India | Generation | News
PVUNL synchronises Unit-2 of 800 MW Patratu plant
Patratu Vidyut Utpadan Nigam Limited (PVUNL) has synchronised Unit-2, an 800 MW unit of the Patratu Super Thermal Power Plant (STPP), with the grid on March 17, 2026. The milestone advances the project towards full commissioning of Phase I. Project progress The development follows the commercial operation of Unit-1, which was declared on November 5, 2025. Unit-2 has been synchronised but has not yet achieved commercial operation. PVUNL Chief Executive Officer (CEO) Ashok Sehgal stated…