Credence Solar begins work on 2 GW cell plant in Gujarat
Author: PPD Team Date: March 17, 2026
Author: PPD Team Date: March 17, 2026
Credence Solar Panels Pvt. Ltd. has started construction of a 2 GW solar cell manufacturing facility in Rajkot, Gujarat. The Rajkot facility will produce G12 and G12R solar cells and is scheduled for commissioning in the fourth quarter of 2026. Once operational, the plant is expected to improve vertical integration by enabling tighter control over supply chains, product quality, and technology deployment.
The investment aligns with India’s efforts to expand domestic solar manufacturing capacity. A key policy instrument is the Approved List of Cell Manufacturers (ALCM), which aims to promote local production and reduce reliance on imports. The ALCM continues to influence procurement decisions across the renewable energy sector.
The facility will support the manufacturing of higher-wattage modules using larger cell formats. G12 and G12R cells are gaining wider adoption due to their higher efficiency and greater power output per module. Credence Solar Panels Pvt. Ltd. has already introduced G12-based PV modules with capacities up to 730 watts, positioning it among early adopters of large-format module technology in India.
Additional cell manufacturing capacity is expected to support the strengthening of India’s solar supply chain and contribute to broader targets for scaling domestic renewable energy production.
The featured photograph is for representation only.
Author: PPD Team Date: June 30, 2025 The World Bank has approved a $146 million grant through the International Development Association (IDA) to restore Syria’s damaged power infrastructure. The Syria Electricity Emergency Project (SEEP) aims to repair high-voltage lines and substations, with a focus on war-affected regions and key 400kV interconnections with Jordan and Türkiye. Most parts of Syria currently receive just two to four hours of power daily, affecting water, healthcare, and food services….
Author: PPD Team Date: August 29, 2025 G R Infraprojects Limited has received a Letter of Intent (LOI) for the “Transmission system for Evacuation of Power from RE Projects in Rajgarh (1500 MW) SEZ in Madhya Pradesh-Phase III and Evacuation of Power from RE Projects in Neemuch (1000 MW) SEZ in Madhya Pradesh-Phase II.” The award was issued on 27 August 2025 by REC Power Development and Consultancy Limited. The project is being implemented through…
Author: PPD Team Date: September 13, 2024 NTPC has signed an MoU with USAID’s India Mission to create a roadmap for transforming its townships and offices into net zero establishments. NTPC aims to achieve net zero Scope 2 emissions in its townships and offices by FY 2025-26. Efforts are also underway to make these locations net zero in water and waste. The MoU outlines the development of strategies and a roadmap for achieving these goals,…
Author: PPD Team Date: March 30, 2026 The Atomic Energy Regulatory Board (AERB) has granted approval to begin excavation activities for Units 1 and 2 of the Mahi Banswara Rajasthan Atomic Power Project (MBRAPP) in Rajasthan. The units are based on the standard 700 MWe Pressurised Heavy Water Reactor (PHWR) design. The project is located in Banswara district, Rajasthan, and is being implemented by Anushakti Vidyut Nigam Limited (ASHVINI). The company was formed in 2024…
Author: PPD Team Date: March 24, 2026 Power Grid Corporation of India (PGCIL) has increased its capital expenditure (capex) guidance for FY26 to Rs 35,000 crore and has already surpassed the target, reporting actual capex of Rs 35,540 crore as of March 22, 2026, or about 102% of the revised estimate. The company had initially set a capex target of Rs 28,000 crore at the start of FY26. This was revised to Rs 32,000 crore…
Author: PPD Team Date: June 24, 2025 Envision Energy India’s wind turbine model EN-182/5.0 50 Hz TC has been approved under the Ministry of New and Renewable Energy’s (MNRE) Revised List of Models and Manufacturers (RLMM). This approval is mandatory for supplying wind turbines in India. The EN-182/5 MW turbine has a 181 metre rotor diameter, 105.56 metre hub height, and 89 metre blades mounted on a tubular steel tower. It is certified under IEC61400-22:2010…