Author: PPD Team Date: 12/03/2025

APTEL upholds transmission charges liability for UPRVUNL, UPPTCL

The Appellate Tribunal for Electricity’s (APTEL) ruled on appeals by Uttar Pradesh Rajya Vidyut Utapadan Nigam Limited (UPRVUNL) and Uttar Pradesh Power Transmission Corporation Limited (UPPTCL) against an Uttar Pradesh Electricity Regulatory Commission (UPERC) order dated 24 June 2024. The case involved liability for transmission charges of specific transmission elements developed by Obra-C Badaun Transmission Limited (OCBTL), a transmission service provider under a Tariff-Based Competitive Bidding process.

UPRVUNL challenged its liability for transmission charges of Element 1 of Lot 1 from 30 April 2021 until the operationalization of the Obra-C Thermal Power Station (TPS) switchyard. It argued that it was neither a signatory to the Transmission Service Agreement (TSA) nor was any specific relief sought against it in the petition. However, UPERC ruled that UPRVUNL was a defaulting entity as the delay in commissioning the Obra-C TPS led to the non-utilization of the transmission element.

UPPTCL contested its responsibility for transmission charges of Element 9 of Lot 2 from 10 June 2022 to 26 April 2023, arguing that the 400 kV Jaunpur substation’s delay was due to land acquisition and COVID-19 disruptions. The tribunal upheld UPERC’s decision, stating that as the State Transmission Utility (STU), UPPTCL was responsible for planning and coordinating transmission infrastructure and should have ensured timely availability of interconnection facilities.

The tribunal upheld the UPERC order, affirming that UPRVUNL and UPPTCL must bear the transmission charges for the respective periods due to delays in their infrastructure, which prevented power flow. The appeals were dismissed.

Petition No: APL No. 357 OF 2024 & IA No. 1368 OF 2024 & APL No. 369 OF 2024 & IA No. 1377 OF 2024 & IA No. 1638 OF 2024 | Read the full order here.

APTEL directs MSERC to reconsider MePTCL’s tariff dispute over RoE

The Appellate Tribunal for Electricity’s (APTEL) has ruled in favor of Meghalaya Power Transmission Corporation Limited (MePTCL) in a case challenging the Meghalaya State Electricity Regulatory Commission’s (MSERC) tariff order. The appeal, filed in 2017, contested the MSERC’s computation of Return on Equity (RoE) for the financial years 2013-14 and 2014-15.

The dispute arose when MSERC approved an RoE of Rs. 151.7 million for 2013-14 and Rs. 152.1 million for 2014-15, significantly lower than MePTCL’s claims of Rs. 469.5 million and Rs. 514.5 million, respectively. MePTCL argued that the Commission incorrectly calculated the equity base using Gross Fixed Assets (GFA), contrary to the Tariff Regulations, 2011.

The Tribunal, referencing its earlier judgment in a similar case, found that MSERC failed to consider equity additions resulting from the transfer of assets from the erstwhile Meghalaya State Electricity Board (MeSEB) to MePTCL. The Tribunal emphasized that the equity base should reflect the audited balance sheet or transfer scheme notifications, as per Regulation 101 of the Tariff Regulations.

In its final order, the Tribunal set aside the MSERC’s 2016 tariff order and remanded the matter back to the Commission for fresh consideration, directing it to account for the equity additions due to the transfer scheme. The appeal was allowed.

Petition No: APPEAL No. 361 OF 2017 | Read the full order here.

CERC approves trued-up transmission tariff for 2019-24 and new tariff for 2024-29 for SPS in Northern Regional Grid

The Central Electricity Regulatory Commission (CERC) has approved the trued-up transmission tariff for the 2019-24 period and determined the tariff for the 2024-29 period for the Special Protection Scheme (SPS) for the Northern Regional Grid Stage-II. The petition was filed by the Power Grid Corporation of India Limited (PGCIL), which operates the transmission asset.

The CERC, in its order dated February 25, 2025, allowed the trued-up Annual Fixed Charges (AFC) for the 2019-24 period, which included depreciation, interest on loan, return on equity, and interest on working capital. The total AFC for the 2019-24 period ranged from Rs 28.94 million in 2019-20 to Rs 25.07 million in 2023-24.

For the 2024-29 tariff period, the CERC approved the AFC, which included depreciation, interest on loan, return on equity, and interest on working capital. The total AFC for the 2024-29 period ranged from Rs 40.84 million in 2024-25 to Rs 10.98 million in 2026-27 and beyond.

The CERC also allowed PGCIL to recover filing fees, publication expenses, and other charges from the beneficiaries. Additionally, PGCIL was permitted to file separate petitions for security expenses, insurance, and capital spares for the 2024-29 period, as per the 2024 Tariff Regulations.

The order emphasized that the transmission charges would be shared among the beneficiaries in accordance with the 2020 Sharing Regulations. The CERC also noted that any future Goods and Services Tax (GST) on transmission services would be billed separately to the beneficiaries.

