PSPCL signs PPA with SAEL for 400 MW solar power at Rs 2.97/kWh
Author: PPD Team Date: May 5, 2025
Author: PPD Team Date: May 5, 2025
Punjab State Power Corporation Limited (PSPCL) has signed a 25-year power purchase agreement (PPA) with Sukhbir Agro Energy Limited (SAEL) for 400 MW of solar power projects in Punjab. SAEL secured the capacity in 2024 at a tariff of Rs 2.97 per kWh.
The agreement follows PSPCL’s tender issued in May 2023 for procurement of 1,000 MW solar power through tariff-based competitive bidding from projects of 5 MW and above, located anywhere in the state.
The 400 MW project is to be commissioned within 24 months from the date of signing the PPA.
Author: PPD Team Date: April 22, 2025 Toshiba Transmission & Distribution Systems (India) (TTDI) will invest Rs 562 crore to expand its manufacturing capacity in Telangana. The announcement came after TTDI signed a memorandum of understanding (MoU) with the Telangana government during a ceremony in Tokyo. The event was attended by Telangana Chief Minister Anumula Revanth Reddy and Hiroshi Furuta, Chairman and Managing Director of TTDI. The investment is expected to create over 250 direct…
Author: PPD Team Date: November 14, 2025 The New and Renewable Energy (MNRE) Minister Pralhad Joshi has launched a call for proposals for pilot projects that aim to produce green hydrogen from biomass and waste materials. The government has set aside Rs 1 billion for these projects, in addition to Rs 1 billion already assigned to start-up initiatives under the National Green Hydrogen Mission. The Biotechnology Industry Research Assistance Council will run the programme and…
Author: PPD Team Date: March 6, 2026 Jyoti Structures Limited has completed and commissioned the 400 kV Gadag–II transmission line project in Karnataka for ReNew Power. The project forms part of an interstate transmission system developed to evacuate renewable energy from the Koppal Solar Energy Zone. The project includes 100 circuit kilometres (ckm) of twin High Temperature Low Sag (HTLS) transmission lines connecting the Gadag Power Station and the Koppal Power Station. The line passes…
Author: PPD Team Date: November 19, 2025 Gujarat Urja Vikas Nigam Ltd has closed its Phase VII tender for 4 GWh of battery storage capacity. The process covered 2 GW with two hours of storage and led to tariffs between Rs 1.85 lakh and Rs 1.89 lakh per MW per month. The auction’s lowest tariff was Rs 1.8539 lakh per MW per month, quoted by Sun Drops Energia, also known as KP Green. The highest…
Author: PPD Team Date: February 13, 2025 The Small Industries Development Bank of India (SIDBI) and Agence Française de Développement (AFD) have signed a $100 million credit facility agreement aimed at enhancing green finance solutions for micro, small, and medium enterprises (MSMEs) in India. Under the agreement, AFD will provide SIDBI with a $100 million credit line, which will be used to offer MSMEs access to affordable financing for energy-efficient technologies, renewable energy solutions, and…
Author: PPD Team Date: November 7, 2024 Cadeler has signed firm contracts for transporting and installing 64 offshore wind turbines, each with a capacity of 15 MW, along with their foundations for the East Anglia 2 (EA2) wind farm, a 960 MW project in the UK. The contract value for Cadeler ranges between €360 million ($387 million) and €382 million. ScottishPower Renewables is developing the EA2 project off the coast of East Anglia, with offshore…