GE Power secures orders from NTPC and MP Power
Author: PPD Team Date: February 24, 2025
Author: PPD Team Date: February 24, 2025
GE Power India Limited has received work orders worth Rs 403.38 million from NTPC Limited and M.P. Power Generating Company Limited for supplying steam turbine parts and boiler panel services.
The order from NTPC Limited involves supplying steam turbine parts for the Talcher site, to be executed over 15 months. The order from M.P. Power Generating Company Limited includes boiler panel services, scheduled for completion within 80 days.
Earlier in February 2025, GE Power India secured a Rs 162.25 million contract from NTPC to supply generator parts for a thermal power project in Telangana.
Author: PPD Team Date: December 31, 2024 Servotech Renewable Power System Limited has secured an order to install 1,094 grid-connected solar-powered agriculture pumps under the PM KUSUM Scheme’s Component C-1. The Uttar Pradesh New and Renewable Energy Development Authority (UPNEDA) awarded the project, valued at approximately Rs 310 million. The project includes manufacturing, supply, installation, testing, and commissioning of solar pumps, along with solar power plants. Servotech will also provide a five-year warranty and maintenance…
Author: PPD Team Date: February 5, 2025 Lords Mark Industries Private Limited has won a contract from the Uttar Pradesh New and Renewable Energy Development Agency (UPNEDA) to set up 300 MW of grid-connected rooftop solar power plants under the Renewable Energy Service Company (RESCO) model. The firm secured the contract at a tariff of Rs 4.8 per kWh. The contract is part of a larger initiative initiated by UPNEDA in July 2024, initially calling…
Author: PPD Team Date: October 9, 2025 Juniper Green Energy Limited has entered a power purchase agreement (PPA) with Tata Power for a 70 MW firm and dispatchable renewable energy (FDRE) project through its subsidiary, Juniper Green Sigma Eight. The project, based in Maharashtra, will include 180 MWp of combined solar and wind capacity, paired with a 280 MWh battery energy storage system. Power supply from the project is expected to begin on September 22, 2027. Ankush Malik,…
Author: PPD Team Date: June 10, 2025 NTPC Limited commissioned 193 MW under the 245 MW Plot-3 of its 735 MW Nokh Ultra Mega Solar Project on June 9, 2025. The project is located in Nokh, Jaisalmer, Rajasthan. With this commissioning, NTPC has brought 438 MW of solar capacity online at the Nokh site. The project is being implemented in three phases, each with a capacity of 245 MW. The full 735 MW capacity forms…
Author: PPD Team Date: November 21, 2024 Renewable infrastructure developer Field Energy has acquired the 200MW Hartmoor battery storage project from Clearstone Energy, expanding its 11GW portfolio of battery storage projects across Europe. Located near Hartlepool, County Durham, the Hartmoor facility can store 800MWh of electricity, enough to power 500,000 homes for four hours when fully charged. The Hartmoor project will play a critical role in balancing electricity supply and demand, stabilizing the grid, and…
Author: PPD Team Date: October 15, 2024 Ahead of the 29th Conference of the Parties (COP29) to the UN Framework Convention on Climate Change, global leaders gathered in Baku, Azerbaijan, for the pre-COP meeting from 10–11 October. The session, titled Enhance Ambition and Enable Action, aimed to progress key negotiations before the main summit in November. The event is focused on limiting global warming to 1.5°C, as per the 2015 Paris Agreement. A key priority…