Bajel Projects Limited, formerly Bajaj Electricals Limited, has commissioned two key transmission line packages totaling 132.65 km.
The Raipur Pool–Dhamtari (CKT-I and CKT-II) line spans 88.65 km. It was developed under the Western Region Expansion Scheme-XXVIII (WRES-XXVIII).
The Navsari–Magarwada (CKT-I and CKT-II) line spans 44 km. It is part of the Western Region Expansion Scheme-XXIX (WRES-XXIX) and the Transmission Network Expansion in Gujarat to increase ATC from ISTS – Part B.
Power Grid Corporation of India Limited (PGCIL) is the implementing agency for these projects.
Author: PPD Team Date: January 2, 2025 NTPC Limited has declared the results for its 1,200 MW wind-solar hybrid (Hybrid 02) ISTS-connected projects, with an additional greenshoe option of up to 600 MW. JSP Green (Jindal Renewables): 350 MW at Rs 3.38 per kWh. Adyant Enersol (Datta Infra): 150 MW at Rs 3.44 per kWh. Green Prairie Energy IV (EverGreen Power): 200 MW at Rs 3.44 per kWh. AMPIN Energy Utility: 150 MW at Rs…
Author: PPD Team Date: September 29, 2025 Waaree Energies Limited has announced that its wholly owned subsidiary, Waaree Power Private Limited (WPPL), has signed a definitive share subscription and shareholders’ agreement to acquire a 76 per cent stake in Racemosa Energy (India) Private Limited. The aggregate consideration for the transaction is approximately Rs 53 crore. The company stated that the acquisition, disclosed earlier on September 18, 2025, is subject to the fulfilment of conditions precedent….
Author: PPD Team Date: September 1, 2025 Meenakshi Energy Limited (MEL), a subsidiary of Vedanta, has announced the full operationalisation of its 1,000 MW thermal power project in Tirupati, Andhra Pradesh. The commissioning was completed within two years of Vedanta’s acquisition of the asset through the insolvency process. The plant comprises two 350 MW units and two 150 MW units. The 150 MW units were stabilised earlier this year, followed by the commissioning of the…
Author: PPD Team Date: November 21, 2024 CBMM has inaugurated a state-of-the-art niobium-based anode production facility in Araxá, Brazil, marking a milestone in advanced battery technology. The plant will produce 2,000 tonnes of Echion Technologies’ XNO active anode material annually, equivalent to one gigawatt-hour of lithium-ion battery cells. This facility is the largest of its kind globally and aims to serve the rapidly growing demand for niobium-enhanced battery materials, particularly in electric vehicles (EVs), heavy-duty…
Author: PPD Team Date: October 28, 2024 Copenhagen Energy and PetroGreen Energy Corporation have obtained the Green Lane Certificate from the Philippine Board of Investments for their joint floating offshore wind projects under BuhaWind Energy Philippines. This certification will accelerate the permit process, facilitating faster development of their planned 4 GW offshore wind farms. The initiative includes three projects: A 2 GW wind farm in Northern Luzon, targeted for operation by 2030. A 1 GW…
Author: PPD Team Date: October 27, 2025 Waaree Energies Limited has received new solar module orders totalling 692 MW from domestic and international customers, as per a regulatory filing dated October 24, 2025. The company informed that its domestic division secured three orders of 220 MW, 210 MW, and 140 MW from leading players in India’s renewable energy sector. Its wholly owned subsidiary, Waaree Solar Americas, also received an order for 122 MW from a…