Author: PPD Team Date: 18/02/2025

APTEL passes order in KPTCL and HESCOM’s appeal against KERC tariff decision
The Appellate Tribunal for Electricity (APTEL) has issued an order regarding the appeal filed by Karnataka Power Transmission Corporation Limited (KPTCL) and Hubli Electricity Supply Company Limited (HESCOM) against the Karnataka Electricity Regulatory Commission (KERC) ruling in OP No. 20 of 2013, dated June 19, 2014. The KERC had fixed the tariff payable by KPTCL and HESCOM to Global Energy Private Limited (GEPL) at Rs 5.72 per unit for power supplied during April to June 2010 under Section 11(2) of the Electricity Act.
APTEL highlighted that the Rs 5.72 per unit rate was determined without discounting transmission charges from the weighted average market price for the specified period, despite APTEL’s earlier ruling that such deductions should be made. Additionally, APTEL pointed out that KERC had dismissed HESCOM’s claim for set-off of amounts owed to GEPL without providing any reasoning. Since KERC had not addressed the set-off issue, APTEL ruled it was not appropriate to consider this in the appellate proceedings.
APTEL has remanded the matter to KERC on two key points: HESCOM’s set-off claim and the calculation of transmission charges to be deducted from the weighted average market price. KERC is instructed to reconsider both aspects after providing both parties with a fair hearing, in line with the observations and directions in APTEL’s judgment.
Petition No: Appeal No. 272 of 2014 | Click here to read the full order.
APTEL partly allows PCKL and others’ appeal against KERC order
The Appellate Tribunal for Electricity (APTEL) has partly allowed the appeal filed by Power Company of Karnataka Limited (PCKL) and others, challenging the Karnataka Electricity Regulatory Commission (KERC) order in O.P. Nos. 40 and 41 of 2010, dated February 14, 2013.
APTEL observed that the state commission failed to determine the discount on transmission charges as previously directed in APTEL’s remand order. The appellants claimed that accounting for marketing and transmission charges appropriately would reduce the tariff by Rs 0.31 per unit. While KERC had already acknowledged Rs 0.10 per unit for marketing expenses, the appellants sought a transmission charge discount of Rs 0.21 per unit. However, the appellants conceded that the transmission charges could not exceed Rs 0.16 per unit. As such, APTEL ruled that the transmission charge discount could not exceed Rs 0.16 per unit, as agreed by the respondent.
As a result, APTEL directed the appellants to pay Himatsingka Seide Limited and J.K. Cement Works Rs 5.56 per unit, along with interest as per the original order. The payment is to be made promptly, within four months from the date of receipt of the judgment, to compensate for the adverse financial impact caused by the Government of Karnataka’s directions under Section 11(1) of the Electricity Act, requiring the supply of electricity during April to June 2010.
Petition No: Appeal No. 373 of 2024 & IA No. 1623 of 2024 | Click here to read the full order.
RERC notifies Rajasthan Electricity Grid Code Regulations, 2024
The Rajasthan Electricity Regulatory Commission (RERC) has notified the RERC (Rajasthan Electricity Grid Code) Regulations, 2024 (REGC), which will apply to users connected to the intra-state transmission system and state load despatch centre (SLDC) at 33 kV and above. These regulations will also be applicable to new connections and equipment for new works or replacements once the REGC becomes effective.
The regulations mandate SLDCs to develop a load despatch and system operation manual in alignment with REGC, and submit it to RERC for approval, after consulting with users. State transmission utilities (STUs) are required to ensure power evacuation from generating stations for distribution to electricity entities and open access consumers, and to facilitate power exchanges with other entities and through interconnections with the central transmission utility. The state power committee (SPC) will issue guidelines for implementing REGC and facilitating the rules and procedures under its provisions.
