PGCIL completes delayed interstate transmission system for Rajasthan’s solar energy zones
Author: PPD Team Date: September 16, 2024
Author: PPD Team Date: September 16, 2024
Power Grid Corporation of India Ltd (PGCIL) recently commissioned an interstate transmission system (ISTS) under “Powergrid Bhadla Transmission Ltd.” The project, officially named the “Transmission system strengthening scheme for evacuation of power from solar energy zones in Rajasthan (8.1 GW) under Phase-II, Part B,” was completed in August 2024, nearly two years behind schedule.
This Rs 11.06 billion scheme, awarded to PGCIL under the Tariff-Based Competitive Bidding (TBCB) route, involved the construction of a 405-ckm 765kV double-circuit line from the Fatehgarh-II Pooling Station to Bhadla-II Pooling Station. It also included two 765kV line bays at Bhadla-II for the line’s termination.
The project faced delays due to concerns about the transmission line passing through areas inhabited by the endangered Great Indian Bustard (GIB). In July 2022, a Supreme Court-appointed committee cleared the project but required a rerouting, which added 25 ckm to the original line length and increased the project cost by over 50%, from an initial estimate of Rs 7.14 billion.
This ISTS scheme is part of a broader initiative to build transmission infrastructure for evacuating 20 GW of power from Rajasthan’s solar energy zones. PGCIL won the project by quoting an annualized tariff of Rs 728.93 million during an e-reverse auction held in January 2021.
Author: PPD Team Date: November 21, 2025 NTPC Green Energy Limited has signed an MoU with The Singareni Collieries Company Limited to work together on renewable energy development. The agreement was signed on November 19, 2025 in Hyderabad and will focus on solar, wind, and hybrid projects, along with other green technologies. The MoU was exchanged in the presence of Sh. N Balram, Chairman and Managing Director of SCCL, and senior representatives from both sides….
Author: PPD Team Date: February 10, 2026 Oswal Pumps Limited reported strong financial performance for the third quarter and the first nine months of FY26. For the nine-month period ended FY26, total income rose to Rs 15,692 million, reflecting a 47.0% increase compared to the same period last year. Profit after tax (PAT) stood at Rs 2,837 million, translating into a margin of 18.1%. In Q3 FY26, total income reached Rs 5,077 million, up 33.4%…
Author: PPD Team Date: December 10, 2024 Waaree Energies Limited has secured a 1 GW solar photovoltaic (PV) modules supply order from an Indian renewable energy company. The customer is engaged in owning, developing, and operating renewable power projects across India. The supply of these modules is planned for delivery during the financial years 2024-25 and 2025-26.
Author: PPD Team Date: April 15, 2025 The Ministry of New and Renewable Energy (MNRE) has released revised draft guidelines for the installation and certification of prototype wind turbines in India. The new framework allows manufacturers up to three years to complete type testing and secure certification from internationally accredited agencies. The National Institute of Wind Energy (NIWE), Chennai, will implement the framework. Prototype turbines will be installed only for type testing. NIWE will issue…
Author: PPD Team Date: August 4, 2025 The Supreme Court has directed key power sector agencies to submit a coordinated plan to reduce carbon emissions from coal-fired power plants, citing the sector’s major role in worsening air quality and climate change. The order came in response to a civil appeal (No. 388/2021) filed by climate activist Ridhima Pandey. The Bench called climate change an “existential global predicament” and noted that power generation contributes 8 per…
Author: PPD Team Date: September 12, 2024 GE Vernova has secured a 140 MW wind turbine order in Romania from Public Power Corporation Renewables (PPCR). The company will supply, install, and commission 23 turbines, each with a 6.1MW capacity, for a wind project in Vaslui County. The agreement, finalized in Q2 2024, strengthens GE Vernova’s role in the European Union’s energy transition, where it has a long history of installing wind turbines. Initial turbine deliveries…