CERC notifies February 2026 coal escalation rates
Author: PPD Team Date: March 20, 2026
Author: PPD Team Date: March 20, 2026
The Central Electricity Regulatory Commission (CERC) has notified monthly escalation rates for February 2026 applicable to payments under power purchase agreements (PPAs) executed by distribution licensees.Â
Escalation rates
CERC has specified the following rates for February 2026:
These rates are used in tariff adjustments under competitively bid PPAs.
Regulatory basis
The notification has been issued under Clause 5.6(vi) of the Ministry of Power’s Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees dated January 19, 2005, as amended.
It follows a Ministry of Power communication dated April 13, 2022, and a resolution dated July 11, 2022, which introduced changes linked to coal allocation under the Scheme for Harnessing and Allocating Koyala Transparently in India (SHAKTI) policy.
Applicability
The escalation rates apply to PPAs executed under the bidding guidelines and model bidding documents, including those incorporating SHAKTI-based coal allocation provisions.
The notification was signed by Harpreet Singh Pruthi, Secretary, CERC, and published in the Gazette of India on March 16, 2026.
The featured photograph is for representation only.
Author: PPD Team Date: January 9, 2026 On 30 December 2025, the Kerala State Electricity Regulatory Commission (KSERC) issued an order provisionally approving the Resource Adequacy Plan for Kerala for 2025-26 to 2035-36. The plan, prepared by the Central Electricity Authority at the request of Kerala State Electricity Board Limited, was approved subject to specific observations and a requirement for technical review. Demand projections and proposed capacity mix The CEA study projects Kerala’s energy requirement…
Author: PPD Team Date: March 22, 2026 The Central Electricity Regulatory Commission (CERC) has notified the Terms and Conditions of Tariff (Second Amendment) Regulations, 2026, establishing a tariff framework for battery energy storage systems (BESS) co-located with coal, lignite, and gas-based thermal generating stations, as well as interstate transmission infrastructure. Supplementary tariff for integrated storage The amendment introduces a supplementary tariff structure to recover costs of storage assets integrated with existing generating stations or transmission…
Author: PPD Team Date: November 11, 2025 The Delhi Electricity Regulatory Commission (DERC) has granted in-principle approval to Tata Power Delhi Distribution Limited (TPDDL) to procure 200 MW of firm and dispatchable renewable energy integrated with storage, with an additional 200 MW greenshoe option. The approval, issued on November 3, 2025, allows TPDDL to launch a competitive bidding process for projects that combine renewable generation and battery storage to supply round-the-clock clean power. The initiative…
Author: PPD Team Date: August 19, 2025 Â The Gujarat Electricity Regulatory Commission (GERC) has notified the Procurement of Energy from Renewable Sources Regulations, 2025, laying out fresh renewable power purchase obligations (RPPO) for the state. The rules mandate distribution companies, open access consumers, and captive power users above 100 kilowatts to procure a rising share of their electricity from renewable energy and storage until 2030. The regulations, published in the state gazette on August…
Author: PPD Team Date: January 6, 2026 The Himachal Pradesh Electricity Regulatory Commission issued a draft notification on 24 December 2025 proposing the Himachal Pradesh Electricity Regulatory Commission (Himachal Pradesh Electricity Grid Code) Regulations, 2025 to replace the 2008 State Grid Code. The draft sets a comprehensive framework for planning, connection, operation, scheduling, and compliance of the intra state transmission system. Stakeholders can submit objections and suggestions within thirty days from its publication in the…
Author: PPD Team Date: March 18, 2026 The Central Electricity Regulatory Commission (CERC) has proposed revising the congestion charge framework for inter-state electricity transmission, replacing the flat rate in place since March 2010. The proposal was issued in an order dated March 13, 2026 (Petition No. 1/SM/2026), with stakeholder comments invited by April 6, 2026. Proposed mechanism CERC has proposed linking congestion charges to the Deviation Settlement Mechanism (DSM) Regulations, 2024, which replaced the earlier…