Waaree incorporates two new IPP subsidiaries
Author: PPD Team Date: December 17, 2025
Author: PPD Team Date: December 17, 2025
Waaree Energies Limited announced on 16 December 2025 that its wholly owned subsidiary, Waaree Forever Energies Private Limited, has incorporated two new wholly owned subsidiaries, Windora Energy Private Limited and Agni Vayu Energy Private Limited.
The two entities were incorporated in India on 16 December 2025 and are registered with the Registrar of Companies (RoC), Mumbai. Both companies have been classified as Independent Power Producers (IPPs) and have been established solely to facilitate and hold specific power projects.
As per the regulatory disclosure, Waaree Forever Energies Private Limited holds 100 percent of the share capital in both Windora Energy Private Limited and Agni Vayu Energy Private Limited. The companies are newly incorporated and have not yet commenced business operations, resulting in nil turnover. The formation does not constitute a related party transaction.
The latest incorporations add to Waaree Energies’ recent expansion of its IPP structure. Earlier in December 2025, the company incorporated Eco Flux Renewables Private Limited and Solaris Horizon Energy Private Limited as step down subsidiaries through Waaree Forever Energies Private Limited, taking the total number of IPP focused subsidiaries incorporated this month to four.
The featured photograph is for representation only.
Author: PPD Team Date: September 12, 2025 The central government is preparing a carbon capture, utilisation, and storage (CCUS) programme estimated at Rs 38,900 crore, with Rs 19,500 crore to be committed from public funds. The balance is expected to be raised through bank loans and multilateral financing. According to officials, the programme will be structured into multiple sub-schemes. Research and development projects may receive full government support, while other initiatives could be funded between…
Author: PPD Team Date: November 14, 2024 PFC Consulting Limited (PFCCL) has established Wahipora and Sallar Transmission Limited for the transmission project involving the construction of grid substations at Wahipora and Sallar in Kashmir. The project encompasses the downstream transmission network from the upcoming 400/220 kV Grid Sub-Station at Siot, Rajouri, as well as a new 220 kV grid substation at Bhagthali, Kathua, including a 220 kV line and Line-In Line-Out (LILO) tapping from the…
Author: PPD Team Date: July 1, 2025 NTPC Renewable Energy Limited (NTPC REL), a subsidiary of NTPC Limited, has begun commercial operations of 120 MW under Phase-III of the 220 MW Unit-2 solar project. This phase went live on June 29, 2025. With this, NTPC REL has fully commissioned the 325 MW Shajapur Solar Power Park Project in Madhya Pradesh. The project consists of two units—Unit-1 with 105 MW and Unit-2 with 220 MW—of grid-connected…
Author: PPD Team Date: November 28, 2024 The Western Australian (WA) government has completed the second phase of the Kwinana big battery project, marking a major milestone in the region’s energy transition. This phase involved constructing an A$661 million ($428 million) battery energy storage system (BESS) with a capacity of 800 MWh and a 200 MW output capability, supported by 288 battery modules and 72 inverter units. Construction, which began in July 2023, created 200…
Author: PPD Team Date: November 14, 2024 Ormat Technologies has signed a $200 million engineering, procurement, and construction (EPC) contract with Contact Energy for the development of the 101 MW Te Mihi Stage 2 geothermal power plant in New Zealand. Scheduled for completion by mid-2027, this project will contribute to New Zealand’s renewable energy goals by gradually replacing the 1950s-built Wairakei geothermal power station. Te Mihi Stage 2 marks Ormat’s fourth major project in New…
Author: PPD Team Date: July 9, 2025 H&H Aluminium has inaugurated its new solar frame manufacturing plant in Rajkot, Gujarat. The facility has a manufacturing capacity of 24,000 metric tonnes per annum and can support up to 6 GW of solar installations annually. The company has invested approximately Rs 1.5 billion in the new plant. Trial production began in June 2025. Commercial operations are expected to commence within a month. Once fully operational, the plant…