Renewable energy projects face up to 12-month delay in signing of PPAs
Author: PPD Team Date: December 20, 2024
Author: PPD Team Date: December 20, 2024
India’s renewable energy sector is facing significant delays in securing power purchase agreements (PPAs), which are affecting around 40-45 GW of projects out of a total 80-90 GW in the pipeline.
Experts note that distribution companies (discoms) are prioritizing projects with higher capacity utilization factors, contributing to the backlog in PPA signings. The gap between project awards and PPA finalizations currently spans eight to nine months, impacting project execution timelines.
Several factors, including regulatory uncertainties, financial challenges faced by discoms, and conflicts between central and state policies, are contributing to the delays. Grid infrastructure limitations and tariff disputes also complicate matters, with risks of cost overruns and reduced investor confidence.
Delays were notable in 2022 and 2023, with PPA signings consistently falling behind schedule. For instance, Renew’s 500 MW solar project in Gujarat and Adani Green’s 400 MW wind-solar hybrid project in Andhra Pradesh faced significant delays.
Experts suggest aligning discoms’ offtake schedules with the clearer timelines of public sector undertakings to streamline the PPA process and resolve the ongoing delays.
Author: PPD Team Date: March 21, 2025 KEC International Limited has won a contract from Power Grid Corporation of India Limited (PGCIL) for the construction of an 800 kV high voltage direct current (HVDC) and 765 kV transmission line. The contract was awarded on March 15, 2025. Transformers and Rectifiers India Limited (TRIL) has secured a Rs 7.26 billion contract from Gujarat Energy Transmission Corporation Limited (GETCO) for the supply of auto transformers and bus…
Author: PPD Team Date: July 24, 2025 The Ministry of New and Renewable Energy (MNRE) has amended operational guidelines for two components of the PM-Surya Ghar: Muft Bijli Yojana—Incentives for Local Bodies and Model Solar Village. The changes, issued through official memoranda dated July 22, 2025, and July 18, 2024, aim to address implementation gaps and clarify eligibility. Incentives for Local Bodies As per the revised Clause 6(c), the National Programme Implementation Agency (NPIA) will…
Author: PPD Team Date: November 5, 2025 The Maharashtra government has entered into an Rs 8,000 crore agreement with GSC PSP Maha Pvt Ltd of Haryana to develop the Panchmauli-Devalipada pumped storage hydroelectric project across Dhule and Nandurbar districts. The 1,500 MW project is expected to generate around 2,500 jobs and contribute over Rs 1,100 crore in annual revenue to the state. The MoU was signed in Mumbai in the presence of Chief Minister Devendra…
Author: PPD Team Date: December 10, 2025 The Central Transmission Utility has issued draft guidelines to regulate changes in ownership for power generation and storage projects that have not yet reached commercial operation. POWERGRID, acting as the Central Transmission Utility, released the draft on 02 December 2025 for stakeholder consultation. The proposed procedure applies to renewable energy generating stations other than hydro and to energy storage systems other than pumped storage projects. Any change in…
Author: PPD Team Date: April 10, 2025 The Ministry of Coal has signed agreements for two coal blocks under the 11th round of commercial coal mine auctions. Marwatola-II has been awarded to Singhal Business Private Limited. Namchik West has gone to PRA Nuravi Coal Mining Private Limited. One of the blocks is fully explored, while the other is partially explored. Together, the two mines have a peak rated capacity of 0.34 million tonnes per annum….
Author: PPD Team Date: November 17, 2025 Waaree Energies Ltd. has expanded its manufacturing portfolio with two new solar module plants in Gujarat, totalling 3.6 GW per year. The company opened a 2.1 GW facility at Degam in Navsari on November 14, 2025. It commissioned a 1.5 GW unit through its subsidiary Sangam Solar One Private Limited in Samakhiali, Kutch, on November 15, 2025. The Degam expansion took place at Waaree’s existing factory in Village…