Alpex Solar to expand UP cell plant to 2.2 GW
Author: PPD Team Date: November 3, 2025
Author: PPD Team Date: November 3, 2025
Alpex Solar Limited has approved the expansion of its proposed solar cell manufacturing facility in Kosi Kotwan, Uttar Pradesh, from 1.6 GW to 2.2 GW. The company will also adopt advanced G12R tunnel oxide passivated contact (TOPCon) technology as part of the upgrade.
The total capital expenditure for the expansion and technology transition is estimated at Rs 31.36 billion, which will be fully financed through internal accruals.
Under the revised plan, the first phase will establish 1.4 GW of G12R TOPCon capacity, with trial production scheduled for the first quarter of FY2026–27. The second phase will add 800 MW within six months of phase I completion, bringing the total capacity to 2.2 GW. The entire facility is expected to become operational during FY2026–27.
Author: PPD Team Date: March 11, 2026 NHPC Limited has secured Terms of Reference (ToR) for its proposed 2,400 MW Savitri Open Loop Pumped Storage Project in Maharashtra from the Expert Appraisal Committee (EAC) for River Valley and Hydroelectric Projects. The approval resolves a delay caused by the need for a formal clearance from the Mahabaleshwar–Panchgani Eco-Sensitive Zone (ESZ) Monitoring Committee. The ToR was granted during the 48th meeting of the EAC. The proposal had…
Author: PPD Team Date: June 18, 2025 CG Power and Industrial Solutions Limited has secured its largest-ever single order — a Rs 641-crore contract from Power Grid Corporation of India Limited (PGCIL). The order is for 765kV Transformer Package 7TR-12-Bulk. It covers the supply of 765/400kV single-phase transformers under a corporate procurement package. PGCIL had invited bids for this in December 2024. Other bidders included Bharat Heavy Electricals Limited (BHEL) and GE Vernova T&D India…
Author: PPD Team Date: February 7, 2025 Gensol Engineering Limited has been awarded an engineering, procurement, and construction (EPC) contract valued at approximately Rs 9.679 billion (inclusive of goods and services tax) for a 245 MW solar photovoltaic project at the Khavda Renewable Energy Power Park in Gujarat. The contract, secured from a public sector undertaking, also includes three years of operations and maintenance services. Rayzon Solar has secured a contract to manufacture and supply…
Author: PPD Team Date: February 4, 2025 Solex Energy Limited has successfully commissioned an 800 MW high-speed solar module manufacturing line in Surat, Gujarat. The facility produces n-Type TOPCon rectangular cell-based Tapi-R series modules, with capacities ranging from 585 Wp to 625 Wp. This production line operates 30% faster than other Indian facilities, increasing output efficiency and reducing lead times. Equipped with Artificial Intelligence (AI) and Automated Optical Inspection (AOI), the facility ensures enhanced quality…
Author: PPD Team Date: October 17, 2024 Maharashtra State Electricity Distribution Company (MSEDCL) has selected JSW Neo Energy, Tata Power Renewable Energy Limited (TPREL), Avaada Energy, and Juniper Green Energy as the winners of its 1,650 MW wind-solar hybrid auction. These companies will supply power on a long-term basis from grid-connected intrastate projects. JSW Neo secured 600 MW, including 400 MW under the greenshoe option, while Tata Power won 400 MW, with 200 MW under…
Author: PPD Team Date: May 12, 2025 The Central Electricity Regulatory Commission (CERC) has issued the draft Deviation Settlement Mechanism and Related Matters (Second Amendment) Regulations, 2025, proposing limited payments for infirm power injected by thermal generating stations before trial runs. Currently, under the DSM Regulations, 2024, no payments are made for infirm power unless scheduled after a successful trial run. Thermal generators raised concerns about unrecovered fuel costs during mandatory testing. The Ministry of…