Swedish court approves Hydro Energi’s PPA settlement with Markbygden
Author: PPD Team Date: November 4, 2024
Author: PPD Team Date: November 4, 2024
Norwegian renewable company Hydro Energi has settled its long-term power purchase agreement (PPA) with Swedish wind farm operator Markbygden Ett.
Originally signed in 2017, the PPA was intended to supply 1.65 TWh annually from 2021 to 2039, backing the financing of Markbygden’s onshore wind park in northern Sweden, which had a projected output of 2.2 TWh per year.
However, due to financial difficulties, Markbygden Ett halted power deliveries to Hydro Energi on February 6, 2023, and entered a reorganisation in November 2023. By Q3 2024, the undelivered power amounted to 2.5 TWh.
As part of the reorganisation plan approved by Sweden’s Umea district court, Hydro is set to receive €248 million ($268 million) in compensation for non-performance and voluntary contract termination, though the final amount will depend on the wind park’s future sale and a value-sharing agreement.
Hydro’s smelters in Norway maintain a stable power sourcing position through 2030, with an average annual hydropower output of 9.4 TWh and a contract portfolio of 10 TWh. Hydro continues to explore additional renewable sources, including onshore wind, to ensure cost-effective energy for its operations.
Author: PPD Team Date: September 3, 2025 China General Nuclear Power Group (CGN) said the Hualong One has become the world’s most deployed third-generation nuclear reactor, with 41 units operating or under construction. Each unit generates over 10 billion kilowatt-hours of electricity annually and reduces carbon dioxide emissions by 8.16 million tonnes. Seven units are already grid-connected. The design, developed in China, meets international safety standards, holds European Utility Requirements certification, and has cleared the…
Author: PPD Team Date: March 1, 2025 Borosil Renewables Limited has completed its investment of Rs 178.2 million in Clean Max Prithvi Private Limited (CMPPL) in two tranches. The investment follows Borosil Renewables’ initial acquisition of a 49 per cent stake in CMPPL for Rs 49,000, announced in September 2024. The company later invested Rs 35.6 million and Rs 142.6 million, receiving 31,058 and 1,22,797 equity shares, respectively, at a face value of Rs 10…
Author: PPD Team Date: December 5, 2024 Tata Projects Ltd, in collaboration with the Power Grid Company of Bangladesh (PGCB), has completed the 112-km, 400-kV double-circuit Barapukuria-Bogra transmission line project, valued at $120 million. The project, executed in just 14 months, involved the supply of approximately 2,700 km of ACCC® Dhaka-size conductor by Apar Industries, with installation supported by Zeck tensioners and porcelain insulators. The line is part of the larger Barapukuria-Bogra-Kaliakoir transmission project, aimed…
Author: PPD Team Date: April 15, 2025 Insolation Green Energy Private Limited, a wholly-owned subsidiary of Insolation Energy Limited, secured a Rs 360.1 million contract with Nexgen Energies Private Limited on April 13, 2025. The contract is for the supply of Mono PERC solar photovoltaic (PV) modules, which will be used for a solar power project in India. The modules are expected to be supplied in FY 2026. Insolation Energy is known for manufacturing high-efficiency…
Author: PPD Team Date: January 24, 2025 Onix Renewable, Jindal India Renewable Energy, NTPC Renewable Energy, Kolar Solar Power (Rays Power Infra), ReNew Solar Power, and Adani Renewable Energy Holding Nine (Adani Green Energy Limited) have won NHPC Limited’s auction to develop 1,200 MW of interstate transmission system (ISTS)-connected solar power projects, incorporating 600 MW/1,200 MWh energy storage systems (ESS). Onix, Jindal, NTPC, and Kolar were allocated capacities of 100 MW, 180 MW, 300 MW,…
Author: PPD Team Date: December 11, 2024 The European Commission (EC) has approved a €2.6 billion ($2.7 billion) scheme to support Estonia’s offshore wind energy sector, advancing the country’s goal of achieving net-zero emissions. This initiative, aligned with the Estonian Maritime Spatial Plan, will fund the construction and operation of offshore wind farms through a competitive bidding process. The scheme, part of the State Aid Temporary Crisis and Transition Framework (TCTF), is open until December…