APTRANSCO awards 1,000 MW BESS tender with VGF support
Author: PPD Team Date: December 3, 2025
Author: PPD Team Date: December 3, 2025
The Transmission Corporation of Andhra Pradesh Limited (APTRANSCO) has announced the winners of its VGF tender for 1,000 MW and 2,000 MWh standalone BESS projects. The tender was issued in August 2025 under a single-stage, two-envelope system that required both technical and financial bids.
SVR Electro Projects secured 25 MW and 50 MWh at a tariff of Rs 148,000 per MW per month. Ecoren Energy won 275 MW and 550 MWh, Bhagwati Group took 75 MW and 150 MWh, and Legion Energy Products received 25 MW and 50 MWh. These bidders quoted tariffs of Rs 150,000 per MW per month. Bondada Engineering won 225 MW and 450 MWh, and Power Grid Corporation of India secured 150 MW and 300 MWh, both at Rs 164,000 per MW per month. Ecoren Energy also added 225 MW and 450 MWh at Rs 165,000 per MW per month.
Projects will be developed on a build, own and operate basis. VGF support will be capped at Rs 1.8 million per MWh and will be released in three phases. Developers will sign a Battery Energy Storage Purchase Agreement with APTRANSCO and the state distribution companies. Sites span several substations, including Hindupur, Talaricheruvu, Kalikiri, Pampanuruthanda, Maradam, Simhachalam, and Gajuwaka.
Below is a table summarising winners and capacities:
The featured photograph (Source: Envision Energy) is for representation only.
Author: PPD Team Date: February 4, 2025 Solex Energy Limited has successfully commissioned an 800 MW high-speed solar module manufacturing line in Surat, Gujarat. The facility produces n-Type TOPCon rectangular cell-based Tapi-R series modules, with capacities ranging from 585 Wp to 625 Wp. This production line operates 30% faster than other Indian facilities, increasing output efficiency and reducing lead times. Equipped with Artificial Intelligence (AI) and Automated Optical Inspection (AOI), the facility ensures enhanced quality…
Author: PPD Team Date: January 16, 2025 The Tripura Renewable Energy Development Agency (TREDA) has set a target of installing 10,895 solar-powered pumps for irrigation in rural farmlands under the PM KUSUM scheme. Of the target, 3,616 pumps have already been installed, providing irrigation to 7,232 acres of farmland and benefiting 3,616 marginal farmers. Work is underway for the installation of an additional 5,051 pumps, with steps being taken to establish the remaining 2,264 pumps…
Author: PPD Team Date: January 17, 2025 Ecozen, a clean energy technology company, has raised over $23 million in debt funding from investors including responsAbility Investments, Northern Arc Capital, and Maanaveeya Development & Finance. The funds will support the scaling of flagship solutions like Ecotron, Ecofrost, and advanced motor control systems, as well as domestic and international expansion. The company has achieved a compound annual revenue growth rate exceeding 83% over the last three years….
Author: PPD Team Date: June 3, 2025 Schneider Electric Infrastructure Ltd (SEIL) plans to invest about Rs 200 crore to expand manufacturing capacity for circuit breakers and switchgear panels. The investment will support new facilities and upgrades aimed at both domestic and international markets. SEIL will invest Rs 90.60 crore to set up a new circuit breaker plant in Kolkata with an annual capacity of 40,000 units. The plant is scheduled for commissioning before the…
Author: PPD Team Date: November 11, 2025 Waaree Renewable Technologies Ltd. has expanded the value of its existing engineering, procurement, and construction (EPC) contract for a 980 MWp / 700 MWac solar power project by Rs 27.22 crore. The company received formal confirmation of the scope enhancement on November 10, 2025. In a regulatory filing, Waaree stated that the revised contract now totals Rs 1017.82 crore, inclusive of taxes. The company clarified that the expansion…
Author: PPD Team Date: March 24, 2025 The Ministry of Power (MoP) has directed all states and implementing agencies to finalise the awarding of battery energy storage system (BESS) contracts by June 2025. This move aims to ensure the completion of the viability gap funding (VGF) programme by May 2027. Once contracts are awarded, the programme will require 18 to 24 months for implementation. Due to declining BESS prices, the initial target of 4,000 MWh…