Power Sector News Roundup for March 23, 2026
CEA outlines transmission roadmap for 900 GW non-fossil capacity by 2035-36 The Central Electricity Authority released a transmission plan to support over 900 GW of non-fossil fuel capacity by 2035-36. It estimates an investment of Rs. 7,93,300 crores for 1,37,500 circuit-kilometres of lines and 8,27,600 MVA of substation capacity between 2026-27 and 2035-36. The plan includes a buffer of about 115 GW above projected generation needs to account for delays. It flags risks of congestion…