’s solar portfolio within a major renewable energy cluster.

NHPC approves Rs 5,702 crore investment for two J&K hydro projects

NHPC Limited approved investment proposals worth about Rs 5,702 crore for two hydroelectric projects in the Union Territory of Jammu & Kashmir with a combined capacity of 500 MW. The Board approved the Uri-I Stage-II Hydroelectric Project (240 MW) with an estimated cost of Rs 2,708.95 crore, including Rs 264.31 crore Interest During Construction (IDC) and Rs 26.20 crore for enabling infrastructure, with construction scheduled from March 1, 2026. It also approved the Dulhasti Stage-II Hydroelectric Project (260 MW) costing Rs 2,993.96 crore, including Rs 289.06 crore IDC and Rs 245.00 crore for enabling infrastructure, with construction also planned from March 1, 2026. The approvals remain subject to implementation agreements with the Government of Jammu & Kashmir or the Jammu & Kashmir State Power Development Corporation (JKSPDC) and statutory clearances. The projects expand NHPC’s hydropower development pipeline in Jammu & Kashmir.

Similar Posts

  • Power Bytes

    Power Sector News Roundup for December 4, 2025

    Author: PPD Team Date: December 4, 2025 India Vikram Solar names Arun Mittal as CEO of VSL Powerhive Vikram Solar has appointed Arun Mittal as CEO of VSL Powerhive Private Limited to support its entry into the energy storage market as module capacity reaches 9.5 GW. VSL Powerhive will focus on battery storage as part of the company’s plan to operate as an integrated energy transition firm. Mittal brings more than thirty years of experience…

  • Power Bytes

    Power Sector News Roundup for October 24, 2025

    Author: PPD Team Date: October 24, 2025 Global: Rondo Energy commissions world’s largest industrial heat battery India: India supports 10 Pacific nations with solar power under UN partnership Juniper Green commissions 64 MW renewable projects Vikram Solar secures 149 MW module order from Sunsure Energy Bondada Engineering awarded Rs 1,050 crore Adani solar project in Gujarat EQT retains Zelestra India, appoints Parag Sharma as new CEO Keppel gains full control of Cleantech Solar, eyes $400…

  • Power Bytes

    Power Sector News Roundup for July 28, 2025

    Author: PPD Team Date: July 28, 2025 Global: Satellite images reveal China’s race to dominate nuclear fusion India: IEX, Adani Energy, and REC report strong Q1 earnings in FY26 TNPGCL to pilot 200 MW battery storage at thermal plant PFC transfers two transmission subsidiaries to private bidders POWERGRID commissions ER-WR interconnection project NTPC signs MoU with Bihar for battery and renewable energy projects Gurugram, Faridabad industry bodies urge tariff parity with neighbouring states Tata Power…

  • Power Bytes

    Power Sector News Roundup for February 2, 2026

    Author: PPD Team Date: February 2, 2026 India CEA flags widespread non-compliance with mandatory transformer standards The Central Electricity Authority has flagged continued non-compliance by power utilities with mandatory transformer and reactor rating standards. In a letter dated 24 January 2026, the CEA directed utilities and generation companies to strictly follow standard specifications for transformers and reactors rated 66 kV and above. These specifications were issued in April 2021 and became legally binding under regulations…

  • Power Bytes

    Power Sector News Roundup for January 13, 2026

    Author: PPD Team Date: January 13, 2026 India POWERGRID charges 765 kV Bhadla II–Sikar II transmission line Power Grid Corporation of India Limited (POWERGRID) has charged the 765 kV double circuit Bhadla II–Sikar II (2nd) transmission line to strengthen renewable power evacuation from Rajasthan. The charging was executed by POWERGRID Bhadla Sikar Transmission Limited (PBSTL), a tariff based competitive bidding subsidiary. The project forms part of the Transmission System Strengthening Scheme for Evacuation of Power…

Leave a Reply

Your email address will not be published. Required fields are marked *