Petition No: 157/TT/2025 | Read the full order here.

CERC approves trued-up transmission tariff for Hathidah River Crossing and sets new tariff for 2024-29

The Central Electricity Regulatory Commission (CERC) has issued an order approving the truing-up of the transmission tariff for the Hathidah River Crossing Section of the 220 kV Biharsharif-Begusarai Transmission Line for the 2019-24 period and determining the tariff for the 2024-29 period. The petition was filed by the Power Grid Corporation of India Limited (PGCIL), seeking approval under the Electricity Act, 2003, and the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019 and 2024.

The transmission asset, operational since March 2001, serves the Eastern Region, benefiting various state power distribution companies and transmission licensees. PGCIL sought truing-up of the tariff for the 2019-24 period and determination of the tariff for the 2024-29 period, including claims for depreciation, interest on loans, return on equity, operation and maintenance (O&M) expenses, and interest on working capital.

The CERC approved the trued-up annual fixed charges for the 2019-24 period, with total charges ranging from Rs 5.042 million to Rs 5.185 million annually. For the 2024-29 period, the annual fixed charges were set between Rs 5.010 million and Rs 5.033 million. The commission also allowed PGCIL to recover filing fees, publication expenses, and RLDC fees from beneficiaries. Additionally, PGCIL was permitted to file separate petitions for security expenses, insurance, and capital spares for the 2024-29 period.

The order emphasized that any future Goods and Services Tax (GST) on transmission charges would be billed separately. The commission also noted that PGCIL could recover expenses related to the Central Transmission Utility of India Limited (CTUIL) through a separate petition.

This decision ensures the continued operation and maintenance of the critical transmission infrastructure, supporting power distribution in the Eastern Region. The order aligns with the 2019 and 2024 Tariff Regulations, ensuring fair recovery of costs while maintaining regulatory compliance.

Petition No: 481/TT/2024 | Read the full order here.

CERC approves transmission tariff for nine OPTCL lines for 2014-19 period, excludes two lines

The Central Electricity Regulatory Commission (CERC) has approved the transmission tariff for nine non-ISTS (Inter-State Transmission System) lines owned by Odisha Power Transmission Corporation Limited (OPTCL) for the 2014-19 period. The order, dated February 26, 2025, addresses the inclusion of these lines in the computation of Point of Connection (PoC) charges and losses under the 2010 Sharing Regulations.

OPTCL had filed the petition seeking approval for the Annual Fixed Charge (AFC) and Yearly Transmission Charge (YTC) for the nine transmission lines, which carry ISTS power. The lines, ranging from 132 kV to 400 kV, were certified by the Eastern Regional Power Committee (ERPC) as carrying inter-state power. However, two of the lines, the 220 kV Rengali-Rengali and 220 kV Balimela PH-Upper Sileru, were excluded from tariff approval due to lack of power flow during the 2014-19 period.

The CERC determined the tariff based on a normative methodology, considering a 35-year useful life for the transmission lines, as per the Appellate Tribunal for Electricity’s (APTEL) ruling. The capital cost for the lines was derived using historical data from Power Grid Corporation of India Limited (PGCIL), with adjustments for older assets. The O&M expenses were calculated as per the 2014 Tariff Regulations.

The final order allows tariff recovery for seven of the nine lines, with the transmission charges to be adjusted against the Annual Revenue Requirement (ARR) approved by the Odisha Electricity Regulatory Commission. The CERC also directed the ERPC to verify the availability of these lines and link tariff recovery to their operational status.

Petition No: 288/TT/2023 | Read the full order here.

CERC approves transmission tariff for Southern Region System Strengthening Scheme-XVIII for 2019-29

The Central Electricity Regulatory Commission (CERC) has approved the transmission tariff for the Southern Region System Strengthening Scheme-XVIII, filed by the Power Grid Corporation of India Limited (PGCIL). The order, dated February 26, 2025, covers the truing up of tariffs for the 2019-24 period and the determination of tariffs for the 2024-29 period.

The scheme includes several key transmission assets, such as the 400 kV Vijayawada-Nellore line, the 400 kV Thiruvalam-Melakottaiyur line, and the LILO of the Bangalore-Salem line, among others. These assets were commissioned in 2014 and are critical for strengthening the Southern Region’s power transmission network.

PGCIL had filed the petition seeking approval for the Annual Fixed Charges (AFC) for these assets, including depreciation, interest on loans, return on equity, and operation and maintenance expenses. The CERC, after reviewing the submissions, approved the revised trued-up AFC for the 2014-19 period and determined the AFC for the 2019-24 and 2024-29 tariff periods.

The Commission also allowed PGCIL to recover filing fees, publication expenses, and other charges from the beneficiaries. Additionally, PGCIL was permitted to file separate petitions for security expenses, insurance, and capital spares, which will be considered under the 2024 Tariff Regulations.

