Tata Power has commissioned the 400 kV Koteshwar Rishikesh transmission line. The company announced the development in a press release dated 09 December 2025.
The new line will evacuate up to 1,000 MW of hydropower from the Tehri Koteshwar complex in Uttarakhand and supply it to six northern states and three union territories. These include Haryana, Punjab, Uttar Pradesh, Delhi, Rajasthan and Jammu and Kashmir.
The project was delivered by NRSS XXXVI Transmission Limited. The company was acquired by Resurgent Power Ventures, which is a joint venture promoted by Tata Power, ICICI Bank and global investors. The line was built across difficult Himalayan terrain at elevations above 1,816 metres. Tata Power said the completion within a year shows its execution strength. With this project, its operational and under execution transmission network has reached 7,083 circuit kilometres.
This is the third major element of the NRSS project to be commissioned. The line is expected to strengthen energy security and grid reliability across North India and support the integration of renewable energy into the national system.
The featured photograph is for representation only.
Author: PPD Team Date: July 11, 2025 Bharat Coking Coal Limited (BCCL), a subsidiary of Coal India Limited (CIL), has restarted coal production at its legacy PB Project in Jharkhand. This is the first operational project under the mine developer and operator (MDO) model in the CIL ecosystem. The PB Project has been awarded to Eagle Infra India Limited for a 25-year term. It is expected to produce 52 million tonnes of coal during its…
Author: PPD Team Date: August 21, 2025 Shares of US solar companies gained after the Treasury Department issued guidance on clean energy subsidies that proved less restrictive than expected. The new rules, announced on 15 August, clarify what qualifies as a solar or wind project under construction, a requirement for accessing federal tax credits covering 30% of project costs. Developers must now show physical work on-site, not just financial commitments. The Treasury also retained the…
Author: PPD Team Date: December 2, 2025 Uttar Pradesh has announced a new scheme that offers major relief on overdue electricity bills. The Bijli Bill Rahat Yojana from Uttar Pradesh Power Corporation Ltd starts on December 1 and provides a full waiver of surcharge and interest for eligible users, along with a cut in the principal amount. The scheme applies to domestic consumers under LMV 1 with loads up to 2 kW and small commercial…
Author: PPD Team Date: May 29, 2025 The Telangana government is developing a 50-year power generation plan with a near-term target of installing 20,000 MW of green energy capacity by 2029–30. The roadmap aims to align future capacity expansion with increasing electricity demand and evolving technology trends, while improving energy security and reducing emissions. As per the Resource Adequacy Plan for the State of Telangana released by the Central Electricity Authority (CEA), the state’s electricity…
Author: PPD Team Date: December 11, 2024 Teerth Gopicon Private Limited has received a Letter of Award (LoA) worth Rs 2.37 billion from Rajasthan Renewable Energy Corporation Limited (RRECL) to set up 37 MW of rooftop solar photovoltaic (PV) power projects on government buildings in Baran and Pali districts. The contract, awarded on December 7, 2024, includes 11 MW in Baran and 26 MW in Pali. The scope of the project includes the design, supply,…
Author: PPD Team Date: October 6, 2025 Tata Power Renewable Energy Limited (TPREL) has signed a Power Purchase Agreement (PPA) with Tata Power Mumbai Distribution to develop an 80 MW Firm and Dispatchable Renewable Energy (FDRE) project. The initiative will generate 315 MUs annually and reduce over 0.25 million tons of CO₂ emissions, supporting India’s clean energy goals. The project will integrate solar, wind, and battery storage to supply reliable peak-hour power. It is expected…