To promote operational transparency and reliability, the regulations introduce monitoring mechanisms such as self-audits, third-party audits, and periodic cyber security reviews. SLDCs are also tasked with conducting day-ahead, weekly, monthly, and yearly operational studies to assess and declare the total transfer capability and available transfer capability for electricity imports and exports. Additionally, operational planning studies will be performed to evaluate whether planned operations may lead to deviations from system operational limits as per REGC and Central Electricity Authority standards. Any deviations will be reviewed in monthly SPC meetings, with significant deviations being monitored for timely resolution.
Petition No: Petition No: No. RERC/Secy/Reg –155 | Click here to read the full order.
UERC disposes of PTCUL’s petition for investment approval
The Uttarakhand Electricity Regulatory Commission (UERC) has disposed of the petition filed by Power Transmission Corporation of Uttarakhand Limited (PTCUL) seeking investment approval for the detailed project report (DPR) on the augmentation of the 132 kV Purkul substation in Dehradun from 100 MVA (2×40 MVA + 1×20 MVA) to 120 MVA (3×40 MVA) at the 132/33 kV voltage level.
Initially, PTCUL sought approval for Rs 101 million for the proposed augmentation. However, UERC noted that PTCUL, through a letter dated December 19, 2024, submitted a revised petition with an updated DPR amounting to Rs 234.7 million. This revised proposal aims to increase the substation’s capacity from 80 MVA (2×40 MVA) to 160 MVA (2×40 MVA + 1×80 MVA) and was approved by PTCUL’s board of directors in its 96th meeting on November 25, 2024.
Given that the petitioner has already submitted a new petition for the revised augmentation plan with board approval, UERC concluded that the original petition has become infructuous and does not require further proceedings.
Petition No. 46 of 2024
UPERC grants transmission license to Meerut Shamli Power Transmission
The Uttar Pradesh Electricity Regulatory Commission (UPERC) has approved the petition filed by Meerut Shamli Power Transmission Limited for a transmission license to establish a transmission system for the construction of the Meerut (765 kV)-Shamli (400 kV) double-circuit line on a build, own, operate, and transfer basis.
UPERC noted that the project’s scope and objectives align with the broader public interest by improving the transmission network. The commission confirmed that the bidding process met the request for proposal conditions, including blacklisting requirements, and that all necessary declarations and certifications were submitted and evaluated by the bid evaluation committee.
The transmission license is granted under the following conditions:
- The license will remain valid for 25 years unless revoked earlier.
- If the transmission system remains operational beyond 25 years, the licensee may apply for a 10-year extension at least two years before expiry, subject to prevailing regulations.
- The licensee is prohibited from engaging in electricity trading during the license period.
- The licensee must comply with the Electricity Act, relevant regulations, the Indian Electricity Grid Code, the Uttar Pradesh Electricity Grid Code, standards set by the Central Electricity Authority, and any directives issued by UPERC.
Petition No. 2097 of 2024 | Click here to read the full order.
UPERC grants transmission license to Jewar Transmission
The Uttar Pradesh Electricity Regulatory Commission (UPERC) has approved the petition filed by Jewar Transmission Limited for a transmission license to establish a transmission system for the construction of multiple substations and associated lines on a build, own, operate, and transfer basis. The project includes:
- A 400/220 kV, 2×500 MVA GIS substation in Jewar
- A 220/33 kV, 2×60 MVA GIS substation in Cantt (Chaukaghat), Varanasi
- A 220/33 kV, 3×60 MVA GIS substation in Vasundhara, Ghaziabad
- A 220/132/33 kV, 2×160+2×40 MVA substation in Khaga, Fatehpur
UPERC noted that the project’s scope aligns with the public interest by improving the transmission network. The commission confirmed that the bidding process met the request for proposal conditions, including blacklisting requirements, and that all necessary declarations and certifications were submitted and evaluated by the bid evaluation committee.