The transmission charges will be recovered in accordance with the 2020 Sharing Regulations, and the billing and collection will be managed as per the provisions of the 2019 and 2024 Tariff Regulations.

Petition No: 354/TT/2024 | Read the full order here.

CERC approves amendment to POWERGRID Ramgarh Transmission Limited’s licence for Fatehgarh-III substation project

The Central Electricity Regulatory Commission (CERC) has approved an amendment to the existing transmission licence of POWERGRID Ramgarh Transmission Limited (PRTL) to include the “Augmentation of transformation Capacity at 400/220 kV Fatehgarh-III PS (Section-1) by 400/220 kV, 1×500 MVA ICT (5th)” project. The amendment was sought under the Regulated Tariff Mechanism (RTM) following an Office Memorandum (OM) issued by the Central Transmission Utility of India Limited (CTUIL) on October 26, 2023.

The project, estimated to cost Rs 581.8 million, aims to enhance the transformation capacity at the Fatehgarh-III substation to meet the N-1 reliability criteria as per the Central Electricity Authority’s (CEA) Transmission Planning Criteria 2023. The augmentation is critical for ensuring the reliable evacuation of power from renewable energy zones in Rajasthan, particularly for projects with a cumulative capacity of 1980 MW connected to the substation.

PRTL, a wholly-owned subsidiary of Power Grid Corporation of India Limited (PGCIL), had previously been granted a transmission licence for other RTM projects. The current amendment allows PRTL to implement the new project under the RTM mode, with the completion deadline set for April 26, 2025. The CERC has directed PRTL to adhere to the timeline and ensure timely execution.

The Commission also noted that no objections were received from the public or beneficiaries following the publication of notices regarding the amendment. CTUIL has recommended the amendment, and the CERC has invited further suggestions or objections by March 11, 2025, with a hearing scheduled for March 13, 2025.

Petition No: 486/TL/2024 | Read the full order here.

CERC grants transmission licence to POWERGRID Kurawar Transmission for Rajasthan REZ Phase-IV evacuation project

The Central Electricity Regulatory Commission (CERC) has approved the grant of a transmission licence to POWERGRID Kurawar Transmission Limited (formerly Rajasthan IV H1 Power Transmission Limited) for the development of the Inter-State Transmission System (ISTS) to evacuate power from the Rajasthan Renewable Energy Zone (REZ) Phase-IV (Part-2: 5.5 GW) Jaisalmer/Barmer Complex. The project, to be executed on a Build, Own, Operate, and Transfer (BOOT) basis, is part of India’s efforts to enhance its renewable energy infrastructure.

The transmission system includes the establishment of a 765/400 kV Kurawar substation, a 765 kV double-circuit line from Mandsaur to Kurawar, and several other associated transmission elements. The project aims to facilitate the evacuation of 5.5 GW of renewable energy from Rajasthan, aligning with the government’s target of achieving 500 GW of non-fossil fuel capacity by 2030.

POWERGRID Kurawar Transmission Limited, a wholly-owned subsidiary of Power Grid Corporation of India Limited (PGCIL), was selected as the successful bidder through a competitive bidding process conducted by REC Power Development and Consultancy Limited (RECPDCL). PGCIL quoted the lowest transmission charges of Rs 2,734.85 million, securing the project.

The CERC has directed the publication of a public notice to invite suggestions or objections to the grant of the transmission licence. The objections, if any, must be filed by March 13, 2025, with a hearing scheduled for March 19, 2025. The project is expected to be completed within 24 months from the effective date, i.e., by October 15, 2026.

Petition No: 491/TL/2024 | Read the full order here.

CERC issues addendum to suo-motu petition, adds four new respondents to high demand power system case

The Central Electricity Regulatory Commission (CERC) has issued an addendum to its October 7, 2024, order in Suo-Motu Petition No. 9/SM/2024, adding four new respondents to the case. The petition, which focuses on ensuring the safe, secure, and reliable operation of the power system during periods of high seasonal electricity demand, now includes the following entities:

  • Goa Electricity Department
  • System Control Centre, Puducherry Electricity Department
  • DNH & DD Power Corporation Limited, Dadar & Nagar Haveli
  • Jammu & Kashmir Power Transmission Corporation Limited

The CERC’s original order, issued under Section 79(1)(h) of the Electricity Act, 2003, and Regulation 31 of the Indian Electricity Grid Code, 2023, aims to address risks to the power system during critical periods of high demand. The addendum, dated March 3, 2025, ensures that these additional respondents are included in the proceedings, while all other terms of the original order remain unchanged.

Petition No: ADDENDUM in 9/SM/2024 | Read the full order here.

