APTRANSCO plans Rs 9300 crore transmission expansion in Andhra Pradesh
Author: PPD Team Date: January 29, 2026
Author: PPD Team Date: January 29, 2026
The Transmission Corporation of Andhra Pradesh Ltd (APTRANSCO) has outlined plans to complete 55 major transmission projects with a total investment of Rs 9,319.30 crore. The programme will strengthen the state’s power transmission network and ensuring reliable electricity supply across Andhra Pradesh.
According to G Surya Sai Praveenchand, Joint Managing Director of the Transmission Corporation of Andhra Pradesh Ltd (APTRANSCO), the projects will add 8,853 MVA of transformation capacity and 1,558 circuit kilometers of transmission lines. The scope includes new 400 KV, 220 KV and 132 KV substations at locations such as Kakinada SEZ, Achutapuram, Gudivada and Ainavalli. The initiatives form part of the state government’s push to provide round the clock quality power to all categories of consumers.
APTRANSCO currently operates 380 substations and 1,030 power transformers with an aggregate capacity of 71,049 MVA. Its transmission network extends over more than 33,000 circuit kilometers of high voltage lines across the state.
To further improve grid reliability and manage peak demand, APTRANSCO is also implementing Battery Energy Storage System (BESS) projects in two phases. The planned storage capacity totals 1,500 MW or 3,000 MWh and is intended to support grid stability as renewable energy penetration increases.
The featured photograph is for representation only.
Author: PPD Team Date: December 24, 2024 Lending to renewable energy (RE) projects in India surged by 63% in 2023, reaching Rs 302.55 billion, compared to the previous year, according to a report by the Centre for Financial Accountability. Solar energy accounted for 49% of the funding, with Rs 148.14 billion directed toward solar projects. Hybrid projects saw a 31% year-on-year increase, attracting Rs 137.73 billion. Only one loan was made for wind energy projects,…
Author: PPD Team Date: February 4, 2025 The Union Government has allocated a total outlay of Rs 218.47 billion to the Ministry of Power (MoP) under the Union Budget for 2025-26, announced on February 1, 2025. The key allocations include: Rs 160.21 billion for the Revamped Distribution Sector Scheme (RDSS). Rs 8.5 billion for Strengthening of Power Systems, which includes Rs 3.04 billion for the North Eastern Region Power System Improvement Project (NERPSIP) and Rs…
Author: PPD Team Date: December 23, 2025 Bondada Engineering has secured an engineering, procurement, and construction (EPC) order worth Rs 945 crore from NLC India Renewables Limited, acting on behalf of NLC India Limited, for solar projects at the RVUNL Solar Park in Bikaner, Rajasthan. In a regulatory filing, Bondada Engineering said the order covers Balance of System works for 810 MW of solar power capacity, along with full EPC execution and three years of…
Author: PPD Team Date: October 17, 2024 The Ministry of New and Renewable Energy (MNRE) has expanded the Approved List of Models and Manufacturers (ALMM) by adding 2,094 MW of solar module capacity, bringing the total capacity to 58,422 MW. Major additions include SAEL Solar P6 with 2,065 MW and Grew Energy with 29 MW. Meanwhile, ITI, Jyotitech Solar, SunField Energy, and Suryakamal Energy have been removed from the list. New entrants on the provisional…
Author: PPD Team Date: September 24, 2025 ACWA Power has signed a memorandum of understanding (MoU) with Larsen & Toubro’s (L&T) renewables division for the development of the renewables and grid components of the Yanbu green ammonia project in Saudi Arabia. The project is planned as a fully integrated hub powered entirely by solar and wind energy. The MoU covers multiple facilities, including solar photovoltaic plants, wind projects, battery energy storage systems, substations, and transmission…
Author: PPD Team Date: October 14, 2025 Larsen & Toubro Ltd (L&T) has announced multiple major order wins in the Middle East, spanning its Power Transmission & Distribution (PT&D) and Hydrocarbon Onshore businesses. The PT&D vertical has secured grid infrastructure projects worth between Rs 2,500 crore and Rs 5,000 crore, including a 400 kV substation in the UAE to establish a direct interconnection for the GCC super grid, new 132 kV substations to meet growing…