CERC proposes payment for infirm power from thermal plants before trial run
Author: PPD Team Date: May 12, 2025
Author: PPD Team Date: May 12, 2025
The Central Electricity Regulatory Commission (CERC) has issued the draft Deviation Settlement Mechanism and Related Matters (Second Amendment) Regulations, 2025, proposing limited payments for infirm power injected by thermal generating stations before trial runs.
Currently, under the DSM Regulations, 2024, no payments are made for infirm power unless scheduled after a successful trial run. Thermal generators raised concerns about unrecovered fuel costs during mandatory testing. The Ministry of Power also called for a review of the existing provisions.
The amendment proposes payment at the Normal Rate of Charges for Deviation, capped at Rs 2.86/kWh, for power injected between first synchronization and the trial run. The rate reflects average energy charges of thermal plants for 2023-24. However, payment will not apply if grid frequency exceeds 50.05 Hz.
CERC clarified that scheduling of infirm power before the trial run will still not be allowed. The change is intended to support financial recovery for generators while preserving grid reliability.
Comments on the draft can be submitted by June 10, 2025.
Author: PPD Team Date: April 21, 2026 Clean Max Enviro Energy Solutions Limited (CleanMax) has entered into an agreement to supply hybrid renewable energy to Shell India’s operations in Gujarat and Karnataka. The collaboration covers the development of two wind-solar hybrid projects with a combined installed capacity of about 30 MW. In Gujarat, CleanMax is developing a 16.83 MW hybrid plant to supply power to Shell’s liquefied natural gas (LNG) terminal at Hazira, Surat. The…
Author: PPD Team Date: June 6, 2025 Techno Electric & Engineering Company Ltd has received a letter of intent from RailTel Corporation of India to develop a 10 MW data centre in Noida, Uttar Pradesh. The facility will be built on RailTel-owned land. The award is subject to conditions outlined in the letter of intent and will proceed upon signing of a formal agreement. Techno was selected through an open tender and will serve as…
Author: PPD Team Date: November 12, 2024 Power Construction Corporation of China (PowerChina) has officially transferred the 500 kV Thung Song substation project to Thailand’s Electricity Generating Authority of Thailand (EGAT) after successful site acceptance tests. Located in Nakhon Si Thammarat, southern Thailand, the project is crucial for enhancing grid transmission capacity and ensuring stable power operations in the region. The project involved renovating and expanding an existing 230 kV air-insulated switchgear substation and constructing…
Author: PPD Team Date: December 15, 2025 The Central Transmission Utility of India Limited (CTUIL) has released a draft “Detailed Procedure for Grant of Connectivity and General Network Access” for public consultation. The document gives effect to the Central Electricity Regulatory Commission (CERC) Connectivity and General Network Access to the Inter-State Transmission System Regulations, 2022. It will replace the procedure issued in October 2022. CTUIL has invited comments until 27 December 2025. The draft runs…
Author: PPD Team Date: December 31, 2024 Longroad Energy has signed a long-term Power Purchase Agreement (PPA) with Meta for the entire output of its 300 MWac 1000 Mile solar project in Yoakum County, Texas. The energy produced will be supplied to the Southwest Power Pool (SPP) grid and support Meta’s data center operations. The 1000 Mile solar project, Longroad’s first in the SPP region, is expected to commence commercial operations in 2026.
Author: PPD Team Date: July 8, 2025 Hazoor Multi Projects Limited (HMPL) has secured an EPC contract worth Rs 9,130 million from Apollo Green Energy Limited. The contract is for the 200 MW Khavda Solar PV Project – Phase XVII (NHPC) in Gujarat. The Letter of Award (LoA) was issued on July 4, 2025. Apollo Green had won this project from NHPC Limited in August 2024. NHPC, in turn, secured the 200 MW capacity at…