CERC grants transmission licence to BBPTL for Rajasthan REZ Phase IV (6 GW) Bikaner Complex evacuation project

The Central Electricity Regulatory Commission (CERC) has approved the grant of a transmission licence to Bikaner B Power Transmission Limited (BBPTL), a wholly-owned subsidiary of Power Grid Corporation of India Limited (PGCIL), for the development of a transmission system to evacuate power from the Rajasthan Renewable Energy Zone (REZ) Phase IV (Part 3: 6 GW) Bikaner Complex. The project, to be executed on a Build, Own, Operate, and Transfer (BOOT) basis, includes the establishment of a 765/400 kV substation near Siwani, along with associated transmission lines and STATCOM facilities.

The transmission system will facilitate the evacuation of renewable energy from the Bikaner Complex, which has a significant solar energy potential. The project is part of a larger plan to harness 75 GW of renewable energy from Rajasthan, with 6 GW specifically targeted from the Bikaner region. The scheme was approved by the Ministry of Power, and REC Power Development and Consultancy Limited (RECPDCL) was appointed as the Bid Process Coordinator (BPC) for the project.

PGCIL emerged as the successful bidder after a competitive bidding process, quoting the lowest transmission charges of Rs. 5,093.13 million. The bidding process, conducted under the Tariff-Based Competitive Bidding (TBCB) guidelines, saw participation from major players like Adani Energy Solutions, Tata Power, and Sterlite Grid 32. Following the bid, PGCIL acquired 100% equity in BBPTL and submitted the necessary performance guarantees and agreements.

CERC, after reviewing the submissions and recommendations from CTUIL, found BBPTL eligible for the transmission licence. The commission has directed the publication of a public notice to invite objections or suggestions, with a hearing scheduled for March 18, 2025. The project is expected to be completed within 24 months from the effective date of November 11, 2024.

Petition No: 69/TL/2025 | Read the full order here.

CERC approves truing-up and tariff determination for PGCIL’s 400 kV line bays at Fatehpur Substation

The Central Electricity Regulatory Commission (CERC) has approved the truing-up of transmission tariffs for Power Grid Corporation of India Limited (PGCIL) for the 2019-24 period and determined the tariffs for the 2024-29 period for the 400 kV line bays at Fatehpur Substation in the Northern Region. The decision was made under the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019 and 2024.

The transmission asset, which became operational on December 21, 2016, is part of the “Provision of 400 kV bays at Fatehpur for ATS under Unchahar TPS” project. PGCIL filed the petition seeking approval for the trued-up transmission tariff for the 2019-24 block and the determination of the tariff for the 2024-29 block. The commission approved the annual fixed charges (AFC) for both periods, with the 2024-29 AFC ranging from Rs 20.14 million to Rs 18.02 million annually.

Key components of the tariff include depreciation, interest on loans, return on equity (RoE), operation and maintenance (O&M) expenses, and interest on working capital. The RoE was calculated at a base rate of 15.50%, grossed up with the applicable Minimum Alternate Tax (MAT) rate. The O&M expenses were determined based on normative rates specified in the 2024 Tariff Regulations.

The commission also allowed PGCIL to recover filing fees, publication expenses, and RLDC fees from beneficiaries. Additionally, PGCIL was permitted to file separate petitions for security expenses, insurance, and capital spares for the 2024-29 period.

The transmission charges will be borne by NTPC until the start of the Long-Term Access (LTA) agreement, after which they will be shared as per the Central Electricity Regulatory Commission (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2020.

Petition No:91/TT/2025 | Read the full order here.

CERC approves truing-up and tariff determination for PGCIL’s Northern Region assets

The Central Electricity Regulatory Commission (CERC) has approved the truing-up of transmission tariffs for Power Grid Corporation of India Limited (PGCIL) for the 2019-24 period and determined the tariffs for the 2024-29 period for its combined assets in the Northern Region. The assets include a 400 kV bus reactor at Abdullapur and a 400 kV D/C transmission line between Abdullapur and Sonepat, which are part of the system strengthening project for the Karcham Wangtoo Hydroelectric Project.

PGCIL filed the petition seeking approval for the truing-up of tariffs for the 2019-24 period and the determination of tariffs for the 2024-29 period. The commission approved the annual fixed charges (AFC) for both periods, considering factors such as depreciation, interest on loans, return on equity, operation and maintenance (O&M) expenses, and interest on working capital. The AFC for the 2019-24 period was set at Rs 312.13 million for 2019-20, decreasing to Rs 193.16 million for 2023-24. For the 2024-29 period, the AFC was approved at Rs 188.16 million for 2024-25, with minor adjustments in subsequent years.

The commission also allowed PGCIL to recover filing fees, publication expenses, and other charges from beneficiaries. Additionally, PGCIL was permitted to file separate petitions for security expenses, insurance, and capital spares for the 2024-29 period. The order ensures that PGCIL can recover costs associated with transmission services while maintaining regulatory compliance.

Petition No: 92/TT/2025 | Read the full order here.

