THDCIL lowers Unit-1 stator at VPHEP ahead of commissioning
THDC India Limited (THDCIL) has lowered the fully assembled stator of Unit-1 at the (4×111) MW Vishnugad-Pipalkoti Hydro Electric Project (VPHEP) on April 15, 2026. The development marks a key construction milestone and advances the project towards commissioning. The milestone was virtually attended by Sh. Sipan Kumar Garg, Chairman & Managing Director, THDCIL, who acknowledged the project team’s efforts. He stated that the progress reflects THDCIL’s continued focus on sustainable hydropower development and its role…