The transmission license is granted under the following conditions:
- The license will remain valid for 25 years unless revoked earlier.
- If the transmission system remains operational beyond 25 years, the licensee may apply for a 10-year extension at least two years before expiry, subject to prevailing regulations.
- The licensee is prohibited from engaging in electricity trading during the license period.
- The licensee must comply with the Electricity Act, relevant regulations, the Indian Electricity Grid Code, the Uttar Pradesh Electricity Grid Code, standards set by the Central Electricity Authority, and any directives issued by UPERC.
Petition No. 2102 of 2024 | Click here to read the full order.
UPERC grants transmission license to Tirwa Transmission
The Uttar Pradesh Electricity Regulatory Commission (UPERC) has approved the petition filed by Tirwa Transmission Limited for a transmission license to establish a transmission system for the construction of the 220/132/33 kV Tirwa (Kannauj) substation with associated lines. The project also includes the looping-in and looping-out (LILO) of one circuit of the 400 kV double-circuit (D/C) Shamli-Aligarh transmission line at the THDC 2×660 MW Khurja Power Plant on a build, own, operate, and transfer basis.
UPERC observed that the project aligns with the public interest by strengthening the transmission network. The commission confirmed that the bidding process complied with the request for proposal conditions, including blacklisting requirements, and that all necessary declarations and certifications were reviewed by the bid evaluation committee.
The transmission license is granted under the following conditions:
- The license will remain valid for 25 years unless revoked earlier.
- If the transmission system remains operational beyond 25 years, the licensee may apply for a 10-year extension at least two years before expiry, subject to prevailing regulations.
- The licensee is prohibited from engaging in electricity trading during the license period.
- The licensee must comply with the Electricity Act, relevant regulations, the Indian Electricity Grid Code, the Uttar Pradesh Electricity Grid Code, standards set by the Central Electricity Authority, and any directives issued by UPERC.
Petition No. 2104 of 2024 | Click here to read the full order.
CERC approves NHPC’s petition for injection of infirm power
The Central Electricity Regulatory Commission (CERC) has approved NHPC Limited’s petition seeking permission to inject infirm power beyond September 30, 2024, for the commissioning of the 800 MW (4×200 MW) Parbati-II Hydroelectric Project in Himachal Pradesh.
The commission noted that the project, initially sanctioned to be completed by September 11, 2009, has faced multiple delays due to factors such as delayed forest clearance, natural calamities, strikes, adverse geological conditions, and the COVID-19 lockdown. The project is now expected to be completed by March 2025, reflecting a 186-month delay.
CERC, exercising its powers under Regulation 19(3) of the Grid Code, has granted approval for injecting infirm power into the grid for commissioning tests, including full-load testing of all four units, until March 31, 2025. NHPC has been directed to make all efforts to commission the project by the revised deadline.
Petition No: 112/MP/2025 | Click here to read the full order.
CERC determines tariff for Powergrid’s assets in Northern Region for 2024-29
The Central Electricity Regulatory Commission (CERC) has approved Power Grid Corporation of India Limited’s (Powergrid) petition for the truing-up of transmission tariff for the 2019-24 period and the determination of transmission tariff for the 2024-29 period. The approval is for the Combined Asset, which includes the 400 kV D/C Gorakhpur-Lucknow transmission line, its associated bays, and a 30 per cent fixed series compensation (FSC) at Lucknow under the “Northern Region System Strengthening Scheme-X.”
The approved transmission charges (Rs millions) for the 2024-29 tariff period are:

