Adani Power to build 1600 MW ultra-supercritical thermal power plant in Mirzapur

Adani Power is set to construct a 1600 MW (2×800 MW) greenfield ultra-supercritical thermal power plant in Mirzapur, Uttar Pradesh. This project is estimated to cost around Rs 140 billion. 

The company is expanding its thermal portfolio from 15.25 GW to 16.85 GW. The new unit will be built by Adani Power’s subsidiary, Mirzapur Thermal Energy (UP) Ltd. (MTEUPL), which Adani Power acquired from Adani Infra (India) in June. The contract for manufacturing and supplying the main plant equipment has been awarded to Bharat Heavy Electricals Ltd (BHEL). Additionally, Adani Power has initiated the development of a 1600 MW thermal power expansion project at its existing 1,370 MW plant in Raipur, Chhattisgarh. 