Juniper Green commissions 25 MW wind capacity in Gujarat

Author: PPD Team Date: August 7, 2025

Juniper Green Energy has commissioned 25 MW of wind capacity at Dev Bhumi Dwarka, Gujarat. The plant is part of its 50 MW wind power project being developed through subsidiary Juniper Green Beam Private Limited.

This milestone was reached nearly three months before the scheduled commercial operation date of October 17, 2025. The full 50 MW project is backed by a power purchase agreement with Gujarat Urja Vikas Nigam Limited (GUVNL), signed in 2023.

Juniper Green Energy’s CEO Ankush Malik said the early commissioning reflected the firm’s emphasis on timely project delivery.