ArcelorMittal to invest USD 900 million in 1 GW renewable energy projects
Author: PPD Team Date: December 23, 2025
Author: PPD Team Date: December 23, 2025
ArcelorMittal has announced that it will invest USD 900 million in three renewable energy projects in India with a combined capacity of 1 GW. The projects will increase the company’s global renewable energy capacity to 3.3 GW on completion.
The projects will be located in Maharashtra, Rajasthan, and Gujarat, with power supplied to AMNS India, the steelmaking joint venture between ArcelorMittal and Nippon Steel. The portfolio includes a 36 MW solar project in Amaravati, Maharashtra, targeted for completion in H1 2027. A 400 MW solar project with a 500 MWh battery energy storage system is planned in Bikaner, Rajasthan, while an integrated project in Bachau, Gujarat, will comprise 250 MW of wind, 300 MW of solar, and 300 MWh of battery storage. Both are scheduled for completion in H1 2028.
The company said the projects will double its renewable energy capacity in India to 2 GW and are expected to deliver annual carbon dioxide savings of about 1.6 million tonnes. Power from these assets will support AMNS India’s steelmaking operations.
Separately, AMNS India is developing a 550 MW renewable energy project in Bachau, Gujarat, comprising 300 MW of solar and 250 MW of wind capacity, with expected annual carbon dioxide savings of about 0.9 million tonnes.
The featured photograph is for representation only.
Author: PPD Team Date: February 19, 2025 Shakti Pumps Limited has invested Rs 390 million in its wholly owned subsidiary, Shakti Electric Vehicle (EV) Mobility Private Limited, by subscribing to 4 million equity shares of face value Rs 10 each. The subsidiary will focus on manufacturing, processing, trading, and distributing EV motors and charger controllers. Shakti EV Mobility, incorporated in December 2021, aims to drive innovation and meet the growing demand for EV components, as…
Author: PPD Team Date: March 24, 2025 The Federal Government of Nigeria (FGN) has announced plans to increase the country’s power transmission capacity from 8,500 MW to 10,000 MW by the end of 2026. On March 4, 2025, Nigeria recorded its highest peak power generation of 5,801.84 MW, which was successfully transmitted to distribution centres nationwide. As per Nigeria’s Integrated Resource Plan (IRP), USD 192 million has been allocated for the construction of 16 transmission…
Author: PPD Team Date: December 31, 2025 Power Grid Corporation of India Limited (PGCIL) has awarded Bharat Heavy Electricals Limited (BHEL) a major contract worth Rs 3,618 million for supplying high-capacity transformers. The contract forms part of a bulk procurement package aimed at strengthening national transmission infrastructure. The state-owned transmission utility finalised the award for the “765 kilovolt (kV) Transformer Package TTR-15/BULK.” The scope covers the supply of 17 units of 765/400 kV, 500 Mega…
Author: PPD Team Date: February 6, 2026 The Ministry of New and Renewable Energy (MNRE) has issued the fourth revision of its Approved List of Models and Manufacturers (ALMM) for solar photovoltaic cells. The update adds a new manufacturer and expands the approved model range of existing producers, reinforcing the government’s focus on domestic solar manufacturing. The revised list, dated February 5, 2026, includes Evervolt Solar Technology India Private Limited as a first time entrant….
Author: PPD Team Date: May 21, 2025 The Board of Directors of NLC India Limited has approved forming a joint venture (JV) with Rajasthan Rajya Vidyut Utpadan Nigam Limited (RRVUNL) to develop the Gurha Thermal Power Project. The decision was made on May 19, 2025. The JV will have a 74:26 equity split between NLC India and RRVUNL. It will be responsible for establishing, maintaining, and operating the 3×125 MW thermal power project. The proposed…
Author: PPD Team Date: April 4, 2025 Larsen & Toubro (L&T), through its Heavy Engineering arm, has completed the delivery of four steam generators (SGs) for the Kaiga Atomic Power Station in Karnataka. These are part of the indigenously developed 10×700 MWe Pressurised Heavy Water Reactor Fleet Programme. The fourth SG was despatched nine months ahead of schedule. The full set of four SGs was delivered in 45 months, with the first completed in just…