CERC approves truing-up and tariff determination for PGCIL’s Tala-Siliguri transmission system

The Central Electricity Regulatory Commission (CERC) has approved the truing-up of transmission tariffs for Power Grid Corporation of India Limited (PGCIL) for the 2019-24 period and determined the tariffs for the 2024-29 period for the Tala-Siliguri Transmission System in the Eastern Region. The system includes 400 kV transmission lines, reactors, and associated bays, which are critical for power transmission in the region.

PGCIL filed the petition seeking approval for the truing-up of tariffs for the 2019-24 period and the determination of tariffs for the 2024-29 period. The commission approved the annual fixed charges (AFC) for both periods, considering factors such as depreciation, interest on loans, return on equity, operation and maintenance (O&M) expenses, and interest on working capital. The AFC for the 2019-24 period was set at Rs 268.57 million for 2019-20, decreasing to Rs 265.45 million for 2023-24. For the 2024-29 period, the AFC was approved at Rs 254.03 million for 2024-25, with minor adjustments in subsequent years.

The commission also allowed PGCIL to recover filing fees, publication expenses, and other charges from beneficiaries. Additionally, PGCIL was permitted to file separate petitions for security expenses, insurance, and capital spares for the 2024-29 period. The order ensures that PGCIL can recover costs associated with transmission services while maintaining regulatory compliance.

Petition No: 98/TT/2025 | Read the full order here.

CERC approves transmission charges for Bikaner REZ Phase-IV (Part-3) project

The Central Electricity Regulatory Commission (CERC) has approved the transmission charges for the Rajasthan Renewable Energy Zone (REZ) Phase-IV (Part-3: 6 GW) Bikaner Complex project. The order, dated March 5, 2025, follows a competitive bidding process conducted by REC Power Development and Consultancy Limited (RECPDCL) under the Ministry of Power’s guidelines.

The project, aimed at evacuating power from the Bikaner complex, was awarded to Power Grid Corporation of India Limited (PGCIL) after it emerged as the lowest bidder with an annual transmission charge of Rs 5,093.13 million. The bidding process, which included four participants—Adani Energy Solutions, Tata Power, PGCIL, and Sterlite Grid 32—was conducted through an e-reverse auction. PGCIL’s final offer was significantly lower than the estimated annual transmission charges of Rs 5,647.34 million.

The Bid Evaluation Committee (BEC) certified that the process adhered to the Tariff-Based Competitive Bidding Guidelines for Transmission Service. The project involves establishing a 765/400 kV substation, transmission lines, and associated infrastructure, with a scheduled commissioning date of 24 months from the transfer of the Special Purpose Vehicle (SPV).

CERC’s order also mandates that the transmission charges be shared among designated Inter-State Transmission System (ISTS) customers as per the CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2020. The commission has condoned a 14-day delay in filing the petition due to procedural issues and has directed the publication of notices for granting a transmission license to Bikaner B Power Transmission Limited, the SPV acquired by PGCIL.

Petition No: 70/AT/2025 | Read the full order here.

CERC approves trued-up transmission charges for Mau-Balia line for 2019-24 and 2024-29 periods

The Central Electricity Regulatory Commission (CERC) has approved the trued-up transmission charges for the 132 kV S/C Mau-Balia Transmission System in the Northern Region for the 2019-24 period and determined charges for the 2024-29 period. The order follows a petition filed by Power Grid Corporation of India Limited (PGCIL) under the Electricity Act, 2003.

PGCIL sought CERC’s approval for the transmission tariff truing-up for the 2019-24 period and determination for the 2024-29 period. The petitioner also requested approvals for recovering costs related to filing fees, publication expenses, RLDC (Regional Load Despatch Centre) fees, and insurance expenses. The petition covered annual fixed charges (AFC) and cost elements such as depreciation, return on equity, and operation & maintenance (O&M) expenses.

For the 2019-24 period, the commission approved the trued-up AFC, with annual charges ranging from Rs 66.55 million in 2019-20 to Rs 65.75 million in 2023-24. For the 2024-29 period, the AFC was set between Rs 62.94 million in 2024-25 and Rs 66.33 million in 2028-29​.

CERC approved PGCIL’s petition for the trued-up transmission charges and allowed the petitioner to recover costs related to the filing fee, publication expenses, RLDC charges, and license fees. Additionally, PGCIL can file separate petitions for security expenses, insurance, and capital spares during the 2024-29 period​.

The approved transmission charges will be borne solely by Uttar Pradesh Power Corporation Limited (UPPCL), the primary beneficiary of the transmission system​.

Petition No: 139/TT/2025 | Read the full order here.

CERC grants transmission license to POWERGRID Bikaner Neemrana Transmission Limited

The Central Electricity Regulatory Commission (CERC) has granted a transmission license to POWERGRID Bikaner Neemrana Transmission Limited, a wholly owned subsidiary of Power Grid Corporation of India Limited (PGCIL). The license allows the company to develop specific transmission infrastructure under the Regulated Tariff Mechanism (RTM).

