Transmission and transformation capacity additions exceed targets in FY25

The Central Electricity Authority (CEA) reports that transmission and transformation capacity additions in the first seven months (April-October) of FY25 have surpassed planned targets. This marks the first instance of exceeding the target in FY25. A total of 4,337 circuit kilometres (ckm) of transmission lines were added, 10% higher than the planned 4,762 ckm. Similarly, 33,265 MVA of substation capacity was achieved, surpassing the target of 30,780 MVA by 8%. Central government utilities, led by…