Source: CERC
Petition No. 453/TT/2024 | Click here to read the full order.
CERC approves NTPC’s petition seeking review of order dated April 24, 2024
The Central Electricity Regulatory Commission (CERC) has approved NTPC Limited’s petition for a review of its order dated April 24, 2024, in Petition No. 563/GT/2020. The petition pertains to the truing-up of tariff for the Kudgi Super Thermal Power Station (2400 MW) from the commercial operation date (COD) of Unit-I.
The commission noted that certain clerical and arithmetical errors had occurred in the original order, specifically due to the non-consideration of repayment adjustments and depreciation adjustments arising from de-capitalization in the interest on loan and depreciation calculations. The de-capitalization of spare items amounting to Rs 1.98 million during the period from the COD of Unit-III to March 31, 2019, was identified as an error apparent on the face of the order and was rectified on review.
The revised tariff components (Rs million) are as follows:

Source: CERC
Petition No. 24/RP/2024 | Click here to read the full order.
CERC trues up transmission tariff for Powergrid’s assets in Southern Region
The Central Electricity Regulatory Commission (CERC) has approved Power Grid Corporation of India Limited’s (Powergrid) petition for truing up transmission tariff for the 2019-24 period under the CERC (Terms and Conditions of Tariff) Regulations, 2019. The commission also determined the transmission tariff for the 2024-29 period under the CERC (Terms and Conditions of Tariff) Regulations, 2024 for the Combined Asset in the Southern Region.
The Combined Asset includes:
- Asset-I: LILO (Loop-In Loop-Out) of both circuits of the 400 kV D/C Gazuwaka-Vijayawada Transmission Line at Vemagiri
- Asset-II: Extension of the 400/220 kV Substation at Vijayawada under System Strengthening-VI of the Southern Region Grid
The approved annual transmission charges (Rs millions) for the 2024-29 tariff period are as follows:

Source: CERC
Petition No. 376/TT/2024 | Click here to read the full order.
CERC trues up NTPC’s petition for tariff of Dadri Loni Road transmission line
The Central Electricity Regulatory Commission (CERC) has approved NTPC Limited’s petition for truing up tariff for the 2014-19 period and determining tariff for the 2019-24 period for the Dadri Loni Road 400 kV D/C dedicated transmission line associated with the National Capital Thermal Power Station, Dadri-II (980 MW).
The commission noted that as per the power purchase agreement between NTPC and Delhi discoms, the entire transmission charges and losses will be borne by Delhi discoms. Since the transmission line is considered part of the generating station, annual fixed charges will be recovered based on the generating station’s availability, without additional incentives for the transmission system’s availability.
The trued-up annual transmission charges on a pro-rata basis for 2014-19 are:
- 2014-15: Rs 9.71 million (August 2 – September 7) and Rs 110.57 million (September 8 – March 31).
- 2015-16: Rs 194.66 million.
- 2016-17: Rs 191.74 million.
- 2017-18: Rs 185.80 million.
- 2018-19: Rs 181.01 million.
The approved annual transmission charges for the 2019-24 period are:
- 2019-20: Rs 172.10 million.
- 2020-21: Rs 167.25 million.
- 2021-22: Rs 161.61 million.
- 2022-23: Rs 156.12 million.
- 2023-24: Rs 150.87 million.
Source: CERC
Petition No. 89/GT/2023 | Click here to read the full order.
CERC grants transmission license to Rajasthan IV C Power Transmission
The Central Electricity Regulatory Commission (CERC) has approved the petition filed by Rajasthan IV C Power Transmission Limited for a transmission license to establish an inter-state transmission system. The project, titled “Transmission system for evacuation of power from Rajasthan REZ Ph-IV (Part-2:5.5 GW) (Jaisalmer/Barmer Complex): Part C,” will be developed on a build, own, operate, and transfer (BOOT) basis.
CERC noted that the petitioner company meets the necessary requirements under the Act and the Transmission Licence Regulations, 2024, for granting the transmission license for this system.
The license is subject to the following conditions for its duration:
- The transmission license will remain in force for 25 years from the issue date unless revoked earlier.
- The licensee must comply with the Central Electricity Regulatory Commission (Procedure, Terms, and Conditions for Grant of Transmission Licence and Other Related Matters) Regulations, 2024, or any future amendments.
- The licensee may apply for an extension of the license term two years before the current license expires, in accordance with Regulation 9(2) of the 2024 Transmission Licence Regulations.
- The licensee is prohibited from engaging in electricity trading or entering into related contracts during the license period.
Petition No: 317/TL/2024 | Click here to read the full order.
CERC trues up transmission tariff for 2019-24 for assets in Eastern region
The Central Electricity Regulatory Commission (CERC) has approved the petition filed by Power Grid Corporation of India Limited (Powergrid) for the truing up of the transmission tariff for the 2019-24 period, as per the CERC (Terms and Conditions of Tariff) Regulations, 2019. Additionally, CERC has determined the transmission tariff for the 2024-29 period under the CERC (Terms and Conditions of Tariff) Regulations, 2024 for the asset “63 MVAR Line Reactor on 400kV Kolaghat-Rengali line at Rengali Sub-station” in the Eastern region.
The annual transmission charges for the 2024-29 tariff period for this transmission asset are as follows (Rs million):