The petition was filed under Section 14 of the Electricity Act, 2003, along with the CERC regulations on transmission licenses. The project involves implementing transmission bays at the 765/400/220 kV Bikaner-III substation to interconnect renewable energy generation capacities from NTPC Renewable Energy Ltd., Deshraj Solar Energy Pvt. Ltd., Sunbreeze Renewables Nine Pvt. Ltd., and MRS Buildvision Pvt. Ltd.

The proposed infrastructure includes:

  • Two 220 kV line bays for NTPC Renewable Energy Ltd. (500 MW)
  • One 220 kV line bay for Deshraj Solar Energy Pvt. Ltd. (300 MW)
  • Three 400 kV line bays for Sunbreeze Renewables (1400 MW) and MRS Buildvision (1000 MW)

The estimated project costs are Rs 11.14 million for NTPC Renewable’s connectivity and Rs 50.09 million for the remaining projects. The transmission system will facilitate power evacuation from these renewable sources, ensuring grid integration and stability.

CERC approved the license, directing the company to comply with transmission regulations, grid codes, and open access requirements. The commission acknowledged requests from developers for the early completion of transmission bays before their scheduled connectivity dates. However, it noted that liability for bay charges due to delays would remain with the respective generators.

CTUIL and the Central Electricity Authority (CEA) were instructed to monitor project execution and report any lapses. The order also mentioned that the Ministry of Power would review transmission schemes costing up to Rs 500 million for further approvals.

Petition No: 478/TL/2024 | Read the full order here.

CERC adopts transmission charges for POWERGRID Kurawar Transmission Limited

The Central Electricity Regulatory Commission (CERC) has approved the adoption of transmission charges for the transmission system being developed by POWERGRID Kurawar Transmission Limited (formerly Rajasthan IV H1 Power Transmission Limited). The project, aimed at evacuating 5.5 GW of renewable energy from Rajasthan Renewable Energy Zone (REZ) Phase-IV (Jaisalmer/Barmer Complex), will be implemented on a Build, Own, Operate, and Transfer (BOOT) basis.

The transmission system, allocated through tariff-based competitive bidding, will include the establishment of a 765/400/220/132 kV substation at Kurawar, multiple transmission lines, and line bays. The project was awarded to Power Grid Corporation of India Limited (PGCIL), which emerged as the lowest bidder in the competitive bidding process conducted by REC Power Development and Consultancy Limited (RECPDCL).

PGCIL secured the project with an annual transmission charge of Rs 2,734.85 million, significantly lower than the estimated Rs 4,572.13 million. The bid evaluation committee confirmed that the bidding process adhered to the Ministry of Power’s guidelines and was conducted transparently.

CERC approved and adopted the discovered transmission charges, ensuring that costs will be shared among designated inter-state transmission system customers (DICs) as per the CERC regulations. The commission directed that the implementation of the project be closely monitored, with compliance required under all applicable regulatory provisions.

Petition No: 492/AT/2024 | Read the full order here.

CERC approves trued-up transmission tariff for Chamera-II transmission system

The Central Electricity Regulatory Commission (CERC) has approved the trued-up transmission tariff for the 2019-24 period and determined the tariff for the 2024-29 period for the LILO (Loop In Loop Out) of the 400 kV S/C Chamera-I Kishenpur transmission line at Chamera-II. The transmission system is associated with the Chamera Hydroelectric Project (HEP) Stage-II in the Northern Region and is operated by Power Grid Corporation of India Limited (PGCIL).

PGCIL sought CERC’s approval under the Electricity Act, 2003, for the truing-up of charges from 2019-24 and the determination of fixed charges for the 2024-29 period. The company also requested approvals for recovering costs related to return on equity, interest on loans, operation and maintenance (O&M) expenses, and other applicable charges.

The approved transmission tariff for the 2019-24 period saw annual fixed charges ranging from Rs 369.39 million in 2023-24 to Rs 384.75 million in 2019-20. For the 2024-29 period, the tariff was set between Rs 345.82 million in 2028-29 and Rs 358.74 million in 2024-25.

CERC approved the trued-up tariff for the 2019-24 period and the determined charges for the 2024-29 period. The commission also allowed PGCIL to recover expenses related to petition filing fees, publication costs, Regional Load Despatch Centre (RLDC) charges, and applicable taxes. Additionally, PGCIL can file separate petitions for security expenses, insurance, and capital spares during the 2024-29 period. The approved transmission charges will be borne by the designated beneficiaries, including Uttar Pradesh Power Corporation Limited (UPPCL), Rajasthan’s state distribution companies, and other Northern Region utilities.

Petition No: 131/TT/2025 | Read the full order here.

CERC approves trued-up transmission tariff for Kishanpur-Pampore transmission line

The Central Electricity Regulatory Commission (CERC) has approved the trued-up transmission tariff for the 2019-24 period and determined the tariff for the 2024-29 period for the Series Capacitors on Circuits-I and II of the 220 kV double circuit Kishanpur-Pampore Transmission Line at Kishanpur Sub-station in the Northern Region. The petition was filed by Power Grid Corporation of India Limited (PGCIL) under the Electricity Act, 2003.

