RAPP-7 achieves rated power operation of 700 MW
Author: PPD Team Date: February 11, 2026
Author: PPD Team Date: February 11, 2026
Nuclear Power Corporation of India Limited (NPCIL) announced that Unit 7 of the Rajasthan Atomic Power Project (RAPP-7) achieved its rated power operation of 700 MW for the first time on February 10, 2026, at 05:15 hours. The milestone marks a key step in India’s indigenous nuclear power programme.
The 700 MW Pressurised Heavy Water Reactor (PHWR), developed indigenously by NPCIL, reached full power after a series of sequential commissioning stages. The unit achieved criticality on September 19, 2024, was synchronised with the Northern Grid on March 17, 2025 after clearance from the Atomic Energy Regulatory Board (AERB), and entered commercial operation on April 15, 2025.
NPCIL said the achievement reflects engineering capability, coordinated teamwork, and institutional integration across the nuclear programme. The Rajasthan Atomic Power Station (RAPS) at Rawatbhata, where RAPP-7 is located, is India’s third-largest nuclear power plant by installed capacity.
The successful operation of RAPP-7 at rated capacity highlights the scaling of indigenous PHWR technology and adds stable baseload capacity to the national grid from a non-carbon-emitting source.
Author: PPD Team Date: October 3, 2025 The Ministry of Power (MoP) has notified a revised renewable consumption obligation (RCO) framework under the Electricity (Amendment) Rules, 2025. The new rules unify state-level renewable purchase obligations (RPOs) under a single national compliance mechanism framed through the Energy Conservation Act, 2001. The framework applies to distribution licensees, open access consumers, and captive users. It replaces the earlier structure issued in October 2023, while retaining the national RCO…
Author: PPD Team Date: March 23, 2026 Solarium Green Energy Limited has received two purchase orders totalling about Rs 22.51 crore (excluding GST), for the supply of TOPCon solar panels to projects across Karnataka, Tamil Nadu, Andhra Pradesh, and Puducherry. The larger order, valued at around Rs 14.10 crore, involves the supply of Bureau of Indian Standards (BIS)-certified 715/720 Wp TOPCon N-type bifacial dual glass panels for grid-connected projects in Karnataka, Tamil Nadu, and Andhra…
Author: PPD Team Date: August 6, 2025 The Ministry of Power has published draft rules to implement a compliance mechanism under the Energy Conservation Act, 2001. Released on 5 August 2025, the Energy Conservation (Compliance Enforcement) Rules, 2025 outline enforcement roles, penalties, and reporting duties for entities under the Act. The Bureau of Energy Efficiency (BEE) will be responsible for identifying and verifying cases of non-compliance. Covered entities include manufacturers, importers, and designated consumers as…
Author: PPD Team Date: December 20, 2024 The central government has selected a site near Arasinakeri, Koppal, for Karnataka’s second nuclear power plant. However, the proposal faces opposition due to land shortages and environmental concerns, particularly regarding nearby protected forest areas. The government requires 1200 acres for the plant, but only 615-635 acres are available. The district administration is surveying nearby land, at least 3 km from populated areas, to meet the requirement. Environmentalists and…
Author: PPD Team Date: December 22, 2025 The Ministry of Power held the second meeting of the India Energy Stack (IES) Taskforce on 19 December 2025 in New Delhi to advance the development of a digital public infrastructure (DPI) for the power sector, according to a Press Trust of India (PTI) report. The IES Taskforce has been set up to develop a unified, secure and interoperable digital framework for the power sector. REC Limited, the…
Author: PPD Team Date: April 2, 2026 Power Mech Projects Limited has secured an operations and maintenance (O&M) contract from Hindustan Zinc Limited for a 91.5 MW captive power plant and its transmission line up to the main receiving substation (MRSS). The contract is valued at Rs 109.22 crore excluding goods and services tax (GST) and has a tenure of 48 months. Power Mech will execute the work as an independent contractor. The order follows…