GE Vernova selects Worley Chemetics to design key component of BWRX-300 SMR
Author: PPD Team Date: November 4, 2024
Author: PPD Team Date: November 4, 2024
GE Vernova’s nuclear division, GE Hitachi Nuclear Energy (GEH), has appointed Worley Chemetics to design and fabricate the isolation condenser system for its BWRX-300 small modular reactor (SMR).
This partnership brings Worley Chemetics into the BWRX-300 qualified supplier group, enhancing Ontario’s nuclear supply chain with its fabrication facility in Pickering, Canada.
Worley Chemetics’ president, Andrew Barr, expressed enthusiasm for the collaboration, highlighting its 60-year experience in sustainable process technologies and recent ASME nuclear certification. Ontario Power Generation (OPG) and GEH, along with AtkinsRéalis and Aecon Construction Group, plan to construct four 300MW BWRX-300 units at OPG’s Darlington site. With site preparations underway, construction is expected to start next year, targeting commercial operation by 2029.
The BWRX-300 is a cornerstone of GE Vernova’s energy transition strategy, incorporating NRC-certified design elements to meet decarbonisation goals and reduce construction and operating costs. Sean Sexstone, GEH’s EVP, emphasized that the isolation condenser system’s passive safety feature is central to the reactor’s design.
Image Credit: GE Vernova
Author: PPD Team Date: November 5, 2025 NTPC Limited has announced the start of commercial operations for Unit 1 (800 MW) of the Patratu Super Thermal Power Project (STPP) Phase I, developed by its subsidiary Patratu Vidyut Utpadan Nigam Limited (PVUNL). The unit achieved commercial operation at 00:00 hours on November 5, 2025. With this addition, the NTPC Group’s total installed and commercial capacity has reached 84,849 MW. Unit 1 had earlier been synchronized with…
Author: PPD Team Date: November 29, 2024 Egypt’s General Authority for Investment and Free Zones (GAFI) has partnered with Polish firm Hynfra to establish a green ammonia production facility with an initial investment of $1.6 billion. The plant’s first phase will operate entirely on renewable energy, including solar and wind power. Surplus electricity will feed Egypt’s national grid, while the facility exports green ammonia to the European Union under long-term agreements. The project is part…
Author: PPD Team Date: December 4, 2025 NHPC Limited has achieved test synchronisation of the 250 MW Unit 2 of the 2,000 MW Subansiri Lower Hydroelectric Project with the national grid on 2 December 2025. The company expects the commercial operation date for Unit 2 by this month. The synchronisation marks a key step in the phased commissioning of the eight-unit project. NHPC leadership, including CMD Bhupender Gupta, Government Nominee Director Mohammad Afzal, directors from…
Author: PPD Team Date: March 12, 2025 Power Grid Corporation of India Limited (PGCIL) has awarded multiple contracts for transmission projects in Rajasthan and Uttar Pradesh. Vikran Engineering & Exim Private Limited secured a contract worth Rs 825.54 million for the 400 kV AIS substation package SS-134 under the Transmission System for Evacuation of Power from Renewable Energy Zones (REZ) in Rajasthan (20 GW) Phase-III Part B1. The scope includes the augmentation of transformation capacity…
Author: PPD Team Date: November 7, 2024 India’s energy storage capacity is projected to increase 12-fold to 60 GW by FY 2032, as outlined in a new SBICAPS report. This expansion is anticipated to outpace the growth in renewable energy (RE) sources, as RE tenders increasingly include storage, rising from 5% of projects in FY 2020 to 23% by FY 2024. Battery energy storage systems (BESS) are expected to make up the majority of this…
Author: PPD Team Date: August 7, 2025 Juniper Green Energy has commissioned 25 MW of wind capacity at Dev Bhumi Dwarka, Gujarat. The plant is part of its 50 MW wind power project being developed through subsidiary Juniper Green Beam Private Limited. This milestone was reached nearly three months before the scheduled commercial operation date of October 17, 2025. The full 50 MW project is backed by a power purchase agreement with Gujarat Urja Vikas…