NTPC secures land in three states for nuclear power projects
Author: PPD Team Date: August 21, 2025
Author: PPD Team Date: August 21, 2025
NTPC Ltd has received land assurances from Gujarat, Chhattisgarh and Madhya Pradesh to set up nuclear power plants through its subsidiary NTPC Parmanu Urja Nigam Ltd (NPUNL), officials told Moneycontrol.
The company has sought guarantees on water availability before beginning geotechnical studies. A twin 700 MW reactor unit requires about 70 million cubic meters of water annually, a key factor in site selection.
NTPC plans to invest at least $60 billion in nuclear energy over the next two decades. Of India’s 100 GW nuclear capacity target by 2047, NTPC has been mandated to deliver 30 GW using pressurised heavy water reactors, small modular reactors, and new technologies.
Author: PPD Team Date: January 14, 2026 The Vibrant Gujarat Regional Conference held in Rajkot on January 12-13, 2026, resulted in major renewable energy investment proposals for Gujarat. Four companies signed Memoranda of Understanding (MoUs) with the Government of Gujarat, committing investments of over Rs 34,000 crore across renewable power, biofuels, and biogas projects. NLC India Limited (NLCIL), a Navratna public sector undertaking under the Ministry The largest commitment came from NLC India Limited, a…
Author: PPD Team Date: December 19, 2024 The Central Electricity Regulatory Commission (CERC) has granted a final transmission licence to “Bhadla-III Transmission Ltd,” a wholly-owned TBCB subsidiary of Power Grid Corporation of India Ltd (PGCIL). The licence, issued on December 15, 2024, is valid for 25 years unless revoked earlier. Bhadla-III Transmission Ltd is developing an ISTS scheme titled “Additional transmission system for evacuation of power from Bhadla-III PS as part of Rajasthan REZ Phase-III…
Author: PPD Team Date: January 7, 2025 Gensol Engineering Limited has secured an engineering, procurement, and construction (EPC) contract for a 275 MW solar photovoltaic project at the Khavda Rann renewable energy solar park in Kutch, Gujarat. The project, valued at Rs 10.61 billion, also includes three years of operations and maintenance.
Author: PPD Team Date: March 17, 2025 Patratu Vidyut Utpadan Nigam Limited (PVUNL) achieved a major milestone on March 11, 2025, by synchronizing Unit 1 of the Patratu Thermal Power Project Phase I with the grid. On the same day, a dry run was completed for all units of the project, marking significant progress in its commissioning. PVUNL, a special purpose vehicle (SPV) formed by NTPC Limited in partnership with Jharkhand Bijli Vitran Nigam Limited…
Author: PPD Team Date: November 20, 2024 Schneider Electric Infrastructure Ltd (SEIL) has reported a 14.3% year-on-year growth in its order backlog, which stood at Rs 13.89 billion as of September 30, 2024. The company also noted robust growth in order inflows during FY25. In Q2FY25 (July to September), SEIL achieved an order inflow of Rs 5.72 billion, a 16.3% increase from Rs 4.92 billion in Q2FY24. For H1FY25 (April to September), order inflows rose…
Author: PPD Team Date: July 7, 2025 Assam Power Distribution Company Limited (APDCL) has signed a deed of agreement with NIRL Assam Renewables Limited (NARL) for the transfer of land to develop a 500 MW solar power project in Lahorijan, Assam. The agreement was signed on June 27, 2025. Under the agreement, APDCL will transfer 8,000 bighas of land to NARL, a joint venture between NLC India Renewables Limited (NIRL) and APDCL. NIRL is a…