Solarworld wins Rs 267.5 crore BOS contract for NTPC Bikaner solar block
Author: PPD Team Date: April 2, 2026
Author: PPD Team Date: April 2, 2026
Solarworld Energy Solutions Limited has received a letter of award from NTPC Renewable Energy Limited for the balance of system package for Block-IX, a 200 MWac block under NTPC’s 1,000 MW grid-connected solar PV project at Bikaner, Rajasthan.
The contract, valued at approximately Rs 267.53 crore including taxes, was awarded on March 31, 2026, and carries an execution timeline of 19 months. The scope also includes three years of comprehensive operations and maintenance of the solar PV plant.
The 1,000 MW Bikaner project comprises two blocks of 300 MW each and two blocks of 200 MW each. Solarworld’s award covers one of the 200 MW blocks under bidding document NRE-CS-5800-004(BOS1)-9.
The contract adds to a growing order book for Solarworld from NTPC. The company has also secured BESS EPC contracts from NTPC Limited worth approximately Rs 285 crore in the latest round of awards issued on March 30, 2026, covering a 50 MW/100 MWh system at Feroze Gandhi Unchahar Thermal Power Station in Uttar Pradesh and a 75 MW/150 MWh system at Solapur Super Thermal Power Station in Maharashtra. Solarworld had earlier won a Rs 314.26 crore BESS contract at Solapur under Lot-1, taking its total NTPC BESS pipeline at that station past Rs 491 crore.
The featured photograph is for representation only.
Author: PPD Team Date: November 12, 2024 Inox Wind Limited (IWL) has secured an 87 MW order from Continuum Green Energy for its 3 MW Wind Turbine Generators (WTGs). This repeat order will be executed on turnkey basis, with IWL providing multi-year operations and maintenance services post-commissioning. The projects are slated for Gujarat and Rajasthan. This addition brings Continuum’s total orders with IWL to approximately 700 MW and elevates IWL’s order book to over 3.4…
Author: PPD Team Date: April 25, 2025 Gujarat Industries Power Company Limited (GIPCL) has commissioned 25 MW of a 75 MW captive solar photovoltaic (PV) power project at Vastan, Gujarat on April 24, 2025. The full project is being developed by Madhav Infra Projects Private Limited on an engineering, procurement, and construction (EPC) basis. It spans 140 hectares within the mining lease area of the Vastan Lignite Mine near the Surat Lignite Power Plant. This…
Author: PPD Team Date: February 18, 2026 Saatvik Green Energy Limited has announced that its material subsidiary, Saatvik Solar Industries Private Limited, has received and accepted an order worth Rs 44.10 crore for the supply of solar photovoltaic (PV) modules. The order is scheduled for execution by March 2026. In a regulatory disclosure, the company stated that the contract has been awarded by a domestic entity. The customer has been described as a prominent Independent…
Author: PPD Team Date: March 19, 2025 The Committee of Directors (CoD) on investment of projects at Power Grid Corporation of India Limited (PGCIL) has approved two major transmission projects, with a total investment of Rs 3.41 billion. The approval was granted on March 13, 2025. The first project “Transmission scheme for evacuation of power from Ratle HEP (850 MW) & Kiru HEP (624 MW): Part-B in Jammu & Kashmir” is divided into two parts:…
Author: PPD Team Date: October 31, 2025 Larsen & Toubro (L&T) has secured a major role in TenneT’s High Voltage Direct Current (HVDC) offshore wind program. TenneT, the Dutch-German transmission system operator, nominated L&T in collaboration with Hitachi Energy to deliver advanced HVDC converter stations that will support renewable energy integration across the North Sea. The project aims to accelerate the transmission of large-scale renewable power into the European grid, particularly across German and Dutch…
Author: PPD Team Date: December 4, 2024 The National Committee on Transmission (NCT) recently approved the Eastern Region Expansion Scheme-44 (ERES-44), estimated to cost Rs 3.85 billion, to be executed by Power Grid Corporation of India Ltd (PGCIL) under the Regulated Tariff Mechanism (RTM). The project will modernize the ageing 220 kV transmission network in the Eastern region, including cross-border lines with Bhutan. It involves replacing existing conductors with High-Temperature Low Sag (HTLS) conductors, capable…