Source: CERC
Petition No. 10/TT/2025 | Click here to read the full order.
CERC trues up transmission tariff for 2019-24 for Powergrid’s assets
The Central Electricity Regulatory Commission (CERC) has approved the petition filed by Power Grid Corporation of India Limited (Powergrid) for the truing up of the transmission tariff for the 2019-24 period under the CERC (Terms and Conditions of Tariff) Regulations, 2019. Additionally, CERC has determined the transmission tariff for the 2024-29 period under the CERC (Terms and Conditions of Tariff) Regulations, 2024 for Asset-I: the 220 kV Jallandhar-Hamirpur D/C Transmission Line along with associated bays in the Northern Region.
The annual transmission charges for the 2024-29 tariff period for this transmission asset are as follows (Rs million):

Source: CERC
Petition No: 7/TT/2025 | Click here to read the full order.
CERC approves Powergrid’s petition for truing up of transmission tariff of assets in Northern Region
The Central Electricity Regulatory Commission (CERC) has approved Power Grid Corporation of India (Powergrid)’s petition for the truing-up of transmission tariff for the 2019-24 period under the CERC (Terms and Conditions of Tariff) Regulations, 2019. Additionally, CERC has determined the transmission tariff for the 2024-29 period under the CERC (Terms and Conditions of Tariff) Regulations, 2024 for the “Combined Asset,” comprising Asset-I: 315 MVA, 400/220 kV ICT at Mandola and Asset-II: 315 MVA, 400/220 kV ICT at Ludhiana under the “Spare ICT Scheme” in the Northern Region.
The transmission charges allowed for the combined asset during the 2024-29 tariff period are as follows (Rs million):

Source: CERC
Petition No: 5/TT/2025 | Click here to read the full order.
CERC determines transmission tariff for 2024-29 for Powergrid’s assets
The Central Electricity Regulatory Commission (CERC) has approved the petition filed by Power Grid Corporation of India Limited (Powergrid) for the truing-up of transmission tariff for the 2019-24 period under the CERC (Terms and Conditions of Tariff) Regulations, 2019. Additionally, CERC has determined the transmission tariff for the 2024-29 period under the CERC (Terms and Conditions of Tariff) Regulations, 2024 for the “System Strengthening Scheme in Roorkee” in the Northern Region.
The transmission charges allowed for the asset during the 2024-29 tariff period are as follows (Rs million):

Source: CERC
Petition No. 4/TT/2025 | Click here to read the full order.
CERC trues up transmission tariff for Powergrid’s asset
The Central Electricity Regulatory Commission (CERC) has approved the petition filed by Power Grid Corporation of India Limited (Powergrid) for the truing up of the transmission tariff for the 2019-24 period and for determining the transmission tariff for the 2024-29 period for the Combined Asset. The asset includes Asset-1: 315 MVA ICT-III at Ludhiana Sub-station, and Asset-2: Bay extension work at Wagoora Sub-station under the “Northern Region System Strengthening Scheme-VII (NRSS-VII)” in the Northern Region.
The transmission charges allowed for the combined asset during the 2024-29 tariff period are as follows (Rs million):

Source: CERC
Petition No. 8/TT/2025 | Click here to read the full order.
CERC trues up transmission tariff for Powergrid’s assets in Southern region
The Central Electricity Regulatory Commission (CERC) has approved the petition filed by Power Grid Corporation of India Limited (Powergrid) for the truing up of transmission tariff for the 2019-24 period and the determination of transmission tariff for the 2024-29 period under the CERC (Terms and Conditions of Tariff) Regulations for the 400 kV D/C Kaiga-Sirsa transmission line in the Southern Region.
The transmission charges allowed for the transmission asset during the 2024-29 tariff period are as follows (Rs million):

Source: CERC
Petition No. 37/TT/2025 | Click here to read the full order.
Featured photograph is for representation only.