NTPC commissions first 800 MW unit of Patratu Thermal Power Project
Author: PPD Team Date: November 5, 2025
Author: PPD Team Date: November 5, 2025
NTPC Limited has announced the start of commercial operations for Unit 1 (800 MW) of the Patratu Super Thermal Power Project (STPP) Phase I, developed by its subsidiary Patratu Vidyut Utpadan Nigam Limited (PVUNL). The unit achieved commercial operation at 00:00 hours on November 5, 2025.
With this addition, the NTPC Group’s total installed and commercial capacity has reached 84,849 MW. Unit 1 had earlier been synchronized with the grid on March 11, 2025, following successful trial operations and a dry run of all units under Stage I.
PVUNL, a special purpose vehicle formed by NTPC in partnership with Jharkhand Bijli Vitran Nigam Limited (JBVNL), is developing the 2,400 MW Phase I project in Ramgarh district, Jharkhand. The project comprises three units of 800 MW each and is being implemented by Bharat Heavy Electricals Limited (BHEL) under an EPC contract valued at Rs 18,668 crore.
About 85% of the electricity generated from Phase I will be supplied to Jharkhand to meet its growing demand. Phase II of the project is planned to add an additional 2,800 MW. Coal for the plant will be supplied from the Banhadi coal block in Latehar district, where local communities have granted no-objection certificates for mining activities.
Author: PPD Team Date: February 28, 2025 Shakti Pumps Limited has invested Rs 600 million in its wholly owned subsidiary, Shakti Electric Vehicle (EV) Mobility Private Limited, by subscribing to 6 million equity shares with a face value of Rs 10 each. Last week, Shakti Pumps invested Rs 390 million in the subsidiary by subscribing to 4 million equity shares. Shakti EV Mobility is engaged in manufacturing, processing, trading, and distributing EV motors and charger…
Author: PPD Team Date: June 30, 2025 The Ministry of New and Renewable Energy (MNRE) has revised guidelines under the Biomass Programme, part of the National Bioenergy Programme (Phase-I) for FY 2021–22 to 2025–26. Announced on June 27, 2025, the changes aim to reduce compliance burden and simplify project execution for developers. Simplified documentation process Several submission requirements for briquette and pellet plants seeking Central Financial Assistance (CFA) have been removed. Developers no longer need…
Author: PPD Team Date: June 10, 2025 NHPC Limited began commercial operations of 53.57 MW on June 7, 2025, under its 1,000 MW grid-connected solar photovoltaic (PV) power project in Bikaner, Rajasthan. The commissioned capacity is part of a 300 MW plant being developed by Tata Power Solar Systems Limited at Karnisar-Bhatiyan in Bikaner. So far, 160.71 MW of capacity has been commissioned. Under the scheme, usage charges are capped at Rs 2.45 per kWh,…
Author: PPD Team Date: May 15, 2025 Sungrow has secured a contract from Juniper Green Energy Private Limited to supply inverters for 835 MW of solar power projects in Rajasthan and Maharashtra. The contract was awarded on May 15, 2025. Under the agreement, Sungrow will supply its SG320HX-20 (300 kW) string inverters and SG4400UD-20 (4.4 MW) central inverters. These inverters will be deployed across multiple project sites. In Rajasthan, the projects are located in Fatehgarh…
Author: PPD Team Date: April 21, 2025 Power Grid Corporation of India Limited (PGCIL) has declared the Commercial Operation Date (COD) for the Western Region Expansion Scheme-XXVII (WRES-XXVII) as April 16, 2025. The project was physically commissioned earlier, on March 26, 2025. Designed to strengthen the transmission network in Chhattisgarh, the scheme aims to improve power import capability into the state, enhance supply reliability to the Dhamtari substation of Chhattisgarh State Power Distribution Company Limited…
Author: PPD Team Date: April 4, 2025 Power Mech Projects Limited has won a Rs 4.25 billion contract from Mirzapur Thermal Energy (UP) Private Limited, a wholly owned subsidiary of Adani Power Limited (APL), for civil works, including ancillary and raw water reservoir (RWR) works, for the Mirzapur Thermal Power Project. The contract was awarded on March 28, 2025. The scope of work includes civil works and erection of prefabricated structural steel for the boiler,…