PGCIL completes delayed interstate transmission system for Rajasthan’s solar energy zones
Author: PPD Team Date: September 16, 2024
Author: PPD Team Date: September 16, 2024
Power Grid Corporation of India Ltd (PGCIL) recently commissioned an interstate transmission system (ISTS) under “Powergrid Bhadla Transmission Ltd.” The project, officially named the “Transmission system strengthening scheme for evacuation of power from solar energy zones in Rajasthan (8.1 GW) under Phase-II, Part B,” was completed in August 2024, nearly two years behind schedule.
This Rs 11.06 billion scheme, awarded to PGCIL under the Tariff-Based Competitive Bidding (TBCB) route, involved the construction of a 405-ckm 765kV double-circuit line from the Fatehgarh-II Pooling Station to Bhadla-II Pooling Station. It also included two 765kV line bays at Bhadla-II for the line’s termination.
The project faced delays due to concerns about the transmission line passing through areas inhabited by the endangered Great Indian Bustard (GIB). In July 2022, a Supreme Court-appointed committee cleared the project but required a rerouting, which added 25 ckm to the original line length and increased the project cost by over 50%, from an initial estimate of Rs 7.14 billion.
This ISTS scheme is part of a broader initiative to build transmission infrastructure for evacuating 20 GW of power from Rajasthan’s solar energy zones. PGCIL won the project by quoting an annualized tariff of Rs 728.93 million during an e-reverse auction held in January 2021.
Author: PPD Team Date: November 21, 2024 UltraTech Cement Limited is expanding its use of electric trucks, contracting 100 EV trucks to transport 75,000 tonnes of clinker monthly over a 400-km roundtrip between its Dhar Cement Works in Madhya Pradesh and Dhule Cement Works in Maharashtra. This initiative is projected to cut carbon emissions by 17,000 tonnes annually. The move builds on a pilot project launched in January 2024 with five EV trucks. UltraTech plans…
Author: PPD Team Date: November 13, 2024 Bharat Heavy Electricals Ltd (BHEL) has secured a contract from NTPC Ltd to establish the main plant package for the 3×800 MW Telangana Stage-II supercritical thermal power plant. The contract encompasses design, engineering, manufacturing, supply, erection, commissioning, and civil construction. BHEL has received a Limited Notice to Proceed (LNTP) from NTPC to commence basic engineering work for the main plant package. Before this contract, BHEL had contributed to…
Author: PPD Team Date: August 14, 2025 The West Bengal cabinet has approved the construction of two 800 MW supercritical power units in Salboni, Jhargram. The projects are expected to draw investments exceeding Rs 10,000 crore and will operate under a public-private partnership model. State power minister Aroop Biswas noted that JSW Group is already setting up two 800 MW supercritical units at the same location. The Salboni site has a long history of proposed…
Author: PPD Team Date: November 4, 2024 Tata Power reported reduced Aggregate Technical & Commercial (AT&C) losses in its Odisha power distribution business during the first half of FY25. The investor presentation indicated improvements in two of the four discoms, TPCODL and TPSODL, while AT&C losses in TPWODL remained constant and slightly increased in TPNODL. Overall, AT&C losses across the Odisha discoms, weighted by electricity purchase volume, decreased to 22.6% in H1 FY25 from 23.9%…
Author: PPD Team Date: January 31, 2025 Voltamp Transformers Ltd has commenced construction of its new power transformer manufacturing facility at Jarod in Vadodara district, Gujarat. The company has completed all land acquisition formalities and initiated work on the factory building. The facility aims to address rising demand in the transformer market over the next 7–10 years. In its first phase, the plant will have an annual capacity of around 6,000 MVA, producing transformers…
Author: PPD Team Date: January 13, 2025 The Central Government has approved an additional 5,000 MW of decentralized solar power projects under Component A of the Pradhan Mantri Kisan Urja Suraksha evam Utthaan Mahabhiyan (PM-KUSUM) program in Rajasthan. This allocation supports the Rajasthan government’s vision of providing daytime electricity to farmers by 2027. The state received an additional quota following a representation by Chief Minister Bhajan Lal Sharma and a team of senior officials, who…