CERC allows withdrawal option for stalled RE connectivity cases
The Central Electricity Regulatory Commission (CERC) has issued an order in Petition No. 666/MP/2025, allowing renewable energy developers an optional withdrawal window where final connectivity grants have been delayed due to transmission planning constraints flagged by the Central Transmission Utility of India Limited (CTUIL). The order, dated April 10, 2026, stems from a petition filed by Saurya Urja Company of Rajasthan Limited (SUCRL). The developer had sought relief from strict land document submission timelines under…