PGCIL completes delayed interstate transmission system for Rajasthan’s solar energy zones
Author: PPD Team Date: September 16, 2024
Author: PPD Team Date: September 16, 2024
Power Grid Corporation of India Ltd (PGCIL) recently commissioned an interstate transmission system (ISTS) under “Powergrid Bhadla Transmission Ltd.” The project, officially named the “Transmission system strengthening scheme for evacuation of power from solar energy zones in Rajasthan (8.1 GW) under Phase-II, Part B,” was completed in August 2024, nearly two years behind schedule.
This Rs 11.06 billion scheme, awarded to PGCIL under the Tariff-Based Competitive Bidding (TBCB) route, involved the construction of a 405-ckm 765kV double-circuit line from the Fatehgarh-II Pooling Station to Bhadla-II Pooling Station. It also included two 765kV line bays at Bhadla-II for the line’s termination.
The project faced delays due to concerns about the transmission line passing through areas inhabited by the endangered Great Indian Bustard (GIB). In July 2022, a Supreme Court-appointed committee cleared the project but required a rerouting, which added 25 ckm to the original line length and increased the project cost by over 50%, from an initial estimate of Rs 7.14 billion.
This ISTS scheme is part of a broader initiative to build transmission infrastructure for evacuating 20 GW of power from Rajasthan’s solar energy zones. PGCIL won the project by quoting an annualized tariff of Rs 728.93 million during an e-reverse auction held in January 2021.
Author: PPD Team Date: February 11, 2025 The Japan Atomic Energy Agency (JAEA) plans to request the Nuclear Regulation Authority (NRA) to review its proposal for building a hydrogen production facility as early as February, as reported by The Japan News. The facility, intended to produce hydrogen using heat from a gas reactor, will be located next to the High-Temperature Engineering Test Reactor (HTTR) in Oarai, Ibaraki Prefecture, and will operate integrally with the reactor….
Author: PPD Team Date: September 9, 2025 Vikram Solar has received an order to supply 336 megawatts (MW) of solar modules to L&T Construction. The modules will be deployed at Khavda, Gujarat, where the company has supplied earlier projects as well. For this order, Vikram Solar will provide its Hypersol G12R modules built on N-type technology. The modules are designed with up to 80 per cent bifaciality, improved performance in high temperatures, and a year-on-year…
Author: PPD Team Date: February 14, 2025 The Ministry of New and Renewable Energy (MNRE) has released draft guidelines outlining the design, specifications, performance, and testing for solar cold storage systems equipped with thermal energy storage (TES) backup. These systems are primarily powered by solar photovoltaic (PV) energy, with TES providing backup cooling during non-solar hours, ensuring uninterrupted refrigeration for agricultural produce, dairy, fisheries, and pharmaceutical products. The guidelines define standards for solar cold storage…
Author: PPD Team Date: February 28, 2025 Adani Saur Urja (LA) Limited, a subsidiary of Adani Green Energy Limited (AGEL), has received a Letter of Award (LoA) from Uttar Pradesh Power Corporation Limited (UPPCL) for energy storage capacity from the 1,250 MW Pumped Storage Project in the Sonbhadra district. The annual fixed cost payable under the LoA is Rs 76.53 million per MW per year, excluding taxes, for a 40-year period from the Commercial Operation…
Author: PPD Team Date: August 19, 2025 L&T Energy GreenTech Limited (LTEG), a wholly owned subsidiary of Larsen & Toubro, has signed a joint development agreement with Japan’s ITOCHU Corporation to develop and commercialise a 300 kilo tonnes per annum (KTPA) green ammonia project at Kandla, Gujarat. Under the agreement, ITOCHU plans to offtake the product for bunkering applications in Singapore. L&T acquired land at Kandla last year for green hydrogen and ammonia projects. The…
Author: PPD Team Date: October 7, 2025 Solar and energy storage developers will face higher equipment prices from Q4 2025 due to Chinese policy changes and production cuts, according to Wood Mackenzie. This marks an end to the 18-month period of unusually low prices in the market. The report identifies three main factors driving the increase: consolidation in the polysilicon sector, supply-side production cuts, and the cancellation of China’s 13% VAT export rebate. Together, these…