NHPC delays commissioning of Karnisar solar project to September
Author: PPD Team Date: August 26, 2025
Author: PPD Team Date: August 26, 2025
NHPC Limited has revised the timeline for completing its 300 MW Karnisar solar power project in Rajasthan. The remaining capacity is now expected to be commissioned by September 30, 2025, instead of the earlier target of August 31.
As of now, 214.28 MW of the project has been commissioned. In July, NHPC also began commercial operations of a 53.57 MW solar unit under Phase IV of its 1,000 MW grid-connected solar PV project in Bikaner. The unit became operational on June 30, 2025, under the Central Public Sector Undertaking (CPSU) Tranche-III program.
The 300 MW Karnisar project is located at Karnisar-Bhatiyan in Bikaner and is being executed by Tata Power Solar Systems Limited on an engineering, procurement, and construction basis.
Author: PPD Team Date: October 25, 2024 NLC India Limited (NLCIL) has entered into a joint venture agreement with Rajasthan Rajya Vidyut Utpadan Nigam Limited (RRVUNL) to establish a 3×125 MW lignite-based thermal power plant in Rajasthan, along with developing lignite mines to fuel the station. The initial paid-up capital for this project is set at Rs 500,000, with NLCIL holding a 74% stake and RRVUNL holding 26%. In addition, NLC India Renewables Limited, a…
Author: PPD Team Date: October 13, 2025 Toshiba JSW Power Systems, the Indian subsidiary of Toshiba, has secured a contract from NTPC Limited to deploy a centralised monitoring platform across 165 thermal and renewable energy facilities. The project marks NTPC’s first adoption of a centralised plant monitoring solution. The platform will be installed at NTPC-owned and joint venture sites, including projects still in the planning stage. It is scheduled to become operational between March and…
Author: PPD Team Date: August 7, 2025 The Ministry of New and Renewable Energy (MNRE) issued a clarification on 6 August 2025 regarding its revised guidelines for prototype wind turbine installations. The clarification pertains to clause 1(ii)(e) of the guidelines released on 12 June 2025. MNRE stated that the National Institute of Wind Energy (NIWE) may issue revised grid synchronisation recommendation letters for prototype wind turbines already recommended under earlier guidelines. However, this is allowed…
Author: PPD Team Date: December 6, 2024 Advait Energy Transitions has secured an order for the supply of 24 F optical ground wire (OPGW) cables on a turnkey basis for the 400 KV Kurukshetra-Malerkotla transmission line. The contract, awarded by NRSS XXXI (B) Transmission, includes both supply and installation under a build, own, and operate model. The project is scheduled to be completed within seven months.
Author: PPD Team Date: May 23, 2025 Adani Renewable Energy Fifty Seven Limited, a subsidiary of Adani Green Energy Limited (AGEL), started commercial operations of a 187.5 MW solar power project in Gujarat’s Khavda on May 22, 2025. The project is part of AGEL’s larger plan to develop a 30,000 MW wind-solar hybrid renewable energy park in the Rann of Kutch. The mega hybrid park will include 26,000 MW of solar and 4,000 MW of…
Author: PPD Team Date: July 18, 2025 A new report by the Save Ennore Creek Campaign, as reported by The New Indian Express, has found that Ennore’s thermal power plants either violated air pollution norms or failed to provide valid emissions data nearly 49% of the time during the winter season (November 2024 to January 2025). The findings raise serious concerns about enforcement by the Tamil Nadu Pollution Control Board (TNPCB). The report, titled Breathless…