PGCIL sought CERC’s approval for truing up the 2019-24 transmission charges and determining the fixed charges for the 2024-29 period. The company also requested approvals for recovering costs related to return on equity, operation and maintenance (O&M) expenses, and other applicable charges. The commission approved the trued-up annual fixed charges for the 2019-24 period, with annual charges ranging from Rs 92.28 million in 2019-20 to Rs 99.22 million in 2023-24. For the 2024-29 period, the fixed charges were set between Rs 88.41 million in 2024-25 and Rs 87.80 million in 2028-29.

CERC allowed PGCIL to recover expenses related to petition filing fees, publication costs, Regional Load Despatch Centre (RLDC) charges, and applicable taxes. Additionally, PGCIL can file separate petitions for security expenses, insurance, and capital spares during the 2024-29 period. The transmission charges will be borne by the designated beneficiaries, including state power distribution companies from Uttar Pradesh, Rajasthan, Himachal Pradesh, Punjab, Haryana, Jammu & Kashmir, Uttarakhand, and Delhi.

Petition No: 90/TT/2025 | Read the full order here.

CERC approves trued-up transmission tariff for system strengthening in the Southern Region

The Central Electricity Regulatory Commission (CERC) has approved the trued-up transmission tariff for the 2019-24 period and determined the tariff for the 2024-29 period for a set of transmission assets under the “System Strengthening-VII in the Southern Regional Grid.” The petition was filed by Power Grid Corporation of India Limited (PGCIL) under the Electricity Act, 2003.

PGCIL sought CERC’s approval for truing up transmission charges for the 2019-24 period and determining the fixed charges for the 2024-29 period. The transmission system includes the LILO (Loop In Loop Out) of the 400 kV Trichy-Madurai line at Karaikudi, 2×315 MVA transformers at Karaikudi, the LILO of the 400 kV Talaguppa-Neelamangala line at Hassan, and 400/220 kV transformers at Hassan Sub-station. The commission approved the trued-up annual fixed charges for the 2019-24 period, ranging from Rs 531.59 million in 2019-20 to Rs 387.09 million in 2023-24. For the 2024-29 period, the fixed charges were set between Rs 351.05 million in 2024-25 and Rs 361.19 million in 2028-29.

CERC allowed PGCIL to recover expenses related to petition filing fees, publication costs, Regional Load Despatch Centre (RLDC) charges, and applicable taxes. Additionally, PGCIL can file separate petitions for security expenses, insurance, and capital spares during the 2024-29 period. The transmission charges will be borne by beneficiaries, including state power distribution companies in Tamil Nadu, Kerala, Goa, Puducherry, Andhra Pradesh, Telangana, and Karnataka.

Petition No: 105/TT/2025 | Read the full order here.

CERC approves trued-up transmission tariff for Amritsar and Moga sub-stations

The Central Electricity Regulatory Commission (CERC) has approved the trued-up transmission tariff for the 2019-24 period and determined the tariff for the 2024-29 period for augmentation of transformation capacity at Amritsar and Moga sub-stations in the Northern Region. The petition was filed by Power Grid Corporation of India Limited (PGCIL) under the Electricity Act, 2003.

The transmission assets under this petition include a 315 MVA ICT-IV (Interconnecting Transformer) along with associated bays at Moga sub-station, ICT-II with associated bays and two PSEB feeder bays at Amritsar sub-station, and two PSEB line bays at Moga sub-station. The project was approved to enhance power transformation capacity in the region.

For the 2019-24 period, the commission approved the trued-up annual fixed charges, which ranged from Rs 920.10 million in 2019-20 to Rs 823.80 million in 2023-24. For the 2024-29 period, the charges were set between Rs 674.54 million in 2024-25 and Rs 757.30 million in 2028-29. The commission also allowed PGCIL to recover expenses related to petition filing fees, publication costs, RLDC (Regional Load Despatch Centre) charges, and applicable taxes. Additionally, PGCIL can file separate petitions for security expenses, insurance, and capital spares during the 2024-29 period.

The transmission charges will be borne by designated beneficiaries, including power distribution companies in Uttar Pradesh, Rajasthan, Himachal Pradesh, Punjab, Haryana, Jammu & Kashmir, Uttarakhand, Delhi, Chandigarh, and the North Central Railway.

Petition No: 140/TT/2025 | Read the full order here.

CERC approves trued-up transmission tariff for East-West Transmission Corridor Strengthening Scheme

The Central Electricity Regulatory Commission (CERC) has approved the trued-up transmission tariff for the 2019-24 period and determined the tariff for the 2024-29 period for the Combined Asset under the East-West Transmission Corridor Strengthening Scheme in the Western Region. The petition was filed by Power Grid Corporation of India Limited (PGCIL) under the Electricity Act, 2003.

