Arunachal & Sikkim grid upgrade completion expected by March 2025

The Centrally-funded “Comprehensive Scheme for Transmission and Distribution (T&D) System in Arunachal Pradesh & Sikkim” is set to be fully commissioned by March 2025, with 62% of the project completed as of August 31, 2024. The project involves 294 elements, including transmission lines and substations. While Sikkim has completed 41 of 55 elements, Arunachal Pradesh has commissioned 141 of 239 elements. Challenges remain in transmission line construction, with only 1,029 ckm of the planned 4,241…