NTPC Green Energy Limited (NGEL) has declared commercial operation of 270 MW capacity at the 1,200 MW Khavda-II Solar PV Project in Gujarat, effective March 11, 2026.
The commissioned capacity represents the third part of the project being developed by NREL, a wholly-owned subsidiary of NGEL and a step-down subsidiary of NTPC Limited.
Following this addition, the total commercial capacity of the NGEL Group has reached 9,292.68 MW. The overall installed capacity of the NTPC Group, including all subsidiaries, now stands at 88,544 MW, while commercial capacity is reported at 87,464 MW.
The Khavda-II Solar PV Project is located in Gujarat and forms part of NTPC’s strategy to expand its renewable energy portfolio.
The featured photograph is for representation only.
Author: PPD Team Date: November 29, 2024 The Union government approved coal allocation for Madhya Pradesh on 28 November 2024 to establish thermal power plants with a combined capacity of 4,100 MW. This was the first approval for coal allocation in five years, with the last granted in 2019 for plants totaling 1,360 MW. The new power plants are expected to attract investments of Rs 250 billion and create significant direct and indirect employment opportunities,…
Author: PPD Team Date: July 24, 2025 L&T Energy GreenTech Ltd (LTEG), a subsidiary of Larsen & Toubro (L&T), will develop India’s largest green hydrogen plant at Indian Oil Corporation Ltd’s (IOCL) Panipat Refinery in Haryana. According to a company statement, the plant will supply 10,000 tonnes of green hydrogen annually to IOCL for 25 years. The project will be implemented on a build-own-operate (BOO) model and is aligned with the Government of India’s National…
Author: PPD Team Date: April 29, 2025 The joint venture (JV) of Rays Power Infra Private Limited and Insolation Energy Limited has secured an engineering, procurement, and construction (EPC) contract from Assam Power Distribution Company Limited (APDCL) to set up a 125 MW solar power project. This project is part of the 1,000 MW Khagarijan Solar Power Project under the Mukhya Mantri Sauro Shakti Prokolpo scheme. The scope includes design, engineering, supply, construction, erection, testing,…
Author: PPD Team Date: July 14, 2025 The Government of Meghalaya is likely to reinstate the old Memorandum of Understanding (MoU) with Athena Energy Ventures Private Limited (AEVPL) for the implementation of the Kynshi Stage I Hydro Electric Project. The project will be located on the Kynshi River and developed on a run-of-the-river (RoR) basis. The original MoU with AEVPL was scrapped after the company proposed a hybrid Pumped Storage Project (PSP) model, which was…
Author: PPD Team Date: November 25, 2024 Avaada Aqua Batteries, a subsidiary of Avaada Group, has signed a Memorandum of Understanding (MoU) with the Rajasthan government to establish a 1.2 GW pumped storage project (PSP) in the Sirohi district. With a budget of Rs 58 billion, the project is expected to be completed within five to seven years. It aims to provide Round the Clock with renewable energy and enhance grid stability by integrating solar…
Author: PPD Team Date: October 18, 2024 The International Energy Agency (IEA) highlighted the vulnerabilities in the global energy system, exacerbated by regional conflicts and geopolitical tensions, in its World Energy Outlook 2024. The IEA underscored the need for stronger policies and investments to hasten the energy transition. Despite these challenges, the agency expects a relatively abundant supply of various fuels and technologies in the coming years, including oil, LNG, solar PV, and batteries. IEA…