MNRE clarifies operational rules for BioCNG project funding
Author: PPD Team Date: September 22, 2025
Author: PPD Team Date: September 22, 2025
The Ministry of New and Renewable Energy (MNRE) has released a memorandum detailing performance requirements that BioCNG projects must meet to qualify for Central Financial Assistance (CFA). The directive sets out minimum generation thresholds for disbursing the full amount of support.
The clarification applies to the Waste to Energy Programme under Phase-I of the National Bioenergy Programme. It follows the original guidelines issued on November 2, 2022, and the subsequent revision on June 27, 2025.
As per the directive, performance inspection will now require three consecutive months of operation. During this period, plants must demonstrate continuous 24-hour operation at no less than 80 per cent of rated capacity or the maximum CFA-eligible capacity, whichever is lower.
An annexure to the memorandum includes a table outlining minimum generation benchmarks for BioCNG plants with capacities ranging from 2 tonnes per day to 33 tonnes per day.
The memorandum specifies that CFA will not be granted if the plant load factor is under 50 per cent. For projects exceeding 24 tonnes per day, generation data for a 24-hour run at no less than 50 per cent of rated capacity must be submitted.
The directive, issued with the Secretary’s approval, has been circulated to implementing bodies such as IREDA and state-level agencies.
Author: PPD Team Date: February 26, 2025 Adani Power Limited received a letter of intent (LoI) from the resolution professional to acquire Vidarbha Industries Power Limited (VIPL) on 24 February 2025. The acquisition is subject to the terms of the LoI and necessary approvals from the National Company Law Tribunal (NCLT), Mumbai, along with other regulatory authorities, courts, or tribunals as required. VIPL, a wholly owned subsidiary of Reliance Power Limited (RPL), developed a 600…
Author: PPD Team Date: December 16, 2024 Power Grid Corporation of India Limited (PGCIL) has received Letters of Intent (LoI) for two major transmission projects. These include the transmission system under ISTS for evacuating power from Kudankulam Nuclear Power Plant Units 3 and 4 (2×1000 MW) and the system strengthening at Koppal-II and Gadag-II for integrating renewable energy (RE) generation projects in Karnataka. Both schemes will be implemented on a build, own, operate, and transfer…
Author: PPD Team Date: August 13, 2025 The Central Electricity Regulatory Commission (CERC) will hold a public hearing on 18 August 2025 to discuss the Draft Power Market (First Amendment) Regulations, 2025, and the Draft Guidelines for Virtual Power Purchase Agreements (VPPA). According to the public notice issued on 6 August 2025, the hearing will be conducted online. The session on the draft amendment to the Power Market Regulations will begin at 11:00 a.m., followed…
Author: PPD Team Date: November 20, 2024 The interregional electricity transfer in India grew 7.8% year-on-year in the first half (H1: April to September) of FY25, reaching 134,714 MU (million units), up from 123,918 MU in H1FY24, according to Grid Controller of India Ltd (GRID-INDIA). Key Highlights: WR-NR transfers: Exports from the Western Region (WR) to the Northern Region (NR) surged by 34.3%, totalling 54,099 MU in H1FY25, representing 40.2% of the total interregional transfers,…
Author: PPD Team Date: July 29, 2025 The Ministry of New and Renewable Energy (MNRE) has issued two updates clarifying the implementation of the Approved List of Models and Manufacturers (ALMM) for solar photovoltaic (PV) projects, with new guidance on tender compliance timelines and the treatment of battery storage-linked solar plants under the framework. On 28 July 2025, MNRE amended its earlier order dated 9 December 2024 to ease compliance for developers participating in government-backed…
Author: PPD Team Date: July 16, 2025 NLC India Limited has announced a Rs 1.25 trillion investment plan to increase its power generation capacity from 6.7 GW to 20 GW by 2030. The expansion will span across renewable energy, thermal power, and mining. Out of the total capital outlay, Rs 650 billion is earmarked for renewable energy and green initiatives. This includes Rs 150 billion specifically for battery energy storage systems. Rs 450 billion is…