Kalpataru energises 101.39 km transmission lines in Rajasthan
Kalpataru Projects International Limited (KPIL) has completed the charging and energisation of the WO-467A2/B2/E3 transmission project in Rajasthan, comprising 765 kV and 400 kV double-circuit (D/C) loop-in loop-out (LILO) transmission lines with a combined length of 101.39 km.
The project forms part of the transmission network in the Northern Region and includes infrastructure associated with the Beawar LILO transmission system.
Project details
The 765 kV D/C LILO transmission line, spanning 68.30 km, was energised on July 23, 2026. Earlier, the 400 kV D/C LILO transmission line, measuring 33.09 km, was energised on April 3, 2026.
The charging and energisation activities were completed without any observations, with all system parameters operating within the prescribed limits.
The successful commissioning of both transmission lines adds over 100 km of high-voltage transmission infrastructure to the Northern Region network and supports power transfer capabilities in Rajasthan, which continues to witness significant additions in renewable and conventional generation capacity.
The completion of the project marks another transmission milestone for KPIL, which is among the major engineering, procurement and construction (EPC) contractors in the power transmission sector.