PFCCL re-invites RFP for ERGS-I transmission project
Author: PPD Team Date: 24/01/2025
Author: PPD Team Date: 24/01/2025
PFC Consulting Limited (PFCCL) re-invited the Request for Proposal (RFP) for selecting a Transmission Service Provider (TSP) through the tariff-based competitive bidding (TBCB) process for the Eastern Region Generation Scheme-I (ERGS-I) on January 21, 2025.
The deadline for bid submission is March 25, 2025. The earlier bidding process was conducted in March 2024.
PFCCL is serving as the bid process coordinator (BPC) for the establishment of these projects through the TBCB process.
The transmission scheme involves the LILO of both circuits of Angul–Sundargarh (Jharsuguda) 765 kV 2xS/c lines at NLC-Talabira generation switchyard, with a total capacity of 50 km (25 km Loop in and 25 km Loop out). The estimated cost of the project is Rs 4.13 billion.
Author: PPD Team Date: 28/10/2024 JSW Steel’s Board has approved an expanded power purchase agreement (PPA) to procure renewable power for a total of 2,507 MW across its sites at Vijayanagar, Dolvi, Salem, and Anjar. Of the initial 1,637 MW commitment, 375 MW has already been commissioned, with an additional 580 MW expected to come online by March 2025. The Board has now greenlit further renewable procurement, including a hybrid energy capacity of 600 MW…
Author: PPD Team Date: 28/10/2024 Larsen & Toubro (L&T) has secured a ‘significant’ contract, estimated between Rs 10 billion and Rs 25 billion, to implement advanced welding technologies for the ITER Organisation’s nuclear fusion project, the world’s largest, located in Cadarache, Southern France. L&T will focus on critical technologies for assembling ports and complex components within the ITER Tokamak’s vacuum vessel. ITER, the International Thermonuclear Experimental Reactor, is a large-scale scientific collaboration aiming to make…
Author: PPD Team Date: 23/05/2025 Waaree Renewable Technologies Limited has announced the incorporation of a new wholly owned subsidiary, Sunsational Power Private Limited, to strengthen its presence in the solar energy sector. The subsidiary, set up with an authorised capital of Rs 0.1 million, is awaiting its certificate of incorporation and has not yet commenced commercial operations. It will operate exclusively within the solar renewable energy domain. The announcement comes alongside Waaree’s strong financial performance…
Author: PPD Team Date: 11/07/2025 The Bihar Cabinet has approved the Bihar Renewable Energy Policy 2025, replacing its 2017 version. The new policy sets a five-year target to develop 23,968 MW of renewable energy capacity and 6.1 GWh of energy storage. Drafted by the Bihar Renewable Energy Development Agency (BREDA), the policy spans a wide range of technologies including solar, wind, biomass, green hydrogen, geothermal, pumped hydro, and battery storage. It introduces regulatory and financial…
Author: PPD Team Date: 28/03/2025 Syngene International Limited has increased its stake in O2 Renewable Energy Private Limited II from 26 percent to 33.79 percent. This move strengthens Syngene’s renewable energy consumption strategy while ensuring compliance with captive power requirements under the Electricity Act. The investment supports O2 Renewable Energy’s 201.2 MW wind-solar hybrid power plant in Kudligi Taluk, Bellary District, Karnataka. Syngene invested Rs 65 million through equity shares and compulsory convertible debentures as…
Author: PPD Team Date: 13/02/2025 The Small Industries Development Bank of India (SIDBI) and Agence Française de Développement (AFD) have signed a $100 million credit facility agreement aimed at enhancing green finance solutions for micro, small, and medium enterprises (MSMEs) in India. Under the agreement, AFD will provide SIDBI with a $100 million credit line, which will be used to offer MSMEs access to affordable financing for energy-efficient technologies, renewable energy solutions, and climate-friendly business…
Author: PPD Team Date: 28/10/2024 JSW Steel’s Board has approved an expanded power purchase agreement (PPA) to procure renewable power for a total of 2,507 MW across its sites at Vijayanagar, Dolvi, Salem, and Anjar. Of the initial 1,637 MW commitment, 375 MW has already been commissioned, with an additional 580 MW expected to come online by March 2025. The Board has now greenlit further renewable procurement, including a hybrid energy capacity of 600 MW…
Author: PPD Team Date: 28/10/2024 Larsen & Toubro (L&T) has secured a ‘significant’ contract, estimated between Rs 10 billion and Rs 25 billion, to implement advanced welding technologies for the ITER Organisation’s nuclear fusion project, the world’s largest, located in Cadarache, Southern France. L&T will focus on critical technologies for assembling ports and complex components within the ITER Tokamak’s vacuum vessel. ITER, the International Thermonuclear Experimental Reactor, is a large-scale scientific collaboration aiming to make…
Author: PPD Team Date: 23/05/2025 Waaree Renewable Technologies Limited has announced the incorporation of a new wholly owned subsidiary, Sunsational Power Private Limited, to strengthen its presence in the solar energy sector. The subsidiary, set up with an authorised capital of Rs 0.1 million, is awaiting its certificate of incorporation and has not yet commenced commercial operations. It will operate exclusively within the solar renewable energy domain. The announcement comes alongside Waaree’s strong financial performance…
Author: PPD Team Date: 11/07/2025 The Bihar Cabinet has approved the Bihar Renewable Energy Policy 2025, replacing its 2017 version. The new policy sets a five-year target to develop 23,968 MW of renewable energy capacity and 6.1 GWh of energy storage. Drafted by the Bihar Renewable Energy Development Agency (BREDA), the policy spans a wide range of technologies including solar, wind, biomass, green hydrogen, geothermal, pumped hydro, and battery storage. It introduces regulatory and financial…
Author: PPD Team Date: 28/03/2025 Syngene International Limited has increased its stake in O2 Renewable Energy Private Limited II from 26 percent to 33.79 percent. This move strengthens Syngene’s renewable energy consumption strategy while ensuring compliance with captive power requirements under the Electricity Act. The investment supports O2 Renewable Energy’s 201.2 MW wind-solar hybrid power plant in Kudligi Taluk, Bellary District, Karnataka. Syngene invested Rs 65 million through equity shares and compulsory convertible debentures as…
Author: PPD Team Date: 13/02/2025 The Small Industries Development Bank of India (SIDBI) and Agence Française de Développement (AFD) have signed a $100 million credit facility agreement aimed at enhancing green finance solutions for micro, small, and medium enterprises (MSMEs) in India. Under the agreement, AFD will provide SIDBI with a $100 million credit line, which will be used to offer MSMEs access to affordable financing for energy-efficient technologies, renewable energy solutions, and climate-friendly business…
Author: PPD Team Date: 28/10/2024 JSW Steel’s Board has approved an expanded power purchase agreement (PPA) to procure renewable power for a total of 2,507 MW across its sites at Vijayanagar, Dolvi, Salem, and Anjar. Of the initial 1,637 MW commitment, 375 MW has already been commissioned, with an additional 580 MW expected to come online by March 2025. The Board has now greenlit further renewable procurement, including a hybrid energy capacity of 600 MW…
Author: PPD Team Date: 28/10/2024 Larsen & Toubro (L&T) has secured a ‘significant’ contract, estimated between Rs 10 billion and Rs 25 billion, to implement advanced welding technologies for the ITER Organisation’s nuclear fusion project, the world’s largest, located in Cadarache, Southern France. L&T will focus on critical technologies for assembling ports and complex components within the ITER Tokamak’s vacuum vessel. ITER, the International Thermonuclear Experimental Reactor, is a large-scale scientific collaboration aiming to make…