FGD retrofitting in thermal power plants reaches 11% of total capacity
Author: PPD Team Date: December 18, 2024
Author: PPD Team Date: December 18, 2024
The retrofitting of thermal power plants with flue-gas desulphurization (FGD) units has reached only 11.1% of the total installed capacity, according to a report presented in Parliament.
Union Power Minister Manohar Lal informed the Rajya Sabha on December 16, 2024, that FGD units have been commissioned in 44 thermal power plants, representing a combined capacity of 22,590 MW out of the total target of 2,04,160 MW across 537 units.
Work on FGD retrofitting is underway for 233 units with a capacity of 1,02,040 MW, accounting for 50% of the total. Contracts have been awarded for these units, while 138 units with a capacity of 43,987 MW are still under tendering, and 122 units totalling 35,543 MW are in the pre-tendering stage.
Thermal plants are required to comply with emission norms set by the Ministry of Environment, Forest and Climate Change (MoEF&CC), and failure to meet FGD installation deadlines will result in “environment compensation” fees, ranging from Rs 0.20 to Rs 0.40 per kWh depending on the delay.
Uttar Pradesh leads with 10 units totalling 4,300 MW in FGD installation, followed by Maharashtra (3,770 MW) and Madhya Pradesh (3,570 MW).
Author: PPD Team Date: March 24, 2025 Bharat Heavy Electricals Limited (BHEL) has secured a major contract from Gujarat State Electricity Corporation Limited (GSECL) for the expansion of the Ukai thermal power station in Tapi district, Gujarat. The company received a letter of intent (LoI) for the engineering, procurement, and construction (EPC) package of the 1×800 MW extension unit 7. The contract, valued at approximately Rs 75 billion, includes the supply, erection, testing, and commissioning…
Author: PPD Team Date: December 10, 2025 Kalpataru Projects International Limited has received new contracts worth about Rs 2,003 crore across its domestic and international operations. The company announced the wins in a press release dated 10 December 2025. The orders fall under the Buildings and Factories segment in India and the Power Transmission and Distribution business in India and overseas. The company said the Transmission and Distribution awards expand its presence in key markets….
Author: PPD Team Date: December 8, 2025 Russia has started supplying nuclear fuel for the upcoming units of the Kudankulam Nuclear Power Plant. Rosatom said the first cargo flight carrying VVER 1000 fuel assemblies from the Novosibirsk Chemical Concentrates Plant in Siberia has reached India. Seven flights will deliver the full reactor core and reserve fuel for units 3 and 4. The shipments are part of a 2024 contract that guarantees fuel for the entire…
Author: PPD Team Date: February 2, 2025 The Economic Survey 2024-25 argues against shutting down coal-based power plants, citing a lack of economic rationale. It states that India should focus on becoming a developed country by 2047 before targeting net-zero emissions by 2070. India’s coal-fired power plants, mostly commissioned in the 2010s, still have substantial lifespans. Unlike the US and Europe, which can transition to natural gas, India relies on coal due to its reserves…
Author: PPD Team Date: August 26, 2025 NHPC Limited has revised the timeline for completing its 300 MW Karnisar solar power project in Rajasthan. The remaining capacity is now expected to be commissioned by September 30, 2025, instead of the earlier target of August 31. As of now, 214.28 MW of the project has been commissioned. In July, NHPC also began commercial operations of a 53.57 MW solar unit under Phase IV of its 1,000…
Author: PPD Team Date: January 29, 2025 BAJEL Projects Limited, formerly Bajaj Electricals Limited, has received a Notification of Award from Power Grid Corporation of India Limited (PGCIL) for Transmission Line Package TL03. The contract involves constructing a 120 km, 765 kV double-circuit transmission line (Dausa – Ghiror Part-III) under the Rajasthan Renewable Energy Zone (REZ) Phase-IV (Part-4: 3.5 GW) evacuation system. PGCIL invited bids in September 2024, and the project is expected to be…