NLC India (NLCIL) has commenced commercial operations of the first 660 MW unit of its 3×660 MW Ghatampur Thermal Power Plant (GTPP) in Uttar Pradesh.
The unit, which completed its trial operation on 7 December 2024, began commercial operations on 12 December 2024. This is the first fossil fuel-based thermal power plant commissioned in India in this financial year.
With this addition, NLCIL and its group companies have increased their total installed power generation capacity from 6,071 MW to 6,731 MW.
The GTPP project, developed through Neyveli Uttar Pradesh Power (NUPPL), a joint venture with Uttar Pradesh Rajya Vidyut Utpadan Nigam (UPRVUNL), will meet the growing electricity demands of Uttar Pradesh and Assam. Equipped with supercritical technology, the plant achieves higher efficiency, reduced fuel consumption, and lower emissions.Â
Author: PPD Team Date: September 5, 2025 The Union Cabinet has cleared a six-year, Rs 1,500 crore incentive scheme to boost domestic recycling of critical minerals from secondary sources. Part of the National Critical Mineral Mission, the scheme will support extraction from e-waste, lithium-ion battery scrap, and end-of-life vehicle parts. Incentives include a 20% capital subsidy for new and expanded units, and operating subsidies linked to sales. Large entities can claim up to Rs 50…
Author: PPD Team Date: December 9, 2024 Serentica Renewables plans to invest Rs 500 billion to develop 10,000 MW of renewable energy capacity in Rajasthan, as part of its efforts to position the state as a renewable energy hub. This investment aligns with the company’s participation in Rising Rajasthan 2024. Currently, Serentica has 3,000 MWp of renewable energy under construction in the state, focused on serving India’s commercial and industrial sectors, with over 400 MWp…
Author: PPD Team Date: June 13, 2025 The National Company Law Tribunal (NCLT), Chandigarh Bench, has approved the merger of Inox Wind Energy Limited (IWEL) with Inox Wind Limited (IWL), as per its order dated June 10, 2025. The merger will simplify the business structure of the INOXGFL Group by eliminating the holding company layer and allowing direct promoter shareholding in IWL. It is expected to reduce IWL’s liabilities by around Rs 20.50 billion and…
Author: PPD Team Date: January 7, 2025 The Ministry of Industry and Trade (MoIT) of Vietnam is revising its Power Development Plan VIII (PDP VIII) to incorporate waste-to-energy projects. The revision will integrate local government proposals, focusing on waste resource capacities and their impact on the national grid. The updated plan is set to be submitted to the Prime Minister for approval by February 2025. This follows the approval of Decision No. 262/QD-TTg, which includes…
Author: PPD Team Date: July 31, 2025 The Prime Minister has laid the foundation stone for Powergrid Corporation’s interstate transmission project for evacuating power from Kudankulam Nuclear Power Plant Units 3 and 4 in Tamil Nadu. The project is estimated to cost Rs 550 crore. The scheme involves a 400 kV double-circuit (quad) transmission line from Kudankulam to the Tuticorin-II gas-insulated substation (GIS), along with the installation of two 400 kV GIS terminal bays at…
Author: PPD Team Date: September 9, 2025 Vikram Solar has received an order to supply 336 megawatts (MW) of solar modules to L&T Construction. The modules will be deployed at Khavda, Gujarat, where the company has supplied earlier projects as well. For this order, Vikram Solar will provide its Hypersol G12R modules built on N-type technology. The modules are designed with up to 80 per cent bifaciality, improved performance in high temperatures, and a year-on-year…