Tata Power to restart 4 GW Mundra plant after Gujarat PPA approval
Author: PPD Team Date: March 23, 2026
Author: PPD Team Date: March 23, 2026
Tata Power’s long-idled Mundra thermal power plant is set to resume operations after the Gujarat cabinet approved a Supplementary Power Purchase Agreement for the facility. The company confirmed to stock exchanges on March 20 that the government order has been issued and that the formal agreement with Gujarat Urja Vikas Nigam Limited will be signed once the remaining regulatory clearances are in place.
The Mundra plant, one of India’s largest imported coal-based power facilities with a capacity of around 4 GW, had been shut for roughly nine months, during which it was accumulating significant cash losses. The key financial sticking point had been coal cost recovery; the revised agreement is structured as a pass-through arrangement, meaning fuel costs will no longer be absorbed by Tata Power, removing the primary reason the plant had become unviable to operate.
The restart is expected to eliminate cash losses that had been running at several hundred crore rupees per year and contribute positively to Tata Power’s EBITDA. The company has indicated that power generation could resume shortly, ahead of peak summer demand.
Beyond Gujarat, Tata Power has indicated discussions are ongoing with other procurer states for similar agreements, which could unlock the plant’s full 4 GW capacity for the grid.
Author: PPD Team Date: October 21, 2024 Himachal Pradesh Chief Minister Sukhvinder Singh Sukhu visited the historic 110 MW Shanan Power House in Mandi district, emphasizing the need for its control to be transferred to the Himachal Pradesh government following the expiration of the lease period. Although the power house is currently operated by the Punjab government, Sukhu mentioned that discussions are ongoing regarding its handover. He noted that the Shanan project, built over a…
Author: PPD Team Date: August 27, 2025 Power Grid Corporation of India Limited (PGCIL) has cleared a new investment proposal worth Rs 209.38 crore for strengthening transmission infrastructure in the North-Eastern region. The project, named North-Eastern Region Expansion Scheme-XXIII (NERES-XXIII), was approved by the company’s Committee of Directors on Investment on Projects on August 26, 2025. According to the regulatory filing, the scheme is expected to be completed within 30 months from the date of…
Author: PPD Team Date: February 12, 2026 Jupiter International Ltd has commissioned a 1 GW mono-PERC solar cell manufacturing unit in Baddi, Himachal Pradesh, increasing its total installed solar cell capacity to approximately 2 GW. The new facility, set up by its wholly owned subsidiary Jupiter Solartech Pvt Ltd, is located in Village Katha in Solan district. It is the company’s third solar cell manufacturing unit and adds to its existing 959 MW capacity. The…
Author: PPD Team Date: October 8, 2025 Hero Future Energies (HFE), through its special purpose vehicle Clean Renewable Energy Hybrid Three Private Limited, has raised Rs 1,908 crore in funding from the State Bank of India (SBI) and Canara Bank to develop a 120 MW hybrid renewable energy project in Kurnool, Andhra Pradesh. The project, contracted with SJVN, will integrate wind, solar, and storage systems to deliver reliable peak power. The loan carries a repayment…
Author: PPD Team Date: November 21, 2024 GE Vernova, Inc. has announced a definitive agreement to acquire Woodward, Inc.’s heavy-duty gas turbine combustion parts business in Greenville, South Carolina. The acquisition aligns with GE Vernova’s strategy to invest in U.S. manufacturing and strengthen its domestic supply chain to meet the growing global demand for heavy-duty gas turbines and upgrades. Eric Gray, President & CEO of GE Vernova’s Gas Power business, emphasized the importance of integrating…
Author: PPD Team Date: June 24, 2025 The Electric Power Transmission Association (EPTA) has asked the government to ease the planned phase-out of the interstate transmission system (ISTS) waiver, set to begin on July 1, 2025. EPTA warned that the proposed 25% yearly withdrawal could disrupt projects and raise costs for commercial and industrial (C&I) consumers. It suggested a slower 10% annual phase-out and a milestone-based relief for delayed but advanced projects. The association requested…