Author: PPD Team Date: 08/02/2025

India's largest 765kV line, the Warora-Kurnool Project, spans 1,756 ckm connecting key regions under CERC. Commissioned by Adani Energy Solutions.

 

On October 19, 2023, Adani Energy Solutions Limited (AESL) commissioned India’s largest 765kV transmission line, the Warora-Kurnool Transmission Project, spanning 1,756 circuit kilometres (ckm). This infrastructure strengthens the Southern Region (SR) by linking it with the Western and Northern grids. Officially named the “Additional Inter-Regional AC Link for Import Into Southern Region (Warora-Warangal and Chilakaluripeta-Hyderabad-Kurnool 765kV Link) Project,” it extends across Telangana, Andhra Pradesh, and Maharashtra.

The project is regulated by the Central Electricity Regulatory Commission (CERC) and features a transformation capacity of 3,000 MVA. It operates under a 35-year Transmission Service Agreement (TSA). PFC Consulting Limited (PFCCL) served as the Bid Process Coordinator (BPC) for the project.

Project Overview: Key Components & Scale

Transmission Lines

  • Warora Pool – Warangal (New) 765 kV double-circuit (D/c) line (350 km, 666 ckm) with 240 MVAr switchable line reactors at both ends.
  • Warangal (New) – Hyderabad 765 kV D/c line (160 km, 270 ckm) with a 330 MVAr switchable line reactor at Warangal.
  • Warangal (New) – Warangal (Existing) 400 kV quad D/c line (10 km, 108 ckm).
  • Hyderabad – Kurnool 765 kV D/c line (170 km, 370 ckm) with a 240 MVAr switchable line reactor at Kurnool.
  • Warangal (New) – Chilakaluripeta 765 kV D/c line (250 km, 478 ckm) with 240 MVAr switchable line reactors at both ends.

Substation Development

A 765/400 kV substation has been established at Warangal (New) with two 1,500 MVA transformers and two 240 MVAr bus reactors.

Additional Infrastructure

A 240 MVAr switchable line reactor has been installed at the Warora Pool end for each circuit of the Warora Pool – Rajnandgaon 765 kV D/c line.

Bay Requirements

  • Six 765 kV line bays at Warangal (New).
  • Two 765/400 kV transformer bays.
  • Two 400 kV line bays.
  • Space for six future 765 kV line bays and eight future 400 kV line bays.

Initially, the project also included the Cuddapah – Hoodi 400 kV quad D/c line (200 km) with 63 MVAr switchable line reactors at both ends, along with the Line-In Line-Out (LILO) of the Kurnool – Thiruvalam 765 kV D/c line at Cuddapah. However, these were later removed from the scope.

Timeline & Key Milestones

  • March 26, 2015: PFC invited bids for consultancy services for surveying and preparing a project report using modern survey techniques. Geoinfosys Technologies and Prasad Surveyors were selected.
  • April 20, 2015: Warora-Kurnool Transmission Limited (WKTL) was incorporated as a special purpose vehicle (SPV) for the project.
  • April 23, 2015: PFC invited the initial Request for Qualification (RfQ) bids for selecting a transmission service provider (TSP).
  • September 11, 2015: PFC issued a revised RfQ for TSP selection, with bids opened on October 12, 2015. The project followed a Build, Own, Operate, and Maintain (BOOM) model, with the TSP selected through the Tariff-Based Competitive Bidding (TBCB) process.
  • November 18, 2015: Power Grid Corporation of India Limited (PGCIL), Sterlite Grid 3 Limited, Essel Infraprojects Limited (EIL), Adani Transmission Limited, and Reliance Power Transmission Limited (RPTL) were declared qualified bidders. All but RPTL submitted financial proposals.
  • July 6, 2016: PFC transferred WKTL to EIL for project implementation.
  • 2021: Adani Transmission Limited (ATL), now renamed AESL, acquired the project.

Stake Acquisition & Project Ownership

  • Sekura Energy Limited, backed by the Edelweiss Infrastructure Yield Plus (EIYP) fund, signed an agreement to acquire a stake in the project for Rs 60 billion, with the transaction to be completed post-project completion.
  • 2021: Adani Transmission acquired the project. After acquiring WKTL, Adani Energy used the Regulated Tariff Mechanism (RTM) to add a spare 80 MVAr reactor at the Warangal substation for operational flexibility.

The project’s journey culminated on October 19, 2023, when Adani Energy successfully commissioned the Warora-Kurnool Transmission line. As demand surges, this project will remain pivotal to India’s economic and environmental goals.

Featured photograph is for representation only

Similar Posts

Leave a Reply

Your email address will not be published. Required fields are marked *