The assets covered in the petition include the 400 kV double-circuit (D/C) Raigarh-Raipur transmission line with associated bays, the 400 kV D/C Ranchi-Rourkela transmission line and Ranchi sub-station extension, a 40% fixed series compensation package at Raipur sub-station, and the 400 kV D/C Rourkela-Raigarh transmission line with associated bays at Raigarh and Rourkela. These assets were consolidated in an earlier order during the 2009-14 tariff period.

For the 2019-24 period, CERC approved the trued-up annual fixed charges, ranging from Rs 9932.23 million in 2019-20 to Rs 6422.36 million in 2023-24. For the 2024-29 period, the approved fixed charges range from Rs 6196.93 million in 2024-25 to Rs 6174.56 million in 2028-29. The commission also allowed PGCIL to recover expenses related to petition filing fees, publication costs, Regional Load Despatch Centre (RLDC) charges, and applicable taxes. Additionally, PGCIL can file separate petitions for security expenses, insurance, and capital spares during the 2024-29 period.

The transmission charges will be borne by designated beneficiaries, including power distribution companies in Madhya Pradesh, Maharashtra, Gujarat, Goa, Dadra and Nagar Haveli & Daman and Diu (DNHDD), and Chhattisgarh.

Petition No: 142/TT/2025 | Read the full order here.

CERC approves trued-up transmission tariff for Raebareli sub-station augmentation

The Central Electricity Regulatory Commission (CERC) has approved the trued-up transmission tariff for the 2019-24 period and determined the tariff for the 2024-29 period for the augmentation of 220/132 kV transformation capacity at Raebareli by adding a 1×100 MVA transformer. The petition was filed by Power Grid Corporation of India Limited (PGCIL) under the Electricity Act, 2003.

PGCIL sought CERC’s approval for truing up the transmission charges for the 2019-24 period and determining the fixed charges for the 2024-29 period. The transmission asset includes a 220/132 kV 100 MVA Interconnecting Transformer (ICT) and associated bays at the Raebareli sub-station, aimed at strengthening the power supply in the Northern Region. The commission approved the trued-up annual fixed charges for the 2019-24 period, ranging from Rs 150.23 million in 2019-20 to Rs 148.06 million in 2023-24. For the 2024-29 period, the annual fixed charges were set between Rs 115.56 million in 2024-25 and Rs 127.07 million in 2028-29.

CERC allowed PGCIL to recover expenses related to petition filing fees, publication costs, Regional Load Despatch Centre (RLDC) charges, and applicable taxes. Additionally, PGCIL can file separate petitions for security expenses, insurance, and capital spares during the 2024-29 period. The transmission charges will be borne by designated beneficiaries, including state power distribution companies in Uttar Pradesh, Rajasthan, Himachal Pradesh, Punjab, Haryana, Jammu & Kashmir, Uttarakhand, Delhi, Chandigarh, and North Central Railway.

Petition No: 14/TT/2025 | Read the full order here.

CERC allows Reliance Industries to share GNA with subsidiary, rejects request for STU-connected entities

The Central Electricity Regulatory Commission (CERC) has ruled on a petition filed by Reliance Industries Limited (RIL) seeking permission to allow its subsidiaries and group companies to use its General Network Access (GNA) at the Jam Khambhaliya Inter-State Transmission System (ISTS) substation in Gujarat. The petition was filed under Section 79 of the Electricity Act, 2003, along with provisions of the General Network Access Regulations, 2022.

RIL, which has 1200 MW connectivity to the ISTS substation at Jam Khambhaliya, sought approval to let its subsidiary, Reliance New Solar Energy Limited (RNSEL), use part of its 500 MW GNA allocation starting from October 2024. RNSEL was granted 50 MW GNA, effective from March 2028, but required access before this date. RIL argued that since both companies are connected at the same ISTS connection point, RNSEL should be allowed to utilize its parent company’s GNA under Regulation 15.1 of the GNA Regulations.

CERC ruled in favor of RIL, allowing RNSEL to use RIL’s GNA. The commission clarified that subsidiaries could utilize a parent company’s GNA at the same connection point without requiring a separate GNA, provided they establish the necessary technical and scheduling arrangements. It directed the National Load Despatch Centre (NLDC) and the Central Transmission Utility of India Limited (CTUIL) to develop a procedure within two months to outline the modalities of such GNA sharing.

However, CERC rejected RIL’s request to permit other subsidiaries and group companies connected to the State Transmission Utility (STU) network to use its GNA without independently applying for their own GNA. The commission held that Regulation 23.1 of the GNA Regulations only allows GNA sharing between two existing GNA grantees and does not extend to non-GNA entities connected to the STU. CERC stated that this was a sectoral issue requiring wider stakeholder consultation and declined to grant an exception through regulatory relaxation.

Petition No: 161/MP/2024 | Read the full order here.

The featured photograph is for representation only

Similar Posts

Leave a Reply

Your email address will not be published. Required fields are marked *