Hinkley Point C installs first new nuclear reactor in over 30 years
Author: PPD Team Date: December 5, 2024
Author: PPD Team Date: December 5, 2024
Hinkley Point C, located in Somerset, southwest England, has achieved a significant milestone with the installation of Britain’s first new nuclear reactor in more than 30 years.
The installation of the first of two 13-metre-long reactor pressure vessels (RPV) is a key development. Once both reactors are operational, Hinkley Point C will supply 7% of Britain’s electricity. This follows the completion of the steel dome installation in late 2023, which sealed the reactor building. The last similar installation in the UK took place at Sizewell B in 1991.
UK Energy Secretary Ed Miliband hailed the RPV installation as a major step forward for the UK’s energy infrastructure. The RPV, a 500-tonne steel container, holds the nuclear fuel that generates heat and steam for the world’s largest turbine. Manufactured by Framatome in France, it arrived at the site in February 2023 and underwent careful installation using a polar crane to ensure precise alignment.
Hinkley Point C, once fully operational, will provide enough clean energy to power six million homes. The project is set to drive forward the UK’s energy independence, support net zero goals, and generate thousands of jobs. Installation of the second reactor and four steam generators is expected in 2025.
Author: PPD Team Date: May 21, 2025 Voith Hydro Private Limited has secured a contract valued at Rs 1,647.5 million for executing electromechanical (E&M) works for the Mankulam Hydro Electric Project in Kerala. The tender was issued by Kerala State Electricity Board (KSEB) in March 2024. The contract involves the completion of E&M works within two years. Located in Devikulam taluk of Idukki district, the Mankulam HEP – Phase I has an installed capacity of…
Author: PPD Team Date: December 19, 2024 Federal Bank has partnered with Ecofy, a green-focused NBFC backed by Eversource Capital, to offer financing solutions for MSMEs investing in rooftop solar installations. The program targets financing 3,600 kW of rooftop solar annually, focusing on installations in the 20-200 kW range, a segment often underserved by lenders. This initiative is expected to reduce over 2,500 tonnes of carbon emissions each year while addressing MSMEs’ financial barriers. Federal…
Author: PPD Team Date: July 10, 2025 Rajesh Power Limited has received a turnkey contract worth Rs 2.20 billion from Madhya Gujarat Vij Company Limited (MGVCL). The order involves the supply, installation, testing, and commissioning of 11 kV medium voltage covered conductor infrastructure. The work will be carried out across multiple locations in Gujarat under two state schemes, the Kisan Suryoday Yojana and the Vanbandhu Kalyan Yojana. Both programmes aim to improve power supply in…
Author: PPD Team Date: August 28, 2025 The Board of Directors of Jaiprakash Power Ventures Ltd (JPVL) has reviewed a proposal to develop a 50 MW solar photovoltaic (PV) power plant at its existing 500 MW Jaypee Bina Thermal Power Plant (JBTTP) site in Bina, Madhya Pradesh. The estimated investment for the project is around INR 300 crore. The company, incorporated in 1994, is part of the Jaypee Group and develops, implements, and operates power…
Author: PPD Team Date: November 18, 2025 Pace Digitek Limited has secured an EPC order worth Rs 9,297.57 million from Maharashtra State Power Generation Company Limited for a 200 MWAC solar project. The contract includes three years of O and M and forms part of a 300 MWAC development planned by the state utility. The project will be delivered on a turnkey basis. The scope covers design, engineering, manufacturing, supply, erection, installation, testing, and commissioning…
Author: PPD Team Date: October 30, 2024 The Central Electricity Regulatory Commission (CERC) has approved the annual transmission tariff of Rs 2.91 billion for Sirohi Transmission Ltd, a wholly-owned subsidiary of Power Grid Corporation of India Ltd (PGCIL), for its ISTS scheme. This project, named “Transmission system for evacuation of power from Rajasthan REZ Phase IV (Part 2: 5.5 GW) (Jaisalmer/Barmer Complex) Part B,” was awarded to PGCIL under the tariff-based competitive bidding (TBCB) process….