Similar Posts
JSW Steel to commission 580 MW renewable power by March 2025
JSW Steel’s Board has approved an expanded power purchase agreement (PPA) to procure renewable power for a total of 2,507 MW across its sites at Vijayanagar, Dolvi, Salem, and Anjar. Of the initial 1,637 MW commitment, 375 MW has already been commissioned, with an additional 580 MW expected to come online by March 2025. The…
Greece becomes net exporter of electricity
Greece has shifted from being a net importer to a net exporter of electricity, now regularly supplying up to a third of its daily production to neighbouring countries. Greek electricity exports reached 2 GW out of a total production of 6 GW, with countries such as Albania, North Macedonia, Bulgaria, Turkey, and Italy receiving significant…
India | Generation | NewsMoxie Power secures 558 MW supply contract from TNPDCL
Adani Power Limited’s subsidiary, Moxie Power Generation Ltd, has received a Letter of Award from Tamil Nadu Power Distribution Corporation Limited (TNPDCL) to supply 558 MW of power for five years, providing long-term revenue visibility for the company’s Tuticorin plant. Moxie Power emerged as the lowest bidder in a competitive bidding process, quoting a tariff…
BII, CIP launch $300 million India renewables platform
British International Investment and Copenhagen Infrastructure Partners have launched North Star, a $300 million platform aimed at developing utility-scale renewable energy projects in India. The platform was announced on Thursday at the Global Partnerships Conference in London. Under the arrangement, BII and CIP will each commit up to $150 million, with CIP investing through its…
Green Energy Corridor Phase I nears finish line
The Green Energy Corridor (GEC) Phase I is close to completion in four states, with 20 GW of the planned 24 GW renewable energy capacity already commissioned. The remaining 4 GW is expected to be completed soon. GEC Phase I was launched to improve grid infrastructure for integrating large-scale renewable energy. It spans eight states:…
CTU issues advisory on additional RE capacity in connectivity studies
The Central Transmission Utility (CTU) has issued a follow up advisory on processing generator connection applications where installed capacity in simulation studies differs from the capacity stated in the connectivity grant letter for renewable energy (RE) plants and parks. Citing a Central Electricity Regulatory Commission (CERC) order dated December 8, 2025 in Petition No. 14/SM/2025,…
