HG Infra subsidiary signs BESPA with GUVNL for 300 MW BESS project
Author: PPD Team Date: December 4, 2025
Author: PPD Team Date: December 4, 2025
H.G. Choraniya Bess, a subsidiary of HG Infra Engineering, has signed a battery energy storage purchase agreement with Gujarat Urja Vikas Nigam Limited for a 300 MW/600 MWh BESS project.Â
The company secured this capacity in GUVNL’s Phase VI auction for 500 MW/1,000 MWh of BESS held in April 2025. The project will be executed on a build own operate basis.
The project is expected to be completed within 24 months. The estimated cost is about Rs 6.70 billion. The tariff has been set at Rs 285,600 per MW for a 12 year period. The storage facilities will be available to GUVNL for charging and discharging as required.
Author: PPD Team Date: January 9, 2025 NTPC Renewable Energy Limited (NTPC REL) has signed a memorandum of understanding (MoU) with Deendayal Port Authority to establish a green hydrogen fueling station and deploy 11 hydrogen-powered buses at Kandla Port, Gujarat. This initiative seeks to replace fossil fuel-based buses at the port, advancing clean energy adoption while supporting decarbonisation and energy security.
Author: PPD Team Date: January 16, 2026 Sterling and Wilson Renewable Energy Limited (SWREL) has reported strong revenue and operating performance for the third quarter of FY26 and raised its full year order inflow guidance to over Rs 11,000 crore, citing sustained demand in the renewable energy market. The Board of Directors approved the unaudited standalone and consolidated financial results at a meeting held on 15 January 2026, for the quarter and nine months ended…
Author: PPD Team Date: July 10, 2025 Hindustan Powerprojects Private Limited (HPPPL) has started construction of a 300 MW (435 MWp) Inter-State Transmission System (ISTS)-connected solar power project in Lalitpur, Uttar Pradesh. The project is part of the larger 2,000 MW ISTS-connected solar programme being implemented for Uttar Pradesh Power Corporation Limited (UPPCL). It was announced during the Clean Energy Summit 2025 held in Lucknow. Under the scope of work, HPPPL will identify land, develop…
Author: PPD Team Date: February 10, 2026 Oswal Pumps Limited reported strong financial performance for the third quarter and the first nine months of FY26. For the nine-month period ended FY26, total income rose to Rs 15,692 million, reflecting a 47.0% increase compared to the same period last year. Profit after tax (PAT) stood at Rs 2,837 million, translating into a margin of 18.1%. In Q3 FY26, total income reached Rs 5,077 million, up 33.4%…
Author: PPD Team Date: December 11, 2024 Five firms have won bids for setting up 2,000 MW Inter-State Transmission System (ISTS) connected solar power projects and 1,000 MW energy storage systems (ESS) under Tranche-XVII of the Solar Energy Corporation of India (SECI), announced on December 9, 2024. The successful bidders and their respective capacities are as follows: Sembcorp Green Infra Private Limited (Sembcorp Energy India Limited) – 150 MW solar and 75 MW ESS at…
Author: PPD Team Date: December 22, 2025 NHPC Limited has declared the commercial operation date of Unit 2 (250 MW) of the Subansiri Lower Hydroelectric Project as 23 December 2025. The company confirmed that the trial run of Unit 2 was successfully completed on 18 December 2025. Before this, NHPC achieved test synchronisation of the unit with the national grid on 02 December 2025. The Subansiri Lower Hydroelectric Project has a planned installed capacity of…