PVUNL achieves rail connectivity for Patratu Thermal Power Project
Author: PPD Team Date: January 23, 2025
Author: PPD Team Date: January 23, 2025
Patratu Vidyut Utpadan Nigam Limited (PVUNL) successfully conducted a trial run for rail connectivity of the Patratu Thermal Power Project Phase I on January 21, 2025.Â
The project, located in Ramgarh district, Jharkhand, is expected to be commissioned by December 2025.
PVUNL, a special purpose vehicle (SPV) formed by NTPC Limited in a joint venture with Jharkhand Bijli Vitran Nigam Limited (JBVNL), is developing the project.Â
Phase I involves three 800 MW units, with a total investment of Rs.186.68 billion. Bharat Heavy Electricals Limited (BHEL) is the engineering, procurement, and construction (EPC) contractor for the project.
Author: PPD Team Date: August 13, 2025 The Cabinet Committee on Economic Affairs has approved an investment of Rs 8,146.21 crore for the Tato-II Hydro Electric Project in Shi Yomi district, Arunachal Pradesh. The project, with an installed capacity of 700 MW (4 x 175 MW), is expected to generate 2,738.06 million units of electricity. The completion timeline is estimated at 72 months. The project will be developed through a joint venture between North Eastern…
Author: PPD Team Date: December 10, 2025 THDC India Limited has begun commercial operation of the third unit of the Tehri Variable Speed Pumped Storage Plant. The 250 MW unit is part of the 1,000 MW project, which is now the largest variable speed pumped storage plant developed by a central public sector enterprise. The Commercial Operation Date was commenced virtually from New Delhi by Manohar Lal, Minister of Power. The Minister said the commissioning…
Author: PPD Team Date: September 1, 2025 Serentica Renewables will set up one of India’s largest battery energy storage system (BESS) projects in Rajasthan through a partnership with Shanghai Gotion Digital Energy Tech Co. The 50 megawatt (MW) / 200.6 megawatt hour (MWh) facility will be located in Bikaner and is scheduled to be commissioned by the end of 2025. This marks Serentica’s first venture into BESS. Akshay Hiranandani, CEO of Serentica Renewables, said the…
Author: PPD Team Date: December 30, 2025 Waa Solar Limited has announced that it has received a major Letter of Award (LOA) from M.P. Urja Vikas Nigam Limited (MPUVNL) for developing grid-connected solar power plants. The information was disclosed through a regulatory filing, stating that the project is valued at around Rs 225 crore and has been awarded by a state-owned power utility. According to the filing made under Regulation 30 of the Securities and…
Author: PPD Team Date: March 18, 2026 The Ministry of New & Renewable Energy (MNRE) has amended the Approved Models and Manufacturers (ALMM) Order to expand domestic sourcing requirements to silicon wafers. The amendment introduces a new compliance layer under ALMM, aimed at strengthening India’s end-to-end solar manufacturing ecosystem. The requirement will take effect from June 1, 2028. Expanded ALMM compliance chain The ALMM framework previously covered solar photovoltaic (PV) modules under List-I and solar…
Author: PPD Team Date: May 21, 2025 NTPC Limited has invited bids for enlistment of agencies to carry out geotechnical investigation works for upcoming nuclear power projects (NPPs). The deadline for bid submission is May 30, 2025. The scope includes investigations at four key project stages: site selection (preparatory), site evaluation (preliminary), excavation consent (detailed), and first pour of concreting (confirmatory). These investigations may be required on land or in water bodies, such as rivers…